HomeMy WebLinkAbout11.18.2025 TC BOT Meeting Minutes FinalStorm Shelter Study for Westlake Academy
ICC 500 2020
Item J.2. Presentation from BRWmade part of the 11.18.2025 TC/BOTMeeting Minutes
OBJECTIVES
Executive Summary
Review ICC 500 Tornado Shelter Impact
Review the Westlake Campus Plan for a
Storm Shelter.
EXECUTIVE SUMMARY
Westlake Academy Campus
Arts and Science Addition will not serve as a Tornado
Shelter, as it will not accommodate the entire student
population and staff
The area under the gym is currently used during storm
events
Concept site plan for the Tornado Shelter building that will
house entire campus located within 1,000 feet of buildings
NEXT STEPS
Determine timing for building a campus Tornado Shelter that
will accommodate the entire student population and staff
Major Building Elements of a Tornado Shelter
STORM SHELTER ICC 500
•2-hour wall construction of separation wall
•Building EJ at separation wall
•Additional SF to for back-up power
generation and possible control room
•Additional SF for toilet facilities
•Premium for missile impact door and
window assemblies
ARCHITECTURAL IMPLICATIONS
•Thicker/heavier structural walls
•12” fully grouted CMU or Concrete walls
•Thicker/heavier roof systems
•Concrete over metal deck
•Increased rebar in walls and roofs
•Increased structural steel tonnage at roofs
•More robust foundations
•Additional structural testing and inspections
STRUCTURAL IMPLICATIONS
•Protection of mechanical
equipment openings
•Emergency ventilation
•Emergency lighting
•Back-up power
MEP IMPLICATIONS
ICC 500 Tornado Shelter for 1,200 | OPTIONS
WESTLAKE ACADEMY CAMPUS
GYM TORNADO SHELTER OPTION
•Competition Basketball Court | Volleyball
•1,200 Seats
•Restrooms
•Electrical / Mechanical
Additional Program Outside the Tornado Shelter
•Lobby and Concessions
•Locker Rooms
•Laundry
•Coaches Offices
25,000 GSF
GYMNASIUM STORM SHELTER
CAFETERIA TORNADO SHELTER OPTION
•Cafeteria (Holds 1,400 in a tornado event)
•Restrooms
•Electrical / Mechanical
Additional Program Outside the Tornado Shelter
•Kitchen
•Chair Storage
16,000 GSF
CAFETERIA STORM SHELTER
AUDITORIUM TORNADO SHELTER
OPTION
•Stage
•Auditorium with 350 Seats
•Control Booth
•Green Room
•Storage
•Restrooms
•Electrical / Mechanical
Additional Program Outside the Tornado Shelter
•Lobby
20,000 GSF
PERFORMING ARTS STORM SHELTER
GYM
OPTION
CAFETERIA
OPTION
AUDITORIUM
OPTION BASELINE
SIZE 25,000 GSF 17,500 GSF 20,000 GSF 8,200 GSF
SEATS 1,200 SEATS 400 SEATS EACH
PERIOD
350 SEATS -
PROS •Competition
Basketball /
Volleyball
•All-school Assembly
•Graduation
•Dedicated Practice
Gym
•Dedicated
Cafeteria
•Dedicated
Cafeteria
•Performance space -
CONS Duplicated function Limited functionality -
COST $20,000,000 $15,500,000 $20,000,000 $6,150,000
* Cost includes construction cost only, no soft costs. Date of Estimate 2025. Cost does not include relocating portables.
STORM SHELTER OPTIONS - 1,400 CAPACITY
WESTLAKE ACADEMY | EXISTING
WESTLAKE ACADEMY | POTENTIAL BUILDING SITES
EVALUATION CRITERIA
Gym located within Athletics Zone of Campus
Large building at front of campus
Good access to existing drives & parking for large events
Adequate utilities
Flat site, no trees to remove
Student access without crossing vehicular drives
Creates competition-size court
Does not require existing Dining Hall to also function as PE
Requires portables to be relocated first
Cost of relocating portables
Leasing and Graduation income opportunities
SITE A1 | GYMNASIUM
Distance from PYP
Good access to existing drives & parking for large events
Adequate utilities
Grease trap considerations
Flat site, no trees to remove
Student access without crossing vehicular drives
Duplicates existing commercial kitchen
Requires portables to be relocated first
Cost of relocating portables
Dining area 2X larger than req’d to meet shelter occupancy
SITE A2 | DINING HALL
Performing Arts located within Arts Zone of campus
Signature building near front of campus
Good access to existing drives & parking for large events
Adequate utilities
Flat site, no trees to remove
Student access without crossing vehicular drives
Provides new Performing Arts opportunities
Requires portables to be relocated first
Cost of relocating portables
SITE A3 | PERFORMING ARTS
Adjacent to upper school
Good access to existing drives & parking for large events
Adequate utilities
Flat site, no trees to remove
Student access without crossing vehicular drives
Maximizes new classrooms with multi-story building
Requires portables to be relocated first
Cost of relocating portables
SITE A4 | CLASSROOMS [NOT A STORM SHELTER]
Gym located within Athletics Zone of Campus
Large building at back of campus
Good access to existing drives
Distant from parking for large events
Adequate utilities
Flat site, no trees to remove
Students must cross vehicular drives to access
Creates competition-size court
Does not require existing Dining Hall to also function as PE
Requires new parking
Does not negatively impact existing facilities
Leasing and Graduation income opportunities
SITE B1 | GYMNASIUM
Far from main entry
Good access to existing drives
Distant from parking for large events
Adequate utilities
Grease trap considerations
Flat site, no trees to remove
Students must cross vehicular drives to access
Duplicates existing commercial kitchen
Requires new parking
Does not negatively impact existing facilities
Dining area 2X larger than req’d to meet shelter occupancy
SITE B2 | DINING HALL
Far from main entry
Good access to existing drives
Distant from parking for large events
Adequate utilities
Flat site, no trees to remove
Students must cross vehicular drives to access
Provides new Performing Arts opportunities
Requires new parking
Does not negatively impact existing facilities
SITE B3 | PERFORMING ARTS
Close proximity to PYP
Eliminates open space at heart of campus
Good access to existing drives and parking
Difficult loading access due to grades and location
Adequate utilities
Grease trap considerations
Significant topography and removal of mature trees
Students access without crossing vehicular drives
Duplicates existing commercial kitchen
Heavy construction in the heart of campus would disrupt
learning and campus life
Significant site prep and grading required
Dining area 2X larger than req’d to meet shelter occupancy
SITE C1 | DINING HALL
Close proximity to PYP
Eliminates open space at heart of campus
Good access to existing drives and parking
Adequate utilities
Significant topography and removal of mature trees
Students access without crossing vehicular drives
Provides new Performing Arts opportunities
Heavy construction in the heart of campus would disrupt
learning and campus life
Significant site prep and grading required
SITE C2 | PERFORMING ARTS
Signature building with high visibility at front of campus
Good access to existing drives and parking
Adequate utilities
Significant topography and removal of mature trees
Students must cross vehicular drives to access
Provides new Performing Arts opportunities
Does not negatively impact existing facilities
Significant site prep and grading required
SITE D1 | PERFORMING ARTS
Close proximity to PYP
Eliminates future growth opportunity for PYP classrooms
Storm Shelter at front of campus
Difficult loading access due to grades and locations
Adequate utilities
Grease trap considerations
Significant topography
Student access without crossing vehicular drives
Duplicates existing commercial kitchen function
Eliminates space for playground
Heavy construction in the heart of the campus would disrupt
learning and campus life
Significant site prep and grading required
Dining area 2X larger than req’d to meet shelter occupancy
SITE E1 | DINING HALL
Direct connection to PYP
Direct connection to PYP
Adequate utilities
Significant topography
Direct connection to PYP
Eliminates space for playground
Heavy construction in the heart of the campus would disrupt
learning and campus life
Significant site prep and grading required
SITE E2 | CLASSROOMS [NOT A STORM SHELTER]
SITE RECOMMENDATIONS
SITE A | CLASSROOMS
SITE B | GYM [STORM SHELTER]
SITE C | REMAIN AS OPEN SPACE
SITE D | PERFORMING ARTS
SITE E | CLASSROOMS
* EXPAND EXISTING DINING AS REQUIRED
[NOT AS A STORM SHELTER]
•Competition Basketball / Volleyball
•All-school Assemblies
•Graduation Ceremonies
•Dedicated Practice Gym
•Dedicated Cafeteria
•Leasing income opportunities
•Does Not Negatively Impact Future
Master Plan
GYMNASIUM STORM SHELTER BENEFITS
EXISTING
EXISTING
EXISTING PARKING
33 SPACES
155 SPACES
4 SPACES
56 SPACES
35 SPACES
PARKING
EXISTING: 283 SPACES
PROPOSED BUILDINGS
A&S
GYM
CR
D
PARKING OPPORTUNITIES
25 SPACES
PARKING
EXISTING: 283 SPACES
DEMO: 37 SPACES
ADDITIONAL: 50 SPACES
TOTAL: 296 SPACES
25 SPACES