HomeMy WebLinkAboutEntrada Plaza Mayor Timeline 2018-2019 Plaza Mayor Timeline — 2018-2019 5/21/2018: Plaza Mayor Site Plan Approved: includes 2 hotels (LQ and Marriott AC) and SUP authorizing 126 condo units. 6/21/2018: In letter dated 6/21/2018 (Attachment 1), Mehrdad Moayedi states that one of the two hotels in the Plaza Mayor will be removed with the remaining hotel to be a Curio Hilton. He also states that the amphitheater will be replaced by an indoor event center. An updated Entrada development schedule is also submitted by Mr. Moayedi (Attachment 2). 7/25/2018: The building permit application for the Plaza Mayor Hilton Curio and condominium building B is received. 8/29/2018: In a letter dated 8/29/2019 (Attachment 3), among other conditions, Centurion American (CA) is informed by Trent Petty that the change from the amphitheater to an event center will require an amendment to the approved development plan for Entrada. 11/26/2018: The SUP authorizing the Plaza Mayor Condos is amended to allow an increase of 24 condos to a maximum of 150 condos which may be included in a maximum of two of the three plaza buildings. 12/26/2018: The building permit application for Plaza Mayor condominium building A is received. 3/5/2019: CA informs Town staff that they intend to abandon the gas well and move the event center and Plaza Mayor hotel to the gas well site with the intent to convert all Plaza Mayor buildings to Condos. The same day, Town staff sends an email describing the steps needed in order to request these changes, which includes an amendment to the development plan. 5/21/2019: The Plaza Mayor condominium SUP expires per SUP Ordinance 855 conditions as the building permit applications have not been issued due to ongoing architectural, structural and design issues. The permits remain unissued. 8/27/2019: Town staff meets with CA representatives to review an incomplete submission of applications that include: moving the hotel from the Plaza Mayor to the gas well pad site; moving the event center to the gas well pad site from the restaurant row area; adding a "storage" building to the gas well pad site; adding 46 additional condo units to the Plaza Mayor to include condos in all three buildings; amending the development plan to account for said changes. The applications are not accepted due to incomplete information and documentation. Attachment '1 June 21, 2018 Mayor Laura Wheat Town of Westlake RE: Westlake Entrada Progress and Timeline Moving Forward Mayor Wheat: I would like to take this opportunity to provide you with an update on our progress in Entrada and share with you our overall project schedule as we are able to begin going vertical on the key components of this development. The level of detail and planning that is required to successfully execute the Vision of Entrada that we cast together has been challenging and time-consuming. Nothing in Entrada is typical or a detail we can 'pull-off-the-shelf.' This attention to detail started with the underground infrastructure that you cannot see. We still own the development through a related entity,and we have invested over$35,000,000 in just the infrastructure and amenities on the 80+ acre development. This is almost double what is typically required in a typical land development, and is reflected in the details and quality features such as brick pavers on all of the streets. The stone Vehicular Bridge and soon-to-be-completed covered Pedestrian Bridge crossing the Canal are iconic features that I feel add a significant level of authenticity to Entrada. Our vertical construction program for Entrada is fully-funded and escrowed for the project, and we have broken ground as soon as permits were received for each of the components other than the central Parking Garage. We will move forward with construction of the garage once the Restaurants are under construction immediately adjacent that will require the parking to be in-place. We will be bringing our best concepts from the restaurants in the Statler Hotel along with several more high-end concepts that will be a great addition to the Town of Westlake. The second set of Restaurant Row buildings will be submitted for permit approval to the Town by July 20th, along with the Chapel and Reception Hall buildings. These buildings will be constructed and open in less than a year from permit release. We recently completed our first Non-Residential building and are proud to be bringing Sendera Title to Westlake Entrada. Our second commercial building is under construction at the Retail Corner and we expect it to be open for business early next year. We have also been working with Starbucks to receive final corporate approval on their building over the last 6 months, as we have had to modify the building to meet their new requirements and also redo the Bell Tower for the StoneCoat Panels. We expect to be under construction on this third building in the Retail Corner within 60 days. I am aware that we have an approved building permit for the outdoor amphitheater, but as we have discussed,we need to upgrade that facility to an enclosed Event and Conference Center building that will be constructed in the same location. This enclosed facility will still seat up to 2500 people for larger events, but can be used for many other uses year-round and not be reliant upon the weather conditions. This building will be over 30,O00 sqft of conditioned space 1800 Valley View Lane Suite 300 Farmers Branch,TX 75234 Attachment 1 that will also be able to be partitioned into smaller spaces to accommodate multiple, simultaneous events and meetings. We will also be marketing this space as available Convention Space in conjunction with the Hotel in the Plaza Mayor. Our landmark feature within Entrada, the Plaza Mayor, received PD Site Plan approval from you and Council less than one month ago. Upon receiving that approval, we have released the Architects and Civil Engineer to move forward with full-steam ahead. As we have discussed, we are modifying the plan for Plaza Mayor to go away from the two Mid-Level Service Hotels and instead bring to Westlake a full-service hotel that matches both the Community and Entrada. We are working to bring a Curio Hilton to the Plaza Mayor, which is the same flag for the Statler Hotel in Dallas. I expect to be able to make a public announcement about this selection of Flag for the Plaza Mayor very soon, and am excited about the opportunity. Aim bridge will be our operations manager, as they have done and continue to da an excellent job with the Statler. We feel this higher level of service hotel is more fitting to the Community and also provides us with brand separation from the other hotels that are currently under way or proposed in the trade area. We will be making our first submittal for the Civil Plans for the Plaza no later than July Gm,with the first submittal far the Building Construction plans to be no later than July 27w. We will proceed with site work on the Plaza as soon as we receive Town approval. Our residential construction of the Villas and Townhomes within Entrada is progressing at a good pace. The detail and quality required to adhere to the Design Guidelines that we crafted together has pushed our price point to over $400 psf, but this is reflective of the Westlake residential market in general. We feel that these residential opportunities provide a unique quality-of-life experience and are a compliment to not only Entrada, but all of Westlake as well. Upon filing of the plat, we will also be able to let Veranda Homes get started with the three homes that she has sold. These homes will be at an even higher price point than our current Villas and Townhomes,further raising the bar on quality in Entrada. l will continue to push my Team as hard as possible to commence vertical construction on each of the projects within Entrada as permits become available. Although the intense level of detail and focus on quality have appeared to cause delays to an outside viewer, rest assured that we push every day to execute the vision we cast together for Entrada. i continue to be proud of Entrada and of our Partnership that has brought the project this far. I am looking forward to delivering a project of excellence that is unmatched. Upon it's completion, the Town of Westlake and it's surrounding communities will have one of the finest mixed-use development in North Texas. Sincerely, Mehrdad Moayedi MRW Investors LLC Manager 1800 Lovers Lane Suite 300 Farmers Branch,TX 75234 Attachment 2 f 3 E Zt ijaHi i ill fr 1 I - 1 1 ? 1 1" 1 g S c a r ig illittH I � c - I & # !yy 3 t Ypp 7 i A 1 THKRIDS NOI JM1SN(O ...0 1iMd 11o1vi Attachment 2 r 1 i it ------77.Lsz i•• . ,s,t ,,-4 --..,:-=- „....,....51.,/ i "._./ ! _. itil .10 • iiili " --- . j- -.,- u0.1.111 fii::;1.?4/4/ . i . i. ,, . . . . ,. ::._._..•.,...-.: ''l / • \ ' I..:,: •'' J . M '11• i ' i • * .1 ••. li • it _. -- ./ . ' M ' . NJ I . , 1 4=1. * 11 / • :.j O ' M ••--,...., , /- 1 • i i ,,t ..:1 _. _ '. - i _.__. .ai • . , . / M M I . 1 — .' -;:t ; • /.; , q . ., .. i = cn 1- „ . _ — /- i rr, m ITI 1:11 . 1...Tt 4 W IQ + I , ',, / .4Th f' • la lgUIL . , ,. 2 ici - I F. _:.-. ., A.• 0 ff 0 . t 7- •:,A i Ai.1 1./c... ,1 I piii 1, ini l'4. I ilip 31 , . , / • 1 dVii\I 1-1-IS -1-D]fOlid 1101\ I xj ----jV Attachment 2 1 - w 1 40, r1 aa i f111 { " ,/j) a _ I 4 H ' ,1 2n ri7 a s H xo rn NV1d 311S IN31 1tO OAVIA1 VZVzd Z-3 A 1-]A1 Attachment 2 , . --- 0 • .. ....- _ : • - = : ' 1-,-2'1 14'1 :'•-• 1 4 1;1 rst.1-,j - 1:0 • ; 1 a r:• , )1. ..,,t,...._. / .•:!: , _ ...„.. , . i:ji ' '''''rf • -•, .•s c s L,t ... , El I,: lil -g tt a tit er. i 1-1 NI Litrritt i i , i, I ..:-. •,_..,::. j_ / __ --,• ------ -,.. ----, i ,- • I ' ".. 2 . . C •:. • 1. f 1 1 1 2 ; •• : , • k I . ; j R . . . a4 I j , iti ..- , rt , '• -1) p.--7.M..-- - ' tf • i •Z I ! 1.! • - .; Inatentili '-,' ! I _ . ,. . . , .. .. . , .,... : 777 7777:1; 4 , • : ? ,.. . I=;. '. .1 ... - '7 • e ' Z / 41j • 1, , t • : 2 gr, - : ' 0, •• ... ,i I i ii '•-. .- ./ ; ' ' .1.! ' l . iti I, '. /.ex rz Et , ..•tz --i- .6.,Q -...---,....'.-I . _..... = 'S.:.- ' ""!". ...' ,! r.'- .... ' ,, 7— - _-., •'- • _____ r_ commioN.wwand ../., RESTAMANT ROW - -.31 - , ' ' ..,' '.,., , I, ,',..„;• .i-: , _ PD srrE PLAN PACISAGE .!.6. :11111 lini..;iti o --. , , -•.'' " • RESTAURANT ROW 2 ?.fjf Illigq, 71 AT WESTLAKE ENTRADA #7^,- MENG i NA ACI7ES / tl terail.G._ - VA 7104C?nleinkli=awn. NV 1(1 LI IS •I \ 111110 A\( ) i -1•N\r111V-1 .qi (c-.-I \\ le Attachment 2 ... ill igi :d- ,: ,Iirt !II Irk * - A . \i.^... !i • I i Il ` r. ,Z ' .f-- _ ellit ..E r • Op. . .. .. 'e► i I -i - ..)-* aali: :,it li. • � 1 a . lie CI:i - , .,. . ,. a— 1V ' y _ - i. \ 4 ... r' 't 11- : 4*'; i L' ,) lir frk m 'f� -1r i fili i. iii ?. •Palritt.s eN 7:j > t S9NI11:10NJ)[ fl1011 1N\'Z111V.S]H £-3A\ _.31 Attachment 2 11 { r -�f 1 . r r _,\_ - e. It i7. !• _ y R-_ .. f am+- C t y r�, �� Lef f• r-. �. \ : icli , (......j......_ • • . - ( . ,— , A i 4 5 5.!.4 .. ... In 1.. _ .__1 • :'''- .. . . F. 4 .-.----'-` '. : - \ ai • ei ,a gy ; 1 x ' Yr iI [. - � Vll 7.H�'r► - - . F + 'r 1 m f I. • '. VAVI$I17A P!7 SITE PLAN PACKAGE - ... f '- ;-i 7 ` 1 DAVIS/114 CORNER 0 ysJ :f 1:i C.) _1 ! AT WESTLAKE ENTRADA D ?;� i ` :E i L 1 bcwc I 7....7 Ap S z `I' - , ,- I L I ll 1 law ar Wean rxe I...WI. rn'1 J , NIV1d 31IS 1N321111tt 9I\Iia/WWI 1I VI]'j 9- IA1 ____V Attachment 2 ramie _ ... ,F ...-- Ird st , 4 1 - . Atcr 7 ' . Al . _~ . Pit, t' . -.114, . 1 , S'.1 :* , J qff, 0 • - t't 4i- : I I • I ' 4. eili:i , •‘. 1 P., • , :' - , r .* •, •-.0 114 . , . 411. i i ti•P f L .r.. . • 1 -1Pli .4 2= . . . . I. -. mu • • ,. r 4 p •4/4 if 15.4 ' .4.-•611Eismiligi . . , fr , NW Ili CM .. 'vi:f, 0 X. '. ,- M Z rriV) ' > > m & > t S9r\111134:11\1111 1 1N111(-0 '11V-1.-:1ll 9-3M ___Ne Attachment 2 cr Criq Cd r) NIV`ld IJ S IM 1l111 J 1111 l\13D LN iIi\3 +-- L \ _Ncl Attachment 2 • - • �' - - �- ,ti . ,....e.:A : r; . '‘, 5' r • • / / IF, 201c -% Yp.. iIa. 4 i ' i i i sp.--2,....- e F • RECEPTION HALL AND CHAPEL f '+v F - PO SITE PLAN PAC1[AGE 7 ill iw 0 ----"^ • I '••- - RECEPTION HALL/CHAPEL i t, t !F rr ,_ t , , _ I AT WESTLAKE ENTRADA I r 1i - ip!_ii!r[i If s i X I { i Ntle.S OTT MACS f Z ] ,1` TOM 9FY+LLTWE 1 PNIe WIRY*PEAS Q ` NV1d :ills J-NThhl.II70 11dVI-iO 9NIaCI]M L-]A \ le Attachment 2 ,,. .11kfli is. _ 5 • ti C'11-'4. • I A L lk fit r., _ ., r iti . t ;'4. ' . i , .-4, f R , f .1 adz , Attachment 3 p&A Mehrdad Moayedi Centurion American 1800 Valley View Lane,Suite 300 Farmers Branch TX, 75234 August 29,2018 Dear Mr. Moayedi: The Town of Westlake has asked Petty&Associates,Inc.to help facilitate your request to amend the PD Site Plan for the Plaza Mayor portion of Entrada as expressed in Ordinance No.854. We look forward to working with you,and your team on that process. As you are acutely aware,the Town places incredible importance on the unique features of Entrada that will distinguish it among all other mixed-use developments in the country. The Town believes the architectural and design uniqueness of Entrada is the sole characteristic that will nourish and sustain its success and allow it to weather market changes in the intensely competitive mixed-use marketplace of north Texas. It is that uniqueness the Town is relying on to attract desirable tenants and create synergy among uses that will make Entrada the premier people-place of the metroplex. The Town has retained P&A to facilitate your request in a manner that supports this vision for Entrada and accelerates the development trajectory on every level. In order to accomplish that, the Town needs your help and cooperation to supply accurate and thorough information on several fronts. Zoning Ordinance Amendment As you know, the multiple regulatory instruments of the Town governing Entrada require the Town to perform specific due diligence on requests associated with changes in land use and construction timing. Specifically,Ordinance No.854 related to the Plaza Mayor states:All structures of the Entrada Plaza Mayor (Hotels, Condominiums, and Garages) must be assembled at the same time. A Certificate of Occupancy will not be issued for any one building unless all other buildings are able to receive a Certificate of Occupancy in unison. You have requested that the Town amend this Ordinance to require that only two of the three structures defining the Plaza Mayor be constructed at this time. In addition, you have requested that the Amphitheatre use be changed to an Event Center use. The Amphitheatre use is prescribed in Ordinance No. 720 and as such, must be amended by the City Council to allow the Event Center use. In order to accomplish your desire objectives, please submit the following: Deliverable#1 a. Please submit a formal written request to the Town describing your request to amend Ordinance No. 854 to accommodate your request to eliminate the requirement that the three building be built simultaneously. b. Please submit a formal written request to the Town describing your request to amend Ordinance No. 720 to accommodate the request to change the Amphitheatre use to an Event Center use and describe the Event Center use. Attachment 3 Financial Status It is the Town's understanding that you are utilizing EB 5 funds to construct Entrada. You have publicly indicated that changing the Amphitheatre use to an Event Center use will require additional capital funds beyond what the EB 5 funds will cover. At this stage of the project and given the multiple delays the project has encountered,the capital sources and uses of funds for Entrada is of vital concern to the Town. In order for the Town to consider requests that ultimately impact the overall Entrada proforma and the utilization of public dollars for this project, the Town would like a better and more detailed understanding of the capital available to complete this project. Deliverable#2 a. Please provide a copy of the EB 5 loan documentation relative to Westlake Entrada. b. Please provide an EB 5 balance sheet validated by the EB 5 Trustee that illustrates the dollars spent to date on Entrada and the payee(s)for those funds as well as the available funds remaining for the project and the current budget reflecting the intended expenditure of the remaining balance. c. Please verify the dollars required to be escrowed under the Reimbursement Agreement for Project B (Parking Garage) after February 2018, have been deposited in compliance with Reimbursement Agreement dated January 2018. Town Development Priorities Centurion American recently submitted an updated proposed construction schedule for the Entrada project. The Town Council wants assurance that the developer's schedule of construction and the corresponding available capital for the iconic architectural features of Entrada is consistent with the Town's priorities. The list below should not be viewed to the exclusion of other planned uses in Entrada like the hotel, restaurants, parking garage, etc., rather it is intended to convey the Town's emphasis on the urgent completion of these significant elements in this priority order. 1. Completed Plaza Mayor 2. Bell Tower 3. Pedestrian Bridge 4. Wedding Chapel 5. Public Parking Garage(Part B Assessments) Deliverable#3 Please review the recently submitted development schedule and describe how, if the Town chooses to allow the Plaza Mayor to proceed with only two buildings at this time, the schedule can be accelerated with particular emphasis on completing the Council's priorities above. Please understand that quality and compliance with the Entrada vision are implicit in reviewing your amended schedule. All three of the Deliverables cited above are critical pieces of information the Town has instructed to be collect prior to the council's formal consideration of your request to amend Ordinance No. 854. The Town's consideration of your request will be viewed in light of your agreement to provide the Deliverables in the detail expressed above.The Town appreciates the effort you and your team have made to make Entrada a special development. However,there is a very clear direction from the Council that any concessions to the current regulatory Ordinances will depend upon your provision of the information requested and your continued adherence to the quality standards established for Entrada. It is clearly in everyone's best interest to expedite this project at every opportunity while the capital markets and tenant attitudes are still conducive to an aggressive schedule. We look forward to assisting you and the Town in this important endeavor. Attachment 3 Sincerely, 3._.7,---" _ Trent Petty President Cc: Mayor and Town Council Toni Brymer,Town Manager L.Stanton Lowry,Town Attorney Kelly Edwards, Town Secretary Jarrod Greenwood,Assistant to the Town Manager Ron Ruthven, Director of Planning and Development