HomeMy WebLinkAboutCore and Town Change Order Jan 2019
10625 N County Rd
Frisco, TX 75033
Ph: 972-668-9340
PENDING CHANGE ORDER No. 90009
To: Troy Meyer From: Darrell Lindsay
Town of Westlake Date: 1/25/2019
Project: Westlake Fire Station
Ph: 817-829-6974
Below is the detail for our proposal to complete the following changes in contract work:
PDU Upgrade
Mall ceiling refinishing
Additional low voltage cabling
BDA system addition
Alert system addition
Proposed Scope of Work: Provide the above items that were not apart of the approved GMP.
The prices below are valid until 2/15/2019
Vendor Name Description Amount
PDU Upgrade $20,174.00
Mall ceiling refinishing $10,500.00
Additional low voltage cabeling $40,600.00
BDA system Addition $28,537.00
Alert system addition $8,134.00
Payment and Performance bond at .90 % $971.00
Builders Risk Insurance at .11% $119.00
General Liability and Umbrella Insurance at .89% $961.00
Sub Total $107,945.00
Fee Included
Total $109,996.00
Contractor reserves the right to request additional time should the actual completion schedule be impacted by
these changes.
Approved By:
Town Manager Date
Town of Westlake
Resolution 19-07