April 22,2013
Project Timeline
Winter, 2010-11 - PMSI firm was hired, Facilities planning / growth
model - Peter Hays Plan
March, 2012 - Bennett-Benner-Pettit - Master Plan, Building Cost,
SDS Growth module
November, 2012 - Westlake Academy Master Plan was adopted by both
Town Council & Board of Trustees
January, 2013 - Bennett-Benner-Pettit firm was hired to provide
architectural services for the phase I WA expansion
February, 2013 - Program Team formed
Project Timeline
March, 2013 - Westlake Academy Development Plan approved by Council and presented in a report to the Planning & Zoning Commission
March, 2013 - RFQ for a Contractor Manager at Risk
April, 2013
Steele & Freeman is the proposed CM at Risk contractor for the project
The Issuer's contractual obligations bonds $8.5M
BB & P and Steele & Freeman kick off meeting- Working on cost of project
Staff meet with BB & P on articulations of buildings
Staff recommends to the Town Council is to start negotiation the GMP with Steele & Freeman
Next Steps
Estimated Timelines
May - Construction documents completed
June - Ground breaking event
June - GMP present to TC
July - Construction starts
Summer 2014 - Move into building
Fall 2014 - Open building on first day of school