Loading...
HomeMy WebLinkAboutWestlake Academy Phase I Expansion 10-28-13Town Council Workshop October 28, 2013 60 day Project Timeline November Place slab Multi-Purpose Hall Underground services Field House Start grade beams Field House Begin structural steel Secondary December Level 2 decking Secondary  Place slab field House Level 3 decking Secondary January Top out Secondary building Place level slab Secondary building Total of 4 rain days 8th and 9th graders art classes Secondary Building Grade Beams Forms Secondary Multi-Purpose Hall Multi-Purpose Hall