Loading...
HomeMy WebLinkAboutWestlake Academy Phase I Expansion presentationTown Council Workshop August 26 ,2013 60 day Project Timeline August Water & sewer completed Earthwork starts on building pad sites FF & E package review by staff Town Council review amendment GMP September Complete earthwork Begin drilling piers October Gas and power  Begin structural steel erection  Place first floor slab Secondary Before & After Pictures Keller ISD Football Stadium – Before Keller ISD Football Stadium - After Steele & Freeman Office WA Gym Building Project Cost Total Project Cost (Base Bid) $10,983,991 Water heaters Name brands Concrete cost Stairs Lighting package Number and size of piers Plumbing package /crawl space Total Value Engineered Cost $10,563,720 Guaranteed Maximum Price Base bid - plaster exterior finish $8,578,694 EIFS vs. plaster $(158,189) EIFS (High Impact north side of Field House) $(153,880) EIFS (All High Impact) $(105,248) Lightning protection (All buildings) $ 69,484 Electric flush valves $ 29,086 GMP Staff Recommends Base bid- EIFS exterior finish $8,542,930 EIFS (All High Impact) $(105,248) Lightning protection (All buildings) $ 69,484 Total GMP $8,542,930 Total Project Cost $10,527,956 Next Steps Recommend Approval of GMP $8,542,930 Total Cost of the project $10,527,956 Note: If GMP is not approved, will results in project delays