HomeMy WebLinkAboutWestlake Academy Phase I Expansion 06-03-13Town Council Workshop June 3 ,2013 90 day Project Timeline May – Civil plans submitted to Town S & F start civil bid package Plans review contractor drawings Structural plans 70% June – Review Multi-Propose Hall Options Ground Breaking Review contractor drawings for bid package Civil bid review Amendment #1 issued by CMR for approval by Town Council June 17th July – GMP bid packages Site utilities and earthwork starts Project bid review Value engineering (if needed) August – Town Council approves GMP Pier drilling Multi-Purpose Hall Pros & Cons Handout WESTLAKE ACADEMY MULTIPURPOSE HALL OPTION 1 WESTLAKE ACADEMY MULTIPURPOSE HALL OPTION 2 WESTLAKE ACADEMY MULTIPURPOSE HALL OPTION 1 WESTLAKE ACADEMY MULTIPURPOSE HALL OPTION 2 WESTLAKE ACADEMY MULTIPURPOSE HALL OPTION 2 WESTLAKE ACADEMY MULTIPURPOSE HALL OPTION 2 Considerations Select option I or II for Multi-Propose Hall Option I Increase roof height – No delay in the project Cost $190,000 Option II Increase Sq. Ft. by 1,730 – Possible 30 delay Some PYP sections eating in classrooms PE would be held in classrooms Cost $500,000 If Council delays decision until June 17th Delay in completing drawings Impacts timing of bid package Possible delay opening to 30 to 45 days Provide practice facilities for PYP sports Everyone could play(A,B,C and D teams) Next Step Selecting Option I or II?