HomeMy WebLinkAboutWestlake Academy Phase I Expansion 06-03-13Town Council Workshop
June 3 ,2013
90 day Project Timeline
May – Civil plans submitted to Town
S & F start civil bid package
Plans review contractor drawings
Structural plans 70%
June – Review Multi-Propose Hall Options
Ground Breaking
Review contractor drawings for bid package
Civil bid review
Amendment #1 issued by CMR for approval by Town Council June 17th
July – GMP bid packages
Site utilities and earthwork starts
Project bid review
Value engineering (if needed)
August – Town Council approves GMP
Pier drilling
Multi-Purpose Hall
Pros & Cons
Handout
WESTLAKE ACADEMY
MULTIPURPOSE HALL OPTION 1
WESTLAKE ACADEMY
MULTIPURPOSE HALL OPTION 2
WESTLAKE ACADEMY
MULTIPURPOSE HALL OPTION 1
WESTLAKE ACADEMY
MULTIPURPOSE HALL OPTION 2
WESTLAKE ACADEMY
MULTIPURPOSE HALL OPTION 2
WESTLAKE ACADEMY
MULTIPURPOSE HALL OPTION 2
Considerations
Select option I or II for Multi-Propose Hall
Option I Increase roof height – No delay in the project
Cost $190,000
Option II Increase Sq. Ft. by 1,730 –
Possible 30 delay
Some PYP sections eating in classrooms
PE would be held in classrooms
Cost $500,000
If Council delays decision until June 17th
Delay in completing drawings
Impacts timing of bid package
Possible delay opening to 30 to 45 days
Provide practice facilities for PYP sports
Everyone could play(A,B,C and D teams)
Next Step
Selecting Option I or II?