MILESTONES
December -Final sale of $9.2M CO’s
January 2017 -Town Council approved Core Construction as the Construction
Manager at Risk
February-March –Town Council directed staff to increase scope and funding to
ensure iconic look
April -Town Council directed staff to proceed with the increase of the project
budget to $2.76M
November -Groundbreaking Ceremony
January 2019 -Estimated completion of construction
February 2019 -Move In/Open House
Project Budget
Total Project Budget $11.9M
Consultants/engineering $ 712,779
Construction GMP 9,737,281
Design 729,500
Owner FF&E 270,440
*Owner Contingency 4%450,000
Total Project Cost $11,900,000
Add Alternates
Lighting package, fencing, air compressor system, boulders, wooden trellis, signage, auto
gate, large bay fans, SCBA filling station,size of the retaining
walls and generator.
Items moved to add Alternates:
Wooden trellis $70,000.00
Outdoor gas grill $7,700.00
Exterior Signs $20,000.00
Electrical gate $28,300.00
Fueling Station $57,327.00
Total $183,327.00
Sign Design
Site Photos
Site Photos
FIRE STATION COST INCREASE
10% to 15% increase in fire station construction in the past 3 years
Increase $880,000 to $1.2M
Today basic fire station square feet cost $360 to $375
2013 -2015 sq. ft. cost range from $264 to $330
Westlake characteristic
Proposed Westlake sq. ft. cost $413
Proposed Westlake elements -building & site $700,000
Includes, building exterior, site work, water feature and landscaping
Add Alternates may include,
Fueling system $64,260
Hose tower $321,302
Water feature $250,000