Loading...
HomeMy WebLinkAboutWestlake Academy Phase I Expansion 08-12-13Town Council Workshop August 12, 2013 60 day Project Timeline August Portable building completed this week Approve GMP on August 26th Town Council Meeting Sewer line completed, Water start this week Construction fence installed this week Atmos - gas and Tri-County- Power September Begin Drilled Piers October Begin Structural Steel Place First Floor Slab Secondary  August 2014 opening Construction Map WA Phase I Expansion Update  Site Plan Each building will be fenced  Staging area Delivery – 9am -2pm Traffic flow and west parking lot Security Background checks Badges Parking EIFS – Exterior Insulation Finished Systems Next steps Plaster or EIFS?