HomeMy WebLinkAboutWestlake Academy Phase I Expansion 08-12-13Town Council Workshop
August 12, 2013
60 day Project Timeline
August
Portable building completed this week
Approve GMP on August 26th Town Council Meeting
Sewer line completed, Water start this week
Construction fence installed this week
Atmos - gas and Tri-County- Power
September
Begin Drilled Piers
October
Begin Structural Steel
Place First Floor Slab Secondary
August 2014 opening
Construction Map
WA Phase I Expansion Update
Site Plan
Each building will be fenced
Staging area
Delivery – 9am -2pm
Traffic flow and west parking lot
Security
Background checks
Badges
Parking
EIFS – Exterior Insulation Finished Systems
Next steps
Plaster or EIFS?