HomeMy WebLinkAboutWestlake Academy Outdoor Learning Center Green Scape Presentation 02-05-18Westlake Academy Outdoor Learning Station Phase II FEBRUARY 5, 2018 Site Plan Math & Sciences Plaza Bid Results Green Scape $231,896.20 / $171,799 Fort Worth Civil Contractor $302,043.00 Hightland Landscaping $13,470.00(Only Landscaping) Brick & Stone Master $19,350.00(Only Stone work) Bid Reduction Special Concrete-Reduced size $30,745 Grading $2,000 Stone walls $5,680 Slab edge wall $12,036 Irrigation $9,636 Total Reduction $60,097 Add Alternates Requested by Foundation and Teachers The following items will be considered and founded by the foundation, Trail markers $8,058 Vertical ruler $9,400 Terraced seating $12,248 Next Steps February 5th -Staff recommends approval con Green Scape Contract February 12 -Finalize contractor documents February 21 -Construction start May 15 -Estimated project Completed followed by ribbon cutting