HomeMy WebLinkAboutWestlake Academy Outdoor Learning Center Green Scape Presentation 02-05-18Westlake Academy
Outdoor Learning
Station Phase II
FEBRUARY 5, 2018
Site Plan
Math & Sciences Plaza
Bid Results
Green Scape $231,896.20 / $171,799
Fort Worth Civil Contractor $302,043.00
Hightland Landscaping $13,470.00(Only Landscaping)
Brick & Stone Master $19,350.00(Only Stone work)
Bid Reduction
Special Concrete-Reduced size $30,745
Grading $2,000
Stone walls $5,680
Slab edge wall $12,036
Irrigation $9,636
Total Reduction $60,097
Add Alternates Requested by
Foundation and Teachers
The following items will be considered and founded
by the foundation,
Trail markers $8,058
Vertical ruler $9,400
Terraced seating $12,248
Next Steps
February 5th -Staff recommends approval con
Green Scape Contract
February 12 -Finalize contractor documents
February 21 -Construction start
May 15 -Estimated project Completed followed
by ribbon cutting