HomeMy WebLinkAboutRes 18-04 Authorizing the Town Manager to enter into an agreement with Terracon for Fire and EMS House 1 TOWN OF WESTLAKE
RESOLUTION NO. 18-04
A RESOLUTION OF THE TOWN COUNCIL AUTHORIZING THE TOWN MANAGER
TO ENTER INTO AN AGREEEMENT WITH TERRACON CONSULTION ENGINEERS
FOR CONSTRUCTION MATERIALS TESTING AND OBSERVATION SERVICES FOR
THE CONSTRUCTION OF THE WESTLAKE FIRE-EMS FIRE HOUSE 1 PROJECT
AND AUTHORIZE TOWN STAFF TO MAKE FUNDING CHANGES NOT TO EXCEED
$25,000 ON THIS PROJECT.
WHEREAS, the Town of Westlake will be constructing a new 18,000 square foot Fire-
EMS Fire House 1; and,
WHEREAS, the Town's current Fire-EMS department has been operating out of a
temporary facility for the past 12 years; and,
WHEREAS,the Council desires to provide stakeholders with an iconic looking fire station
that serves the emergency services needs of the community and meets the community building
standards; and,
WHEREAS, the staff recommends Terracon Consulting Engineers provide the
construction materials testing and observation services for the construction of the Fire—EMS Fire
House 1 project; and,
WHEREAS, the Town Council finds that the passage of this Resolution is in the best
interest of the citizens of Westlake.
NOW, THEREFORE,BE IT RESOLVED BY THE TOWN COUNCIL OF THE TOWN
OF WESTLAKE, TEXAS:
SECTION 1: That, all matters stated in the Recitals hereinabove are found to be true and
correct and are incorporated herein by reference as if copied in their entirety.
SECTION 2: That the Town of Westlake Town Council does hereby authorize the Town
Manager to enter into an agreement with Terracon Consulting Engineers for construction materials
testing and observation services for the Fire—EMS House 1 project attached as Exhibit A; and
authorizes town staff to make funding changes not to exceed $25,000 on this project.
SECTION 3: If any portion of this Resolution shall, for any reason, be declared invalid
by any court of competent jurisdiction, such invalidity shall not affect the remaining provisions
hereof and the Council hereby determines that it would have adopted this Resolution without the
invalid provision.
Resolution 18-04
Page 1 of 2
SECTION 4: That this resolution shall become effective from and after its date of
passage.
PASSED AND APPROVED ON THIS 29th DAY OF JANUARY 2018.
ATTEST: ., f/1 , _,�, �
Laura L. Wheat, Mayor
LQ-L(-)ewe)w.
Kelly Edw s, Town Secretaryy Thomas E. Bryme ; own Manager
O T
APPROVE AS TO ORM: �• h� '.
-E'
L(. Sfanton Ko Attorney
`�'
Resolution 18-04
Page 2 of 2
Irerracon
December 7, 2017
Town of Westlake
Attn.: Mr. Tom Brymer
1500 Solana Boulevard, Building 7, Suite 7200
Westlake, Texas 75262
Subject: Proposal for Construction Materials Testing and Observation Services
Town of Westlake Fire Station
2000 Dove Road, Westlake, Texas 75262
Terracon Proposal No.: P95171268
Dear Mr. Brymer:
Terracon Consultants, Inc. (Terracon) is pleased to submit this proposal to provide construction
materials testing, observation services, or special inspection services for the above referenced
project as required. We are presenting this proposal to confirm our understanding of the
services to be performed for this project, to obtain written authorization to provide these
services, and to present the estimated fee to provide these services. The following sections
outline our understating of the project and provide a description of the tasks to be performed.
A) PROJECT INFORMATION
The site is located at 2000 Dove Road Westlake, Texas. This project will consist of two new
buildings on shallow foundations. One building is the proposed fire station with a building
footprint of 12,279 square feet, and proposed new administrative building with a footprint of
4,606 square feet. Both buildings will consist of structural masonry, structural steel, and wood
framing. There will also be site associated utilities and paving.
Terracon was provided with the following construction documents for preparation of this
proposal:
• Preliminary Civil Drawings by Pacheco Koch dated 09/11/2017
• Preliminary Structural Drawings by BRW Architects dated 09/11/2017
• Specifications dated 09/11/2017
• Geotechnical Report by Terracon dated 10/06/2016
B) SCOPE OF SERVICES
Based on our review and understanding of the documents listed above, Terracon proposes the
following scope of services:
Terracon Consultants, Inc. 2501 East Loop 820 North Fort Worth, Texas 76118
P [817] 268-8600 F [817]268-8602 terracon.com Resolution 18-04
Proposal for Construction Materials Testing Services Irerracon
Town of Westlake Fire Station
2000 Dove Road,Westlake,Texas 76262
December 7, 2017 Terracon Proposal No. P95171268
Earthwork Observations and Testing:
1. Sample materials to be used as building fills, utility trench backfill, wall backfill,
general fill, and pavement subgrades. Prepare and test the samples for
Atterberg Limits (ASTM D4318), Minus #200 Sieve (ASTM D1140), and moisture-
density relationship (ASTM D698).
2. Observe proofrolling operations of the building pad and paving subgrades; and
perform density tests of the building fills, utility trench backfill, wall backfill, general
fill, and pavement subgrades using the nuclear method (ASTM D6938) to
determine the moisture content and percent compaction of the soil materials.
Cast-in-Place Concrete Observations and Testing:
1. Sample and test the fresh concrete for each mix, Perform tests for slump, air
content, ambient and concrete temperatures, and unit weight; and cast test
specimens (ASTM C172, C31, C143, C231, C1064, C138). Terracon
understands that the contractor will be responsible for maintaining the initial field
curing temperature of the concrete test specimens.
2. We have assumed the concrete will be sampled at a frequency of one set of five
test cylinders every 100 cubic yards or fraction thereof per mix per day for all
structural concrete. Terracon requests that a copy of the approved mix design(s)
be provided to us prior to placement of the concrete.
3. Perform compressive strength tests of concrete test cylinders cast in the field
(ASTM C31, C39). Five 4" x 8" concrete cylinders will be prepared for structural
concrete having nominal maximum size aggregate of 1 inch or less. Four 6" x
12" concrete cylinders per set will be prepared for concrete having a nominal
maximum size aggregate of greater than 1 inch. When 6" x 12" cylinders are
prepared, one cylinder will be tested at 7 days, two cylinders will be tested at 28
days and one cylinder will be tested at 56 days or at an age requested by others.
4. When 4" x 8" cylinders are prepared, one cylinder will be tested at 7 days, three
cylinders will be tested at 28 days, and one cylinder will be tested at 56 days or
at an age requested by others.
Reinforcing Steel Observation and Testing:
1. Verify the size, number and placement of reinforcing steel prior to placement of
2. Terracon recommends scheduling a minimum of 24 hours prior to concrete
placement.
Masonry Observations and Testing:
1. Provide a qualified technician for periodic field observation during load-bearing
CMU wall construction.
Responsive Resourceful Reliable P a g e 12
Resolution 18-04
Proposal for Construction Materials Testing Services Irerracon
Town of Westlake Fire Station
2000 Dove Road,Westlake, Texas 76262
December 7, 2017 Terracon Proposal No. P95171268
2. Sample mortar for compressive strength testing. (6 mortar cubes 2"x2"x2" per
5,000 SF wall area)
3. Sample grout for compressive strength testing. (4 grout prisms 3"x3"x6" per 5,000
SF wall area)
Structural Steel Observations and Testing:
1. Terracon recommends that the general contractor schedule a pre-erection
meeting to discuss the erection sequence, review welding and bolting
requirements and to review welder certification records.
2. Provide a Certified Welding Inspector (CWI) in the field to visually observe
accessible field bolted/welded connections in accordance with applicable AISC
and AWS standards.
3. Perform visual inspections of elevated metal decking for placement including
overlap, fastener spacing, supports at openings and penetrations, and puddle
welds pattern, size and quality.
4. Terracon will observe any shear studs in association with composite concrete
decks for number, pattern, and bond.
5. Utilize an Ultrasonic Flaw detector to determine the quality of complete joint
penetration welds such as moment connections or splice connections. If the base
material has a thickness of 5/16" or greater, Terracon recommends that those
welds be tested by the Ultrasonic Method in accordance with AWS D1.1.
6. Perform visual inspections of 100% of completed accessible welds to verify that
the welds meet the visual acceptance criteria of AWS D1.1.
Project Management/ Administration:
A project manager will be assigned to the project to review the daily activity and
assist in scheduling the work. Field and laboratory tests will be reviewed prior to
submittal. The project manager will be responsible for maintaining the project
budget and will oversee the preparation of the final report.
Special Inspections Letter:
Upon completion of our services, a special inspection letter will be prepared, if
requested. The letter will list services Terracon performed and if our results and/
or observation were in compliance.
Responsive Resourceful Reliable P a g e l 3,,
Resolution 18-04
Proposal for Construction Materials Testing Services Irerracon
Town of Westlake Fire Station
2000 Dove Road,Westlake,Texas 76262
December 7,2017 Terracon Proposal No. P95171268
C) REPORTING
Results of field tests will be submitted verbally to available personnel at the site. Written reports
of field tests and observations will be distributed within five business days. Test reports will be
distributed via electronic distribution unless otherwise requested. Please provide Terracon with
a report distribution list prior to the beginning of the project. The list should include the company
name, address, contact person name, phone number, and e-mail address for each person.
Our reported test locations will typically be estimated by pacing distances and approximating
angles and elevations from local control data (staking and layout lines) provided by others on
site. The accuracy of our locations will be dependent on the accuracy, availability and
frequency of the control points provided by the client and/ or contractor.
D) SCHEDULING
Field testing services will be provided on an "as requested" basis when scheduled by your
representative. A minimum of 24-hour notice is required to properly schedule our services. To
schedule our services please contact our dispatcher at (817) 591-4907. The dispatch office
hours are from 7:00 a.m. to 5:00 p.m. Messages left after business hours will be checked the
following business day. Terracon shall not be held responsible for tests not performed as a
result of a failure to schedule our services or any subsequent damage caused as a result of'a
lack of testing. Terracon recommends that a copy of this proposal be provided to the general
contractor so they understand our scope of services and schedule us accordingly. Please note
that the number of tests and trips described in the Scope of Services does not constitute a
minimum or maximum number of tests or trips that may be required for this project.
It is the responsibility of your representative to schedule retests in a like manner to scheduling
our original services. Terracon shall not be held responsible for retests not performed as a
result of a failure to schedule our services or any subsequent damage caused as a result of a
lack of retesting.
If you would like us to perform additional work, please contact us and we will issue a short
Supplement to Agreement form, or Supplemental Proposal, that outlines the additional work to
be performed and associated fees. To authorize us to begin additional work, you simply return
a signed copy of the Supplemental agreement.
Responsive Resourceful ; Reliable F a g e 14
Resolution 18-04
Proposal for Construction Materials Testing Services Irerracon
Town of Westlake Fire Station
2000 Dove Road,Westlake,Texas 76262
December 7, 2017 Terracon Proposal No. P95171268
E) COMPENSATION
Based on the project information available for our review, we propose an estimated cost of
$49,404.00. Services provided will be based on the unit rates included in the attached Budget
Estimate. Please note that this is only a budget estimate and not a not-to-exceed price. Many
factors beyond our control, such as weather and the contractor's schedule, will dictate the final
fee for our services.
For services provided on an "as requested" basis, overtime is defined as all hours in excess of
eight hours per day or outside of the normal hours of 7:00 a.m. to 5:00 p.m. Monday through
Friday, and all hours worked on weekends and holidays. Overtime rates will be 1.5 times the
hourly rate quoted. A four hour minimum charge is applicable to all trips made portal to portal
(our laboratory) to provide our testing, observation and consulting services. A two hour
minimum charge is applicable for trips to the project site for sample pickup only. All labor,
equipment and transportation charges are billed on a portal to portal basis from our office.
You will be invoiced on a monthly basis for services actually performed and/or as authorized or
requested by you or your designated representative. Terracon's total invoice fee is due within
thirty days following final receipt of invoice. Quantities and costs associated with re-tests,
cancellations and stand-by time are not included in our estimated fee.
F) SITE ACCESS AND SAFETY
Client shall secure all necessary site related approvals, permits, licenses, and consents
necessary to commence and complete the services and will execute any necessary site access
agreement. Terracon will be responsible for supervision and site safety measures for its own
employees, but shall not be responsible for the supervision or health and safety precautions for
any third parties, including Client's contractors, subcontractors, or other parties present at the
site.
G) TESTING AND OBSERVATION
Client understands that testing and observation are discrete sampling procedures, and that such
procedures indicate conditions only at the depths, locations, and times the procedures were
performed. Terracon will provide test results and opinions based on tests and field observations
only for the work tested. Client understands that testing and observation are not continuous or
exhaustive, and are conducted to reduce — not eliminate - project risk. Client agrees to the level
or amount of testing performed and the associated risk. Client is responsible (even if delegated
to contractor)for notifying and scheduling Terracon so Terracon can perform these services.
Responsive ii Resourceful Reliable P a g e 15
Resolution 18-04
Proposal for Construction Materials Testing Services Irerracon
Town of Westlake Fire Station
2000 Dove Road,Westlake, Texas 76262
December 7,2017 Terracon Proposal No. P95171268
Terracon shall not be responsible for the quality and completeness of Client's contractor's work
or their adherence to the project documents, and Terracon's performance of testing and
observation services shall not relieve contractor in any way from its responsibility for defects
discovered in its work, or create a warranty or guarantee. Terracon will not supervise or direct
the work performed by contractor or its subcontractors and is not responsible for their means
and methods.
H) AUTHORIZATION
This proposal may be accepted by executing the attached Agreement for Services and returning
an executed copy along with this proposal to Terracon. This proposal for services and
accompanying limitations shall constitute the exclusive terms, conditions and services to be
performed for this project. This proposal is valid only if authorized within sixty days from the
listed proposal date.
We appreciate this opportunity of working with you and we look forward to working with you in
the future.
Sincerely,
Terracon Consultants, Inc.
(Texas Registration No. F-3272)
oey UnderwoodT029— William V. Jac s, P.E.
Project Manager Senior Project Materials Engineer
Attachments:
(1) Budget Estimate
(2) Schedule of Fees and Services
(3) Agreement for Services
Responsive Resourceful . Reliable F a o. e 6
Resolution 18-04
Proposal for Construction Materials Testing Services 1rerracon
Town of Westlake Fire Station
2000 Dove Road, Westlake, Texas 76262
December 7, 2017 Terracon Proposal No. P95171268
BUDGET ESTIMATE
Service Quantity Unit Unit Rate Estimate
BUILDING
Earthwork Observation and Testing
Soils Technician,(min.4 hours) 60 hour $52.00 $3,120.00
Moisture Density Relationship(ASTM D698) 5 each $225.00 $1,125.00
Sieve Analysis(Minus 200,ASTM D1140) 5 each $40.00 $200.00
Atterberg Limits(ASTM D4318) 5 each $75.00 $375.00
Nuclear Density Gauge 12 trip $50.00 $600.00
Vehicle Charge 14 trip $40.00 $560.00
Sub-total $5,980.00
Concrete&Reinforcing Steel Observation and Testing
Concrete Technician,(min.4 hours) 68 hour $52.00 $3,536.00
Concrete Technician,(Overtime) 8 hour $78.00 $624.00
Reinforcing Steel Technician,(min.4 hours) 36 hour $52.00 $1,872.00
Compressive Strength Tests(4"x8") 60 each $17.00 $1,020.00
Concrete Cylinder Pick-Up 18 hour $52.00 $936.00
Vehicle Charge 18 trip $40.00 $720.00
Sub-total $8,708.00
Masonry
Masonry Technician,(min.4 hours) 48 hour $52.00 $2,496.00
Grout Test Prisms 48 each $35.00 $1,680.00
Mortar Test Cubes 72 each $18.00 $1,296.00
Masonry Sample Pick-Up 24 hour $52.00 $1,248.00
Vehicle Charge 24 trip $40.00 $960.00
Sub-total $7,680.00
Structural Steel Observation
Certified Welding Inspector(CWI),(min.4 hours) 32 hour $95.00 $3,040.00
Vehicle Charge 8 trip $40.00 $320.00
Sub-total $3,360.00
SITEWORK
Earthwork Observation and Testing
Soils Technician,(min.4 hours) 92 hour $52.00 $4,784.00
Nuclear Density Gauge 20 trip $50.00 $1,000.00
Vehicle Charge 23 trip $40.00 $920.00
Sub-total $6,704.00
Concrete &Reinforcing Observation and Testing
Concrete Technician,(min.4 hours) 68 hour $52.00 $3,536.00
Concrete Technician,(Overtime) 16 hour $78.00 $1,248.00
Compressive Strength Tests(4'x8") 140 each $17.00 $2,380.00
Concrete Cylinder Pick-Up 24 hour $52.00 $1,248.00
Vehicle Charge 24 trip $40.00 $960.00
Sub-total $9,372.00
ADMINISTRATION
Project Manager 40 hour $120.00 $4,800.00
Clerical 25 hour $60.00 $1,500.00
Project Engineer 5 hour $160.00 $800.00
Final Inspection Letter 1 each $500.00 $500.00
Sub-total $7,600.00
TotalEstimated Project 0i
Responsive Resourceful Reliable P a 9 e 17
Resolution 18-04
Proposal for Construction Materials Testing Services Irerracon
Town of Westlake Fire Station
2000 Dove Road,Westlake, Texas 76262
December 7,2017 Terracon Proposal No. P95171268
SCHEDULE OF SERVICES AND FEES
CONSTRUCTION MATERIALS ENGINEERING
2017
Personnel
ProjectEngineer, per hour ..............................................................................................$160.00
ProjectManager, per hour ...............................................................................................$120.00
Senior Engineering Technician, per hour ..........................................................................$56.00
Engineering Technician, per hour ......................................................................................$52.00
Clerical ............................................................................................................$60.00
Transportation
Vehicle, per trip (within 50 miles of Terracon office) .........................................................$40.00
Mileage (over 50 miles from Terracon office) per mile ........................................................$0.60
A fuel surcharge may be added if fuel costs increase by more than 10% during the project
duration.
Concrete and Reinforcing Steel Field Services
Engineering technician, per hour ......................................................................................$52.00
Engineering technician, overtime rate, per hour ...............................................................$78.00
Concrete Tests
Compressive Strength Tests (ASTM C 31 & C 39), 4"x8", each .......................................$17.00
Compressive Strength Tests (ASTM C 31 & C 39), 6"x12", each .....................................$20.00
Compressive Strength Tests (Contractor Made), each .....................................................$30.00
Beam Flexural Tests (ASTM C 293 or C 78), each ..........................................................$50.00
Concrete Coring Technician, per hour ..............................................................................$52.00
Concrete Coring Technician, overtime rate, per hour .......................................................$78.00
Concrete Coring Generator Fee, per day .........................................................................$25.00
Concrete Coring Testing, each .........................................................................................$75.00
Masonry Field Services
Masonrytechnician, per hour ...........................................................................................$52.00
Masonry technician, overtime rate, per hour ....................................................................$78.00
Compressive strength CMU block (ASTM C 140), each .................................................$100.00
CMU block absorption only(ASTM C 140), each ..............................................................$75.00
CMU Block prism compressive strength (ASTM C 1314), each .......................................$250.00
Grout Test Prisms (ASTM C 1019), each .........................................................................$35.00
Mortar Test Cubes (ASTM C 780 & C 109), each ............................................................$18.00
Responsive : Resourceful Reliable P a g e 18
Resolution 18-04
Proposal for Construction Materials Testing Services Irerracon
Town of Westlake Fire Station
2000 Dove Road,Westlake, Texas 76262
December 7, 2017 Terracon Proposal No. P95171268
SCHEDULE OF SERVICES AND FEES
CONSTRUCTION MATERIALS ENGINEERING
2017
Soils Laboratory Tests
Classification
Atterberg limits (ASTM D 4318), each ..............................................................................$75.00
Sieve analysis (ASTM C 136), each .................................................................................$75.00
Sieve analysis percent finer than#200 (ASTM C 117 or D 1140), each ...........................$40.00
Compaction
Optimum moisture / maximum dry density relations (proctors)
ASTMD698, each ..............................................................................................$225.00
ASTMD1557, each ............................................................................................$275.00
Additional charge for Coarse Aggregate Correction (ASTM D4718) ......................$25.00
TXDOT TEX 113E, each ....................................................................................$250.00
TXDOT TEX 114E, each .................... ...........$225.00
.....................................................
Permeability(ASTM D 5084), each ....................................................................$350.00
Soils Field Services
Soilstechnician, per hour .................................................................................................$52.00
Soils technician, overtime rate, per hour ..........................................................................$78.00
Nuclear Density Gauge, per day .......................................................................... $50.00
Field gradation of lime treated soil, each ................................ ..................................$45.00
Depth check of lime treated soil, each ..............................................................................$25.00
Soil pH value (TEX 128E) each ........................................................................................$25.00
Asphaltic Concrete Services
Asphalttechnician, per hour .............................................................................................$56.00
Asphalt technician, overtime rate, per hour ......................................................................$84.00
Molding specimens (TEX 206F), set of 3 ..........................................................................$75.00
Bulk specific gravity of lab molded specimens, set of 3 ....................................................$50.00
Bulk specific gravity of core specimen (TEX 207F), each .................................................$50.00
Maximum theoretical density (ASTM D 2041 or TEX 227F), each ....................................$75.00
Hveem stability (ASTM D 1560 or TEX 208F), set of 3 ...................................................$100.00
Extraction and Sieve Analysis (ASTM D 2172 or TEX 21 OF), each ................................$200.00
Asphalt coring technician, per hour ..................................................................................$95.00
Asphalt core thickness &density, each ............................................................................$50.00
Responsive Resourceful i Reliable P a g e 19
Resolution 18-04
Proposal for Construction Materials Testing Services 1rerracon
Town of Westlake Fire Station
2000 Dove Road,Westlake,Texas 76262
December 7, 2017 Terracon Proposal No. P95171268
SCHEDULE OF SERVICES AND FEES
CONSTRUCTION MATERIALS ENGINEERING
2017
Drilled Pier
Senior Engineering Technician, per hour .........................................................................$56.00
Senior Engineering Technician, overtime rate, per hour ...................................................$84.00
Wood Truss & Fire Stop
Senior Engineering Technician, per hour .........................................................................$56.00
Senior Engineering Technician, overtime rate, per hour ...................................................$84.00
Structural Steel
Visual Inspection by CWI, per hour ..................................................................................$95.00
Ultrasonic Testing by CWI, per hour .................................................................................$95.00
Ultrasonic Testing Equipment, per day .............................................................................$75.00
Reinforcing Steel Detection
Senior Engineering Technician, per hour ............. .......$56.00
.....................................................
Senior Engineering Technician, overtime rate, per hour ...................................................$84.00
HiltiFerroscan equipment, per day .................................................................................$220.00
Reimbursable Expenses
Direct non-salary project expenses for 'outside" services are billed at cost plus 15 percent for
handling. These include but are not limited to the following: travel and lodging, external
consultants, environmental analytical tests, drilling, special supplies, permits, equipment,
sampling, field testing, on site facilities, clearing/grading contractors, water trucks, bulldozers,
security forces, surveyors, traffic control or other support services.
Remarks
A four (4) hour minimum charge is applicable to all trips made for the performance of testing,
inspection, cancellations or consulting services. A minimum charge of two (2) hours will be
assessed for trips to the project site for sample or cylinder pick up only.
Responsive Resourceful Reliable P a g e 110
Resolution 18-04
1 rerracon
Reference Number:P95171268
AGREEMENT FOR SERVICES
This AGREEMENT is between Town of Westlake ("Client") and Terracon Consultants, Inc. ("Consultant") for Services to be provided by Consultant for
Client on the Town of Westlake Fire Station project("Project"), as described in the Project Information section of Consultant's Proposal dated 12/07/2017
("Proposal")unless the Project is otherwise described in Exhibit A to this Agreement(which section or Exhibit is incorporated into this Agreement).
1. Scope of Services.The scope of Consultant's services is described in the Scope of Services section of the Proposal("Services"), unless Services
are otherwise described in Exhibit B to this Agreement(which section or exhibit is incorporated into this Agreement). Portions of the Services may be
subcontracted. When Consultant subcontracts to other individuals or companies,then consultant will collect from Client on the Subcontractors'behalf.
Consultant's Services do not include the investigation or detection of, nor do recommendations in Consultant's reports address the presence or
prevention of biological pollutants (e.g., mold, fungi, bacteria, viruses, or their byproducts) or occupant safety issues, such as vulnerability to natural
disasters, terrorism, or violence. If Services include purchase of software, Client will execute a separate software license agreement. Consultant's
findings, opinions, and recommendations are based solely upon data and information obtained by and furnished to Consultant at the time of the
Services.
2. Acceptance/ Termination. Client agrees that execution of this Agreement is a material element of the consideration Consultant requires to
execute the Services, and if Services are initiated by Consultant prior to execution of this Agreement as an accommodation for Client at Client's
request, both parties shall consider that commencement of Services constitutes formal acceptance of all terms and conditions of this Agreement.
Additional terms and conditions may be added or changed only by written amendment to this Agreement signed by both parties. In the event Client
uses a purchase order or other form to administer this Agreement,the use of such form shall be for convenience purposes only and any additional or
conflicting terms it contains are stricken. This Agreement shall not be assigned by either party without prior written consent of the other party. Either
party may terminate this Agreement or the Services upon written notice to the other. In such case, Consultant shall be paid costs incurred and fees
earned to the date of termination plus reasonable costs of closing the Project.
3. Change Orders. Client may request changes to the scope of Services by altering or adding to the Services to be performed. If Client so requests,
Consultant will return to Client a statement (or supplemental proposal) of the change setting forth an adjustment to the Services and fees for the
requested changes. Following Client's review, Client shall provide written acceptance. If Client does not follow these procedures, but instead directs,
authorizes,or permits Consultant to perform changed or additional work,the Services are changed accordingly and Consultant will be paid for this work
according to the fees stated or its current fee schedule. If project conditions change materially from those observed at the site or described to
Consultant at the time of proposal,Consultant is entitled to a change order equitably adjusting its Services and fee.
4. Compensation and Terms of Payment. Client shall pay compensation for the Services performed at the fees stated in the Compensation
section of the Proposal unless fees are otherwise stated in Exhibit C to this Agreement(which section or Exhibit is incorporated into this Agreement). If
not stated in either,fees will be according to Consultant's current fee schedule.Fee schedules are valid for the calendar year in which they are issued.
Fees do not include sales tax. Client will pay applicable sales tax as required by law. Consultant may invoice Client at least monthly and payment is
due upon receipt of invoice. Client shall notify Consultant in writing,at the address below,within 15 days of the date of the invoice if Client objects to
any portion of the charges on the invoice, and shall promptly pay the undisputed portion. Client shall pay a finance fee of 1.5% per month, but not
exceeding the maximum rate allowed by law,for all unpaid amounts 30 days or older. Client agrees to pay all collection-related costs that Consultant
incurs, including attorney fees. Consultant may suspend Services for lack of timely payment. It is the responsibility of Client to determine whether
federal, state, or local prevailing wage requirements apply and to notify Consultant if prevailing wages apply. If it is later determined that prevailing
wages apply, and Consultant was not previously notified by Client, Client agrees to pay the prevailing wage from that point forward, as well as a
retroactive payment adjustment to bring previously paid amounts in line with prevailing wages. Client also agrees to defend, indemnify, and hold
harmless Consultant from any alleged violations made by any governmental agency regulating prevailing wage activity for failing to pay prevailing
wages,including the payment of any fines or penalties.
5. Third Party Reliance.This Agreement and the Services provided are for Consultant and Client's sole benefit and exclusive use with no third party
beneficiaries intended. Reliance upon the Services and any work product is limited to Client,and is not intended for third parties other than those who
have executed Consultant's reliance agreement,subject to the prior approval of Consultant and Client.
6. LIMITATION OF LIABILITY. CLIENT AND CONSULTANT HAVE EVALUATED THE RISKS AND REWARDS ASSOCIATED WITH THIS
PROJECT, INCLUDING CONSULTANT'S FEE RELATIVE TO THE RISKS ASSUMED, AND AGREE TO ALLOCATE CERTAIN OF THE
ASSOCIATED RISKS. TO THE FULLEST EXTENT PERMITTED BY LAW, THE TOTAL AGGREGATE LIABILITY OF CONSULTANT(AND ITS
RELATED CORPORATIONS AND EMPLOYEES)TO CLIENT AND THIRD PARTIES GRANTED RELIANCE IS LIMITED TO THE GREATER OF
$50,000 OR CONSULTANTS FEE, FOR ANY AND ALL INJURIES, DAMAGES, CLAIMS, LOSSES, OR EXPENSES (INCLUDING ATTORNEY
AND EXPERT FEES)ARISING OUT OF CONSULTANT'S SERVICES OR THIS AGREEMENT. PRIOR TO ACCEPTANCE OF THIS AGREEMENT
AND UPON WRITTEN REQUEST FROM CLIENT, CONSULTANT MAY NEGOTIATE A HIGHER LIMITATION FOR ADDITIONAL
CONSIDERATION IN THE FORM OF A SURCHARGE TO BE ADDED TO THE AMOUNT STATED IN THE COMPENSATION SECTION OF THE
PROPOSAL. THIS LIMITATION SHALL APPLY REGARDLESS OF AVAILABLE PROFESSIONAL LIABILITY INSURANCE COVERAGE,
CAUSE(S),OR THE THEORY OF LIABILITY, INCLUDING NEGLIGENCE,INDEMNITY, OR OTHER RECOVERY. THIS LIMITATION SHALL NOT
APPLY TO THE EXTENT THE DAMAGE IS PAID UNDER CONSULTANT'S COMMERCIAL GENERAL LIABILITY POLICY.
7. Indemnity/Statute of Limitations.Consultant and Client shall indemnify and hold harmless the other and their respective employees from and
against legal liability for claims,losses,damages,and expenses to the extent such claims, losses,damages,or expenses are legally determined to be
caused by their negligent acts,errors,or omissions. In the event such claims,losses,damages,or expenses are legally determined to be caused by the
joint or concurrent negligence of Consultant and Client,they shall be borne by each party in proportion to its own negligence under comparative fault
principles. Neither party shall have a duty to defend the other party,and no duty to defend is hereby created by this indemnity provision and such duty
is explicitly waived under this Agreement. Causes of action arising out of Consultant's Services or this Agreement regardless of cause(s)or the theory
of liability,including negligence,indemnity or other recovery shall be deemed to have accrued and the applicable statute of limitations shall commence
to run not later than the date of Consultant's substantial completion of Services on the project.
8. Warranty. Consultant will perform the Services in a manner consistent with that level of care and skill ordinarily exercised by members of the
profession currently practicing under similar conditions in the same locale. EXCEPT FOR THE STANDARD OF CARE PREVIOUSLY STATED,
CONSULTANT MAKES NO WARRANTIES OR GUARANTEES, EXPRESS OR IMPLIED, RELATING TO CONSULTANT'S SERVICES AND
CONSULTANT DISCLAIMS ANY IMPLIED WARRANTIES OR WARRANTIES IMPOSED BY LAW, INCLUDING WARRANTIES OF
MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE.
9. Insurance. Consultant represents that it now carries, and will continue to carry: (i)workers'compensation insurance in accordance with the laws of
the states having jurisdiction over Consultant's employees who are engaged in the Services, and employer's liability insurance ($1,000,000); (ii)
Page 1 of 2 Resolution 144ev. 10-16
Irerracon-
Reference Number:P95171268
commercial general liability insurance($1,000,000 occ/$2,000,000 agg); (iii)automobile liability insurance($1,000,000 B.1. and P.D.combined single
limit); and(iv) professional liability insurance($1,000,000 claim/agg). Certificates of insurance will be provided upon request. Client and Consultant
shall waive subrogation against the other party on all general liability and property coverage.
10. CONSEQUENTIAL DAMAGES. NEITHER PARTY SHALL BE LIABLE TO THE OTHER FOR LOSS OF PROFITS OR REVENUE; LOSS OF
USE OR OPPORTUNITY; LOSS OF GOOD WILL; COST OF SUBSTITUTE FACILITIES, GOODS, OR SERVICES; COST OF CAPITAL; OR FOR
ANY SPECIAL,CONSEQUENTIAL,INDIRECT,PUNITIVE,OR EXEMPLARY DAMAGES.
11. Dispute Resolution. Client shall not be entitled to assert a Claim against Consultant based on any theory of professional negligence unless and
until Client has obtained the written opinion from a registered, independent,and reputable engineer,architect,or geologist that Consultant has violated
the standard of care applicable to Consultant's performance of the Services. Client shall provide this opinion to Consultant and the parties shall
endeavor to resolve the dispute within 30 days,after which Client may pursue its remedies at law.This Agreement shall be governed by and construed
according to Kansas law.
12. Subsurface Explorations. Subsurface conditions throughout the site may vary from those depicted on logs of discrete borings,test pits, or other
exploratory services.Client understands Consultant's layout of boring and test locations is approximate and that Consultant may deviate a reasonable
distance from those locations. Consultant will take reasonable precautions to reduce damage to the site when performing Services; however, Client
accepts that invasive services such as drilling or sampling may damage or alter the site.Site restoration is not provided unless specifically included in
the Services.
13. Testing and Observations.Client understands that testing and observation are discrete sampling procedures, and that such procedures indicate
conditions only at the depths,locations,and times the procedures were performed.Consultant will provide test results and opinions based on tests and
field observations only for the work tested. Client understands that testing and observation are not continuous or exhaustive, and are conducted to
reduce-not eliminate-project risk.Client shall cause all tests and inspections of the site,materials,and Services performed by Consultant to be timely
and properly scheduled in order for the Services to be performed in accordance with the plans, specifications, contract documents, and Consultant's
recommendations. No claims for loss or damage or injury shall be brought against Consultant by Client or any third party unless all tests and
inspections have been so performed and Consultant's recommendations have been followed. Unless otherwise stated in the Proposal,Client assumes
sole responsibility for determining whether the quantity and the nature of Services ordered by Client is adequate and sufficient for Client's intended
purpose. Client is responsible (even if delegated to contractor) for requesting services, and notifying and scheduling Consultant so Consultant can
perform these Services. Consultant is not responsible for damages caused by Services not performed due to a failure to request or schedule
Consultant's Services. Consultant shall not be responsible for the quality and completeness of Client's contractor's work or their adherence to the
project documents, and Consultant's performance of testing and observation services shall not relieve Client's contractor in any way from its
responsibility for defects discovered in its work,or create a warranty or guarantee.Consultant will not supervise or direct the work performed by Client's
contractor or its subcontractors and is not responsible for their means and methods. The extension of unit prices with quantities to establish a total
estimated cost does not guarantee a maximum cost to complete the Services.The quantities,when given,are estimates based on contract documents
and schedules made available at the time of the Proposal. Since schedule, performance, production, and charges are directed and/or controlled by
others,any quantity extensions must be considered as estimated and not a guarantee of maximum cost.
14. Sample Disposition, Affected Materials, and Indemnity. Samples are consumed in testing or disposed of upon completion of the testing
procedures (unless stated otherwise in the Services). Client shall furnish or cause to be furnished to Consultant all documents and information known
or available to Client that relate to the identity, location,quantity, nature,or characteristic of any hazardous waste,toxic, radioactive, or contaminated
materials("Affected Materials")at or near the site, and shall immediately transmit new, updated, or revised information as it becomes available.Client
agrees that Consultant is not responsible for the disposition of Affected Materials unless specifically provided in the Services, and that Client is
responsible for directing such disposition. In no event shall Consultant be required to sign a hazardous waste manifest or take title to any Affected
Materials. Client shall have the obligation to make all spill or release notifications to appropriate governmental agencies. The Client agrees that
Consultant neither created nor contributed to the creation or existence of any Affected Materials conditions at the site and Consultant shall not be responsible
for any claims, losses, or damages allegedly arising out of Consultant's performance of Services hereunder, or for any claims against Consultant as a
generator,disposer,or arranger of Affected Materials under federal,state,or local law or ordinance.
15. Ownership of Documents. Work product, such as reports, logs, data, notes, or calculations, prepared by Consultant shall remain Consultant's
property. Proprietary concepts, systems, and ideas developed during performance of the Services shall remain the sole property of Consultant. Files
shall be maintained in general accordance with Consultant's document retention policies and practices.
16. Utilities. Client shall provide the location and/or arrange for the marking of private utilities and subterranean structures. Consultant shall take
reasonable precautions to avoid damage or injury to subterranean structures or utilities. Consultant shall not be responsible for damage to
subterranean structures or utilities that are not called to Consultant's attention, are not correctly marked, including by a utility locate service, or are
incorrectly shown on the plans fumished to Consultant.
17. Site Access and Safety. Client shall secure all necessary site related approvals, permits, licenses, and consents necessary to commence and
complete the Services and will execute any necessary site access agreement. Consultant will be responsible for supervision and site safety measures
for its own employees, but shall not be responsible for the supervision or health and safety precautions for any other parties,including Client, Client's
contractors,subcontractors,or other parties present at the site.
Consultant: Terrac n Consulta ts, I :. Client: Town of Westlake
BY su 1/23/2018 By: Date: �'�O` 1WiliPJ
Name/Title: Engine Vi Jacobs/ enior Project Materials Name/Title: Thomas E.Brymer/Town Manager
Engineer
1500 Solana Boulevard, Building 7,Suite
Address: 2501 E Loop 820 N Address: 7200
Fort Worth,TX 76118-6978 Westlake,TX 76262
Phone: (817)268-8600 Fax: (817)268-8602 Phone: (817)490-5720 Fax: (817)430-1812
Email: Bill.Jacobs@terracon.com Email: tbrymer@westlake-tx.org
Page 2 of 2 Resolution 181
ev. 10-16
CERTIFICATE OF INTERESTED PARTIES FORM 1295
1 of 1
Complete Nos. 1.4 and 6 if there are interested parties. OFFICE USE ONLY
Complete Nos. 1,2,3,5,and 6 if there are no interested parties. CERTIFICATION OF FILING
1 Name of business entity filing form,and the city,state and country of the business entity's place Certificate Number:
of business. 2018-305003
Terracon Consultants, Inc.
Fort Worth, TX United States Date Filed.-
2
iled:2 Name of governmental entity or state agency that is a party to the contract for which the form is 01123/2018
being filed.
Town of Westlake Date Acknowledged:
g Provide the identification number used by the governmental entity or state agency to track or identity the contract,and provide a
description of the services,goods,or other property to be provided under the contract.
2018-1
Professional Consulting Services
Nature of interest
4
Name of Interested Party City,State,Country(place of business) (check applicable)
Controlling Intermediary
Cozart, George D. Austin,TX United States X
Gaboury, David R. Olathe, KS United States X
Cobb, C. Harold Houston,TX United States X
Covert, Michael E. Olathe, KS United States X
Pavlicek, Robert W. Raleigh, NC United States X
Vrana, Donald J. Olathe, KS United States X
Najm,Jamal Lawrenceville, GA United States X
Anderson,Tim W. Tempe,AZ United States X
5 Check only if there is NO Interested Party. ❑
6 UNSWORN DECLARATION
My name is Kyle Burroughs and my date of birth is
My address is 2601 East Loop 820 North Fork Worth TX 76118 USA
(street) (city) (state) (zip code) (wuntry)
I declare under penalty of perjury that the foregoing is true and correct.
Executed in Tarrant County, State of Texas ,on the23rdday of January ,20 18 .
(month) (year)
Signatur f au ized agent of contracting business entity
(Dela
Forms provided by Texas Ethics Commission www.ethics.state.tx.us Version V1.0.5523
CERTIFICATE OF INTERESTED PARTIES
FORM 1295
1 of 1
Complete Nos. 1-4 and 6 if there are interested parties. OFFICE USE ONLY
Complete Nos. 1,2,3,5,and 6 if there are no interested parties. CERTIFICATION OF FILING
1 Name of business entity filing form,and the city,state and country of the business entity's place Certificate Number:
of business. 2018-305003
Terracon Consultants, Inc.
Fort Worth,TX United States Date Filed:
2 Name of governmental entity or state agency that is a party to the contract for which the form is 01/23/2018
being filed.
Town of Westlake Date Acknowledged:
01/24/2018
3 Provide the identification number used by the governmental entity or state agency to track or identify the contract,and provide a
description of the services,goods,or other property to be provided under the contract.
2018-1
Professional Consulting Services
Nature of interest
4
Name of Interested Party City,State,Country(place of business) (check applicable)
Controlling Intermediary
Cozart, George D. Austin,TX United States X
Gaboury, David R. Olathe, KS United States X
Cobb, C. Harold Houston, TX United States X
Covert, Michael E. Olathe, KS United States X
Pavlicek, Robert W. Raleigh, NC United States X
Vrana, Donald J. Olathe, KS United States X
Najm, Jamal Lawrenceville, GA United States X
Anderson, Tim W. Tempe,AZ United States X
5 Check only if there is NO Interested Party. ❑
6 UNSWORN DECLARATION
My name is and my date of birth is
My address is
(street) (city) (state) (zip code) (country)
I declare under penalty of perjury that the foregoing is true and correct.
Executed in County, State of on the day of ,20
(month) (year)
Signature of authorized agent of contracting business entity
(Declarant)
Forms provided by Texas Ethics Commission www.ethics.state.tx.us Version V1.0.5523
Form TGC 2270
VERIFICATION REQUIRED BY TEXAS GOVERNMENT CODE CHAPTER 2270
Contract identifier: �>e I I44. 1((L° `G PJS 5kdi Mott
Department:
By signing below, Company herby verifies the following:
1. Company does not boycott Israel; and
2. Company will not boycott Israel during the term of the contract.
SIGNED BY:
(1/11/ -Piid/ i
Print Name of Person: CMijJ 8 Pedrc,0-1 , Sow,' trig0 to '(
Signing,Title,and .I
Company it'i raeOn
Date signed: /19-01)01) - g
STATE OF TEXAS §
COUNTY OF I acrCA.C,4 §
BEFORE ME,the undersigned Notary Public on this day personally appearedelI Name), on behalf of egy_
(Company) who being duly sworn, stated under oath that he/she has read the foregoing verification
required by Texas Government Code Section 2270.002 and said statements contained therein are true and correct..
SWORN AND SUBSCRIBED TO before me,this diol day of clettObff ,20 a
(-70..i.,. -
P-,4,--,,__.,A--,
NOTARY OF P B C,
FOR THE STATE F TEXAS - —- - -
My Commission Expires: %c'i ANGIE ROBERTS*. ' MY COMMISSION EXPIRES
%– '4'hC1.X4'/ 3► A } perry 3,2019
Government Code§ 2270.002. Provision Required in Contract
Effective: September 1, 2017
A governmental entity may not enter into a contract with a company for goods or services unless the contract contains a written
verification from the company that it:
(1)does not boycott Israel; and
(2)will not boycott Israel during the term of the contract.
The following definitions apply:
(1)"Boycott Israel"means refusing to deal with,terminating business activities with,or otherwise taking any action that is
intended to penalize, inflict economic harm on, or limit commercial relations specifically with Israel,or with a person or entity doing
business in Israel or in an Israeli-controlled territory, but does not include an action made for ordinary business purposes.
(2)"Company"means a for-profit sole proprietorship, organization,association,corporation, partnership,joint venture,
limited partnership, limited liability partnership, or limited liability company, including a wholly owned subsidiary, majority-owned
subsidiary, parent company,or affiliate of those entities or business associations that exists to make a profit.
(3)"Governmental entity"means a state agency or political subdivision of this state.
State law requires verification from a Company for contracts involving goods or services(regardless of the amount)