HomeMy WebLinkAboutRes 02-34-02 Approving Certain Contracts Related to the Westlake Civic CampusTOWN OF WESTLAKE
RESOLUTION NO. 02-34-02
A RESOLUTION OF THE BOARD OF ALDERMEN OF THE TOWN OF
WESTLAKE, TEXAS, APPROVING CERTAIN CONTRACTS RELATED T*
THE WESTLAKE CIVIC C.,MPUS.
BE IT RESOLVED BY THE BOARD OF ALDERMEN OF THE TOWN OF
WESTLAKE, TEXAS:
SECTION 1: That the Board of Aldermen of the Town of Westlake does hereby
approve the contracts related to the Westlake Civic Campus attached here as Exhibit A.
SECTION 2: That this Resolution shall become effective upon the date of its
passage.
ATTEST:
Ginger", rosswy, Town'Sect6tary
.• J, au"Telywil FIM K67 1 -1
L.
Scott Bradley, Mayor
Trent O. Petty, j
Town nager
� W
Manhattan Construction Company
"Building Excellence"
TO: Trent Petty, Westlake Town Manager
111111 !! I l�illiiiii I "Hill
MRIIIIIIIIII!! =�!=11111
Allocate for Scope & Drawing Refinement Amount: $1,024 (allowance for unframed mirrors)
IreIRIM'-• -r •• 0 111 •1
Bid Alternates and Miscellaneous:
Add veneer stone at bottom of classroom windows — Deduct $14,500
Payment & Performance Bonding: Yes / No — $8,025 (Yes)
Variance with Equivalent Budget: Budget = $1,074,720, Approved = $409,295
Bid Process Comments: Eight (8) Solicited, Four (4) No Bid, Received Four (4) bids.
Company Background: DBG Glass has been a glass & glazing contractor operating in the
DFW area for more than 15 years having done projects that range from $100,000 to
$2,000,000.
Bob Bowen, Construction Manager
cc: Estimating File
Job File
Manhattan Construction Company
6300 North Central Expressway * Dallas, Texas * (214) 357-7400 Fax (214) 357- 7798
Manhattan Construction Company
"Building Excellence"
TO: Trent Petty, Westlake Town Manager
111111111111111 111 111011 �!I�
ME
r 11 Ill :l� i Umnii'lli
MMEM1111111 11 1 , ETI ff I'
Original Contract Amount: $549,434
0 ---a
MU-SMKOM
Allocate for Scope & Drawing Refinement Amount: $70,000 (Additional stone work at service dock
wall and allowance for mockup cost)
Total Requested Approval Amount: $619,434
Bid Alternates and Miscellaneous:
Add veneer stone at bottom of classroom windows — ADD $10,783
Payment & Performance Bonding: Yes I No — $8,994 (Yes)
Variance with Eguivalent Budget: Budget = $842,300, Approved = $628,428
Bid Process Comments: Thirteen (13) Solicited, Nine (9) No Bid, Received Four (4) bid
Company Background: Wilks has been a masonry contractor operating in Texas for
more than 7 years doing projects from as small as $20,000 to as big as $7,000,000. 1
I
Bob Bowen, Construction Manager
cc: Estimating Fi
Job File i
9*16=
Trent Petty, Towp-
,U, ager
Manhattan Construction Company
6300 North Central Expressway * Dallas, Texas * (214) 357-7400 Fax (214) 357- 7798
Manhattan Construction Company
"Building Excellence"
TO: Trent Petty, Westlake Town Manager
awal *010 0 a M I M = im M a M; wor, U M. wyn - wo
m -MINE ulfh�
Allocate for Scope & Drawing Refinement Amount: NONE
Bid Alternates and Miscellaneous:
Payment & Performance Bonding: Yes / No — $12 820 (Yes)l
lay."Im
I&LOpawom
Variance with Equivalent Budget: Budget = $456,406, Approved = $595,180
0909- 02211-2 -- • , I I I Li 15411111:1 V ffi;- - �-i F��- M
11111, i!! 0
more than 20 years doing projects from as small as $100,000 to as big as $2,000,000.
Recommended: Approved:
Bob Bowen, Construction Manager Trent Petty, Town Manag , er"
cc: Estimating File
Job File
Manhattan Construction Company
6300 North Central Expressway * Dallas, Texas * (214) 357-7400 Fax (214) 357- 7798
Manhattan Construction Company
"Building Excellence"
TO: Trent Petty, Westlake Town Manager
FROM: Bob Bowen, Construction Manager
Award Item: WATERPROOFING AND CAULKING PACKAGE (#11)
Company to Perform Services: GORMAN AND ASSOCIATES, INC.
Original Contract Amount: $12,265
James
"• •:
Allocate for Scope & Drawing Refinement Amount: $15,580 (allowance for additional building and
site caulking not shown)
- M-0 - - *I -
Payment & Performance Bonding: Yes / No
Variance with Equivalent Budget: Budget = $65,940, Approved = $28,407
Bid Process Comments: Thirteen (13) Solicited, Five (5) No Bid, Received Eight (8) bids.
Company Background: Gorman has been a waterproofing and caulking contractor
operating in the DFW area for more than 15 years.
1=0 I I = 0=6
Bob Bowen, Construction Manager
•
Trent Petty, Town Mahager
Manhattan Construction Company
6300 North Central Expressway * Dallas, Texas * (214) 357-7400 Fax (214) 357- 7798
a
Manhattan Construction Company
"Building Excellence"
TO: Trent Petty, Westlake Town Manager
Award Item: WOOD FRAMING MATERIALS PACKAGE (#08)
Company to Perform Services: WHEAT LUMBER COMPANY
Original Contract Amount: $354,881
Allocate for Scope & Drawing Refinement Amount: $60,000 (allowance for shop drawings and
drawing refinement)
- .1-0 11 1 • 1 -
TIII
mole is
Variance with Equivalent Budget: This Item will see a part of the total Timber Package. Total
• Package Budget = $1,430,279, Approved Material (All Material including Parallam)
$570,761; Left to Purchase is the Erection of Wood Framing.
I
Bob Bowen, Construction Manager
cc: Estimating File
Job File
Trent Petty, Town--:Mnager
Manhattan Construction Company
6300 North Central Expressway * Dallas, Texas * (214) 357-7400 Fax (214) 357- 7798
Manhattan Construction Company
"Building Excellence"
TO: Trent Petty, Westlake Town Manager
FROM: Bob Bowen, Construction Manager
III; - - I III 111 111111111 iliiiiiiiiI��illi�l��iii I I - - I -
11151 ml .. 51111111!!F11ill I'll iflll 111! 1 1111"1 11111111111lil� - I ;
DATE: October 11, 200E
It i l�I I 1 1'''' 1
MMIPWIP 1=1
FTAV • ••- `- 0 . • a- -
Total Requested Approval Amount- $2,900
Bid Alternates and Miscellaneous: one
Payment & Performance Bonding: No
Variance with EguivalenL3gdget- Budget ® $5,000, Approved ® $2,900
Bid Process Comments:, Four (4) Solicited, One (1) No Bid, Received Three (3) bids.
Recommended:
Bob Bowen, Construction Manager
cc: Estimating File
Job File
Trent Petty, Town Mager
Manhattan Construction Company
6300 North Central Expressway * Dallas, Texas * (214) 357-7400 Fax (214) 357- 7798
Manhattan Construction Company
"Building Excellence"
TO: Trent Petty, Westlake Town Manager
FROM: Bob Bowen, Construction Manager
DATE: September 20, 2002
Company to Perform Services: TRUS JOIST
Lem
Allocate for Scope & Drawing Refinement Amount: one
Bid Alternates and Miscellaneous: None
Pay.ment & Performance Bonding: No — Material Supplier Only
Variance with Equivalent Budget: This Item will become part of the total Timber Package.
Release of the Supplier is needed because of lead time to make product.
Bid Process Comments:, Only one supplier makes this produce
Company Background: Trus Joist is a subsidiary of Weyerhaeuser, which specializes in
Parallam beams.
Recommended:
Bob Bowen, Construction Manager
cc: Estimating File
Job File
W3=
Trent Petty, Tow Manager
Manhattan Construction Company
6300 North Central Expressway * Dallas, Texas * (214) 357-7400 Fax (214) 357- 7798
17m -
"Building Excellence"
TO: Trent Petty, Westlake Town Manager
FROM: Bob Bowen, Construction Manager
SUBJECT: Westlake Project - Subcontract Award Request
TWINTITIN
Award Item: ELECTRICAL PACKAGE (#06)
Company to Perform Services: HUMPHREY & ASSOC., INC.
Original Contract Amount: $821,853
Allocate for Scope & Drawing Refinement Amount: one
Total Requested Approval Amount: $821,853
VIA E-MAIL
Page 1 of 1
Bid Alternates and Miscellaneous: ($12,500) (Deduct to go to Gas Heat)
Payment & Performance Bonding.- Yes I No — 10,680
Variance with Equivalent Budget: Budget = $907,317, Approved = $820,033
Bid Process Comments: Nine (9) Solicited, One (1) No Bid, Received Eight (8) bids.
Company Background: Humphrey has been an electrical contractor operating in the
DF W area for more than 25 years.
Recommended: Approved:
Bob Bowen, Construction Manager Trent Petty, To4h�Manager
cc: Estimating File
Job File
Manhattan Construction Company
6300 North Central Expressway * Dallas, Texas * (214) 357-7400 Fax (214) 357- 7798
Manhattan Construction Company
"Building Excellence"
TO: Trent Petty, Westlake Town Manager
FROM: Bob Bowen, Construction Manager
SUBJECT: Westlake Project - Subcontract Award Request
PT&TIMT11IN
Original Contract Amount: $976,000
Allocate for Scope & Drawing Refinement Amount: one
Total Requested Approval Amount: $976,000
Bid Alternates and Miscellaneous: $170,000 (Add for Gas Heat)
Payment & Performance Bonding: Yes / No — 14,000
W 19 111
,E 1lI14
VIA E-MAIL
Page 1 of 1
• I A a a -, .1 0 LUXOII14 ewt$11101 dW SIA e-44 I'llt A- 9
Recommended:
Bob Bowen, Construction Manager
cc: Estimating File
Job File
Trent Petty, Town Manager
Manhattan Construction Company
6300 North Central Expressway * Dallas, Texas * (214) 357-7400 Fax (214) 357- 7798