Approved Site Plans / Building Elevations Plat Status Status of Public Improvements Building Permit Status
1 CVS Pharmacy (Ord. 762)Block N, Lot 3 90% complete; not accepted Issued; Under Temp C of O
2 Primrose School (Ord. 763)Block M, Lot 2 90% complete; not accepted Issued; Under construction
3 Retail Corner (Ord. 771)Blocks O and A substantially incomplete - not accepted Foundation only permits* under review
4 Ampitheater (Ord. 777)Lot 1, Block B (not replatted)#substantially incomplete - not accepted not issued**
5 Gas Pad Parking (Ord. 778)Lot 1, Block B (not replatted)#substantially incomplete - not accepted not issued**
6 Restaurant ROW (Ord. 779)Lot 1, Block B (not replatted)#substantially incomplete - not accepted not issued**
7 Residential Villas (Ord. 783)Block J substantially incomplete - not accepted not issued**
8 Residential Townhomes (Ord. 795)Block I substantially incomplete - not accepted not issued**
Key
Map
ID
Unapproved Site Plans Plat Status Status of Public Improvements Building Permit Status
9 Single Family Residential (Block D, E, F, H)Lot 1, Block B (not replatted)#substantially incomplete - not accepted not issued**
10 Hotel Plaza (Block C)Lot 1, Block B (not replatted)#substantially incomplete - not accepted not issued**
11 Chapel, Town Hall & Parking Garage Lot 1, Block B (not replatted)#substantially incomplete - not accepted not issued***
Key
Map
ID
Unapproved Site Plans Plat Status Status of Public Improvements Building Permit Status
12 Unspecified Residential / Commercial Units Lot 1, Block B (not replatted)#construction not apporoved not issued****
** Building permits cannot be issued until all Phase One public improvements are accepted
*** A foundation only permit is issued for the chapel. All other building permits cannot be issued until site plans are approved and all Phase One public improvements are accepted.
**** No developer's agreement exists for phase 2. Building permits cannot be issued until site plans are approved and all Phase One public improvements are accepted.
Entrada Phase One - Construction Status (as of 1/23/2017)
Entrada Phase Two - Construction Status (as of 1/20/2017)
* Foundation only permit requested by developer. Plans under review
# replat required for compliance with preliminary plat and development plan
Entrada Development Status Report - 1/23/2017
Town of Westlake Page 1 of 4 Planning and Development Dept.
1 3 4 5 9 10 11 12 2 7 8 6 Approved Entrada Development Plan ConstrucƟon / Approval Status Key Map—as of 1/23/2017 Entrada Development Status Report - 1/23/2017Town of WestlakePage 2 of 4Planning and Development Dept.
Event Description Ordinance / Resolution Approval Date
Initial Zoning Approved Ordinance 703 Monday, April 22, 2013
Economic Development Agreement Approved Resolution 13-17 Monday, April 22, 2013
Development Plan Approved Ordinance 720 Monday, October 28, 2013
Preliminary Plat Approved Resolution 13-32 Monday, October 28, 2013
Phase 1 Development Agreement Approved Resolution 13-34 Monday, October 28, 2013
Solana Public Improvement District Created Resolution 14-07 Monday, February 24, 2014
Amendment One to Economic Development Agreement Approved Resolution 14-46 Monday, December 15, 2014
Amendment Two to Economic Development Agreement Approved Resolution 15-02 Thursday, January 15, 2015
Phase One Public Improvements Construction Begins n/a Sunday, March 1, 2015
Initial Final Plat Approved Ordinance 761 Monday, December 14, 2015
Design Guidelines Approved Ordinance 760 Monday, December 14, 2015
Master Landscape, Lighting and Paving Plan Approved Ordinance 759 Monday, December 14, 2015
Amendment One to Ph. 1 Development Agreement Approved Resolution 15-35 Monday, December 14, 2015
CVS Pharmacy Site Plan & Building Elevations Apprved Ordinance 762 Monday, December 14, 2015
Primrose School Site Plan & Building Elevations Approved Ordinance 763 Monday, December 14, 2015
CVS Building Permit Issued*n/a Thursday, January 14, 2016
Retail Corner Site Plan & Building Elevations Approved Ordinance 771 Monday, February 22, 2016
Ampitheater Site Plan & Building Elevations Approved Ordinance 777 Monday, March 28, 2016
Gas Pad Parking Site Plan & Building Elevations Approved Ordinance 778 Monday, March 28, 2016
Restaurant ROW Site Plan & Building Elevations Approved Ordinance 779 Monday, March 28, 2016
Residential Villas Site Plan & Building Elevations Approved Ordinance 783 Monday, April 25, 2016
Primrose Building Permit Issued*n/a Tuesday, July 26, 2016
Residential Townhomes Site Plan & Building Elevations Approved Ordinance 795 Monday, September 19, 2016
CVS Temporary C of O Issued n/a Friday, October 28, 2016
Phase One Public Improvements Construction Projected Completion**n/a Thursday, July 27, 2017
*Permits Issued prior to acceptance of public imrpovements
**According to developer's projection
Entrada Development Chronology - as of 1/23/2017
NOTE: Phase Two agreements, replats, site plans and construction have not been not been approved as of 1/23/2017
Entrada Development Status Report - 1/23/2017
Town of Westlake Page 3 of 4 Planning and Development Dept.
PD Zoning and Concept Plan Approved PD Development Plan Approved (Split into 2 phases) PD Site Plan(s) Approved Preliminary/Final Plats Approved (Final plats further divid-ed as individual replats) Public Improvements Accepted by Town Building Permits Approved 1 2 3 4 C o n s t r u c t I o n o f P u b l I c I m p r o v e m e n t s 5 6 7 Westlake Entrada General Development Process Flow Chart Entrada Development Status Report - 1/23/2017Town of WestlakePage 4 of 4Planning and Development Dept.