HomeMy WebLinkAboutFire EMS Station presentationWestlake Fire –EMS
Station
Town Council December 12, 2016
MILESTONES
June 2016 -Land donation approved by donor
August 2016 -Land donation accepted by Town Council
September 2016 -Fire-EMS Station Town Forum
October 2016 -Cost analysis completed
October 2016 -Closing on 5 acre land donation
October 2016-Proposed Certificate of Obligation Publication of Notice $9.2M
December 2016-P&Z Approved the Re-plat and Re-Zoning of 5 acre property
December 2016-Request for Qualification (RFQ) Construction Management @ Risk
December 2016-Proposed AIA contractor to provide professional architectural
design services with BRW
December 2016 -Final sale of CO
January 2017 -Approve CM@R
BRW Agreement
Total cost of basic services-8.6% of the $6.6M estimate of construction cost pg. 142
Basic Fee $569,750 include,
Architectural $470,750
Structural $42,000
MEP $57,000
Other Services $68,250 include,
Civil engineering $42,750
Landscaping $15,000
Storm water Detention $4,500
Record Documents $6,000
Other services $68,250
Total basic Fees $638,000
Design Milestone dates Pg. 121
NEXT STEPS
December 12 –Staff recommend the approval of the BRW agreement
December 12 -Fire –EMS Station No. 1 Coming soon sign
January 2017 –Recommend approval of the Construction Manager @ Risk
Late January/ February –Second Forum
June 2017 –Complete construction Drawings
June/July 2017 -Project goes out to bid (Completed by the CM@R)
August 2017 -TC approves guaranteed maximum price
August 2017 -Break ground
Fall 2018 –Move in
Town Web site -Government –Capital Projects-New Fire-EMS Station
Fire –EMS Station No. 1 coming Soon Sign
Sign Design
FIRE STATION COST INCREASE
10% to 15% increase in fire station construction in the past 3 years
Increase $880,000 to $1.2M
Today basic fire station square feet cost $360 to $375
2013 to 2015 sq. ft. cost range from $264 to $330
Westlake characteristic
Proposed Westlake sq. ft. cost $413
Proposed Westlake elements -Building & site $700,000
Includes, building exterior, site work, water feature and landscaping
Add Alternates may include,
Fueling system $64,260
Hose tower $321,302
Water feature $250,000