HomeMy WebLinkAboutCapital Improvement Plan documentProposed
June 17, 2013
Town of Westlake
3 Village Circle #202 * Westlake, Tx 76262
DR
A
F
T
Table of Contents
11.. IINNTTRROODDUUCCTTIIOONN
Introduction 1
Funded and Proposed Capital Projects 7
Unfunded (Under Discussion) Capital Projects 8
22.. PPAA RRKKSS AANNDD RREECCRREEAATTIIOONN
Overview 9
Funded Projects 10
Unfunded Projects (Under Discussion) 15
33.. FFAA CCIILLII TTII EESS
Overview 17
Funded Projects 18
Unfunded Projects (Under Discussion) 21
44.. TTRRAA NNSSPPOORRTTAATTIIOONN IIMMPPRROOVVEEMMEENNTTSS
Overview 29
Funded Projects 30
Unfunded Projects (Under Discussion) 40
55.. VVEEHHIICCLLEESS AA NNDD EEQQUUIIPPMMEENNTT
Overview 41
Capital Maintenance & Replacement 42
Replacement & Depreciation Guidelines 43
66.. UUTTII LLII TTYY IIMMPPRROOVVEEMMEENNTTSS
Overview 47
Funded Projects 48
DR
A
F
T
Town of Westlake Vision Statement
Westlake is an oasis of tranquility and natural beauty
amidst an ever expanding urban landscape.
Vision ~ Values ~ Mission
The Town of Westlake Capital Improvement Plan is guided by the Town’s vision, core
values and organizational mission. Our vision recognizes the attributes we cherish as a
community and sets the standard for the Westlake that we want to see in the tomorrows
that are yet to be.
Mission Statement
“On behalf of the citizens,
the mission of the Town of Westlake
is to be a one-of-a-kind community
that blends our rural atmosphere
with our vibrant culture
and metropolitan location.”
Vision Points
~ A SENSE OF PLACE ~
Distinctive neighborhoods,
architecturally vibrant corporate campuses,
grazing longhorns, soaring red-tailed hawks,
meandering roads and trails,
lined with natural stone
and native oaks.
~ WE ARE LEADERS ~
A premiere place to live,
leadership in public education,
corporate and governmental
partnerships, and high
development standards.
~ WE ARE A CARING COMMUNITY ~
Informed residents,
small town charm and values,
historical preservation.
~ EXEMPLARY GOVERNANCE ~
Town officials, both elected
and appointed, exhibit respect,
stewardship, vision,
and transparency.
~ SERVICE EXCELLENCE ~
Public service that is responsive
and professional, while balancing
efficiency, effectiveness
and financial stewardship.
Community Values
Innovation
Educational Leaders
Family Friendly and Welcoming
Engaged Citizens
Preservation of Our Natural Beauty
Strong Aesthetic Standards
Transparent Government
Fiscal Responsibility
DR
A
F
T
1
CAPITAL IMPROVEMENT PLAN
Introduction
This document provides a comprehensive plan of capital improvements that are to be
undertaken by the Town over the next five (5) years. Cost estimates and financing
methods for the improvements are included and are referenced by individual project.
The development of the Town’s Capital Improvement Plan is one of the more complex
and multi-faceted processes of the Town. Striking a balance between the needs and
interests of the residents and the financial capacity of the Town is a challenging
proposition. For this community vision to have meaning, it must be accompanied by
deliberate planning that leads the organization and community to its desired future. This
requires clearly defined goals, proactive strategies, committed leadership, effective
management and above all, the resources to carry out these plans and objectives.
What is a CIP?
First, what it is not; a CIP (Capital Improvement Plan) is not a wish list, rather it is a realistic
plan designed to fulfill the strategic goals and objectives necessary to achieve the mission
and vision of the community. A CIP is a multi-year document that summarizes the capital
needs of a community over a specific time period. It outlines the individual capital
projects, their strategic value and relationship to the community’s long-term goals and
objectives as well as the fiscal impact that they pose to the community.
Why have a CIP?
• Informs the employees, departments, elected officials and the public of an entity’s
intent to invest in its infrastructure and community
• Represents a long-term financial plan and identifies resources or financing
strategies that an entity plans to use to fund the plan
• Establishes priorities and serves as a planning document or blueprint for an
organization’s investment in capital infrastructure both short-term and long-term
• Provides a breakdown of major project costs and phasing as necessary
• DOES NOT appropriate money
CIP Prioritization Strategy – Preserve * Protect * Plan
• Preserve the past by investing in the continued upgrade of town assets and
infrastructure
• Protect the present with improvements and/or additions to facilities, roads, and
capital investments
• Plan for the future of the organization
What is a Capital Project?
Capital includes all long-lived infrastructures such as water facilities, sewers, streets, parks
and buildings along with major equipment like fire trucks, radio systems, vehicles,
computers and fixtures. Capital projects are the individual action plans that make up a
Capital Improvement Plan. The capital projects in this CIP have been categorized into
the following groups: Parks & Recreation, Facilities, Transportation, Vehicles and Utilities.
DR
A
F
T
2
Land, 25%
Capital
Improvements,
26%
Buildings &
Improvements,
38%
Machinery
& Equipment,
6%
Wastewater
Treatment
Rights,
1%
Construction in
Progress, 4%
Capital Assets By Major Category
(per the FY2012 Comprehensive Annual Financial Report)
Capital Assets by Category
When most people think of the Town’s capital assets, they automatically think of the
Westlake Academy campus. While the campus is certainly a very important and visible
asset owned by the Town, it is but one of many. Included in the assets of the Town are all
of the Town’s infrastructure such as its
streets, water and sewer mains, vehicles
and other equipment. In preparing this
year’s CIP, the staff utilized our annual
audit to determine value of the Town’s
assets.
The chart to the right depicts the Town’s
capital assets from the Comprehensive
Annual Financial Report (page 12) as of
Fiscal Year Ended September 30, 2012.
Funding Considerations
In all communities the cost associated with capital projects far outweighs the available
resources necessary to pay for them; in short there is not enough money. This requires
prioritization of the projects based upon their perceived impact on the community. Due
to the vast number of individual desires it is near impossible to satisfy everyone and
requires a collaborative effort to create situations where the benefits are shared equitably
with community stakeholders. In addition, dedicated revenues will, in most cases,
determine which projects get funded. For example, the Utility Fund may only contribute
towards capital projects that improve water and wastewater projects.
Sources of Funding
There are four primary funding sources for capital improvements:
1. Cash Funding (revenue sources such as sales, hotel/motel and property taxes)
2. State/Federal funding (public grants)
3. Private Funding (developmental impact fees or charitable donations)
4. Bond Issuance
The proposed projects in this CIP rely on bond proceeds and other revenues in the
Governmental and Enterprise Funds as well as contributions from corporate partners for
funding. There are two types of bonds: General Obligation (GO) bonds which require
voter approval and Certificates of Obligation (CO) bonds which do not require voter
approval. The current CIP is funded primarily from four sources: Capital Projects & Utility
funds (cash on hand), Contributions and CO bonds.
How Inflation Impacts the CIP
Inflation is defined as a rise in the price of all goods and services over time. This implies
that the purchasing power, or value, of currency will decline in the future relative to costs.
Therefore, more money will be required to fund CIP related expenditures and must be
accounted for. This data is important in calculating the Town’s future liability; by utilizing
inflation trends to calculate future capital replacement costs, we can determine how
‘waiting’ a year or more impacts the total project cost. Most are aware of the benefits of
DR
A
F
T
3
Parks, Trails
& Cemetery
7%
Facilities
Improvements
2%
Transporation
Improvements
39%
Utility
Improvements
10%
Westlke
Academy
Expansion
43%
Funded Projects by Major Category
Five Year $15,933,805
$0
$2
$4
$6
$8
$10
$12
FY 13/14FY 14/15FY 15/16FY 16/17FY 17/18
$0.00
$3.53
$5.32
$8.54
$11.70
$9.19
$3.89
$0.27 $1.04 $1.55
UNFUNDED FUNDED
compounding when it comes to investing.
Unfortunately, this same principle works in
reverse as inflation causes costs to
compound higher over time.
Overview
The Capital Improvement Plan for fiscal
years 2013 through 2018 presents the
Town’s plan for infrastructure
development and improvements. On
April 23, 2012, the Town Council adopted
the second annual plan (FY 2012-2017).
These original projects as well as
additional staff recommended projects
are included in this plan.
The Capital Improvement Plan is evaluated annually by the Town leadership to determine
the financial availability of resources for design, construction, operations, and
maintenance. The following chart provides a graphical comparison of the previous
capital improvement plans.
The majority of capital improvements in Westlake have been unfunded. These projects
represent capital needs that are subject to more discussion and are included to convey to
the Town leaders and other interested parties the general parameters and breadth of
those capital needs. These projects may be moved to the “Funded” section of this CIP in
future years, depending on priorities, funding availability, and other considerations.
Several of these projects such as the permanent fire station and municipal complex are
multi-million dollar projects that have been carried forward since the Academy Complex
was established. Balancing these priorities, while at the same time being cognizant of the
fiscal challenges of our Town, means not all priorities can be addressed.
Funded vs Unfunded (Under Discussion) Capital Improvements
This multi-year capital plan will provide Council with a guide that communicates the
program need or deficiency,
as well as the funding
requirements. It is important
to note that projects which
do not receive funding in a
given year are moved out to
the future years in order to
communicate to those with
decision making responsibility
the need to provide
necessary funding, or through
evaluation, eliminate the
project entirely.
DR
A
F
T
4
Funding of Previously Adopted and Current Proposed Projects
On page 6 of the Capital Improvement Plan adopted in April of 2012, it was noted that
the Town staff anticipated issuing bonds in the amount of $2,095,000 in FY 13/14. Some of
the approved projects have been shifted to future years due to various circumstances;
therefore, we will not be issuing this debt in FY 13/14. Instead, we anticipate a $2.1M
issuance in FY 14/15 and another in FY 16/17 in the amount of $2.6. These Certificates of
Obligations along with cash previously approved and an additional $340K should cover
the financing needs for the projects previously approved as well as the proposed projects
included in this CIP.
Previously Adopted Projects to be completed in FY 12/13
Parks/Trails/Cemetery
• Westlake Academy North Driveway Lighting
Transportation Improvements
• Streets Survey
• Stagecoach Hills Reconstruction/Drainage
• Roanoke Road Reconstruction/Drainage North
• Hwy 377 Westport Parkway Signal
• Hillwood Projects
Utility Improvements
• N1 Sewer Line Transfer I&I Repairs
• Stagecoach Hills Waterline Phase II
Previously Adopted Projects – To be completed in future years
Parks/Trails/Cemetery
• Trail Connection at Hwy 114/Solana
Facilities Improvements
• Westlake Academy – Phase I Expansion
Transportation Improvements
• FM1938 Streetscape Improvements
• SH114/Hwy170 Enhancements
• Roanoke Road Reconstruction/Drainage South
• Sam School Rd Reconstruction/Drainage
• Dove Rd Reconstruction/Drainage (Vaquero/Terra Bella)
DR
A
F
T
5
Utility Improvements
• Ground Storage Tank
• N1 Sewer Line Transfer
Proposed Projects for FY 2014-2018
Parks/Trails/Cemetery - $1,070,300
• Glenwyck Farms Park Improvements
• Trail – Fidelity Campus to Westlake Parkway
• Trail – Westlake Academy to Cemetery
• Trail – Dove / Pearson / Aspen
Facilities Improvements - $99,000
• Outdoor Warning System
Transportation Improvements - $2,038,410
• Hwy 377 Landscape Improvements
• Ottinger Road Bridge Creek Crossing
• Ottinger Road Reconstruction & Drainage
• Wyck Hill Resurface
• Pearson Lane Reconstruction & Drainage
Conclusions
Capital Improvement Plans play an integral role in helping a municipality reach its stated
strategic objectives. Equally important to the capital project development process are
funding and economic considerations. Prudent financial stewardship should be based on
cost minimization and long-range strategic capital preservation. While there are many
methods for funding capital projects, consideration to who benefits from the project, the
life of the capital asset and the affordability of the funding method are all important
factors to consider. DR
A
F
T
6
ALL FUNDED AND PROPOSED CAPITAL PROJECTSFIVE YEAR PROJECTION
TOTAL
Page Proj Totals Thru FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 FIVE YEAR PROJECTS
No.No.Project Description FY 11/12 Estimated TOTAL COST
CAPITAL PROJECT FUNDS
10 CP42 Trail Connection at Hwy 114/Solana - - 15,000 10,000 15,450 - - 40,450 40,450
11 CP50 Glenwyck Farms Park Improvements - - - 250,000 - - - 250,000 250,000
12 CP51 Trail - Fidelity to Westlake Pkwy - - - 270,600 - - - 270,600 270,600
13 CP52 Trail - Westlake Academy to
Cemetery - - - - - - 276,100 276,100 276,100
14 CP53 Trail - Dove/Pearson/Aspen - - - - - 273,600 - 273,600 273,600
CY CP46 WA North Driveway Lighting - 40,000 - - - - - - 40,000
40,000 15,000 530,600 15,450 273,600 276,100 1,110,750 1,150,750
18 CP54 WA - West parking Improvements - - 200,000 - - - - 200,000 200,000
19 CP55 Outdoor Warning System - - 99,000 - - - - 99,000 99,000
CY CP29 WA Dining Hall Improvements 78,085 - - - - - - - 78,085
20 WA WA Expansion 36,398 1,650,000 5,708,601 1,105,001 - - - 6,813,602 8,500,000
1,105,001 - - -
30 CP20 FM1938 Streetscape Improvements 938,076 75,000 1,241,879 739,100 253,100 - - 2,234,079 3,247,155
CY CP26 Mahotea Boone Recon/Drain 88,191 - - - - - - - 88,191
CY CP28 Streets Survey 49,235 - - - - - - - 49,235
31 CP30 SH114/Hwy170 Enhancements 7,500 345,460 301,570 336,000 - - - 637,570 990,530
31 CP30 SH114/Hwy170 Enhancements 89,370 89,370 89,370
CY CP31 Stagecoach Hills Recon/Drain 413,926 84,974 - - - - - - 498,900
CY CP32 Roanoke Road Recon/Drain North 160,732 1,248 - - - - - - 161,980
CY CP33 Aspen Lane Recon/Drain 214,022 - - - - - - - 214,022
32 CP34 Roanoke Road Recon/Drain South 2,900 - - 453,000 - - - 453,000 455,900
33 CP40 Sam School Rd Recon/Drainage - - - 216,000 - - - 216,000 216,000
34 CP41 Dove Rd Recon/Drain (Vaq/TB) - - - 509,945 - - - 509,945 509,945
CY CP47 Hwy 377 Westport Parkway Signal 50,000 28,650 - - - - - - 78,650
35 CP56 HWY 377 Landscape Improvements - - - - - - 700,000 700,000 700,000
36 CP57 Ottinger Road Bridge Creek Crossing - - - - - 330,000 - 330,000 330,000
37 CP58 Ottinger Road Recon/Drainage - - - - - - 572,710 572,710 572,710
38 CP59 Wyck Hill Resurface - - - - - 54,450 - 54,450 54,450
39 CP60 Pearson Lane Recon/Drainage - - - - - 381,250 - 381,250 381,250
CY CP45 Hillwood Projects 99,648 168,859 - - - - - - 268,507
CY CP45 Hillwood Projects - 861,583 - - - - - - 861,583
1,632,819 2,254,045 253,100 765,700 1,272,710 6,178,374 9,768,379
TOTAL CAPITAL PROJECTS FUNDS 2,138,714 3,255,774 7,655,420 3,889,646 268,550 1,039,300 1,548,810 14,401,726 19,796,214
UTILITY FUND 500
48 UF30 TRA Assumption of N-1 Sewer Line - - 82,967 - - - - 82,967 82,967
CY UF31 N1 Sewer Line Transfer I&I Repairs 171,122 75,004 - - - - - - 246,126
49 UF36 Ground Storage Tank (Bonds)3,088 47,800 949,113 - - - - 949,113 1,000,000
49 UF36 Ground Storage Tank (Cash)- - 500,000 - - - - 500,000 500,000
CY UF37 SC Hills Waterline Phase II 234,381 42,420 - - - - - - 276,801
TOTAL UTILITY FUND 408,590 165,224 1,532,079 - - - 1,532,079 2,105,894
2,547,304 3,420,998 9,187,499 3,889,646 268,550 1,039,300 1,548,810 15,933,805 21,902,107
Totals Thru FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 FIVE YEAR
FY 11/12 Estimated TOTAL TOTAL
Previously Adopted Projects Cash 1,343,579 1,094,008 672,337 567,100 253,100 - - 1,492,537 3,930,123
Contributions Cash 1,241,879 172,000 1,413,879 1,413,879
FY 10/11 - $2.095M Bonds previously issued Bonds 1,164,239 629,191 301,570 - - - - 301,570 2,095,000
FY 12/13 - $9.500M Bonds previously issued Bonds 39,486 1,697,800 6,657,714 1,105,001 - - - 7,762,715 9,500,000
FY 14/15 - New Projects Bonds - - - 2,035,545 - - - 2,035,545 2,035,545
FY 16/17 - New Projects Bonds - - - - - 1,039,300 1,548,810 2,588,110 2,588,110
New Projects Cash - - 314,000 10,000 15,450 - - 339,450 339,450
TOTAL $ 2,547,304 $ 3,420,998 $ 9,187,499 $ 3,889,646 $ 268,550 $ 1,039,300 $ 1,548,810 $ 15,933,805 $ 21,902,107
8,877,085 6,007,601 7,112,602
- - - - - - - - - - - - Five Year Projection - - - - - - - - - -
TOTAL FUNDED CAPITAL PROJECTS
new project added this year
Sub-Total - Park/Trails/Cemetery
Sub-Total - Road/Street Improvements
Sub-Total - Facilities Improvements
- - - - - - - - - - - - Five Year Projection - - - - - - - - - - -
-
114,483
2,024,231 1,565,774
1,650,000
DR
A
F
T
7
ALL FUNDED AND PROPOSED CAPITAL PROJECTSFIVE YEAR PROJECTION
Page Proj Totals Thru FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 GRAND
No.No.Project Description FY 11/12 Estimated TOTAL
15 Cemetery Improvements - - - 63,000 31,800 125,000 125,000 344,800
16 10-20 Acre Community Park - - - 3,120,000 1,620,000 - - 4,740,000
Total Park/Trails/Cemetery - - - 3,183,000 1,651,800 125,000 125,000 5,084,800
21 Municipal Building - - - 344,100 3,242,100 - - 3,586,200
22 Fire Station Complex - - - - 372,000 4,798,560 - 5,170,560
23 Maintenance and Storage Facility - - - - - - 10,000 10,000
24 WA - Sport Field Complex - - - - - 83,750 2,856,000 2,939,750
25 WA Phase II - 15 classroom Secondary Addition - - - - 56,343 2,513,100 - 2,569,443
26 WA Phase II - 4 Classroom Kindergarten Addition - - - - - 1,023,620 - 1,023,620
27 WA Phase III - Art & Science Classrooms - - - - - - 1,878,080 1,878,080
28 WA Phase III - Performing Arts Center - - - - - - 4,809,600 4,809,600
Total Facilities Improvements - - - 344,100 3,670,443 8,419,030 9,553,680 21,987,253
40 Dove & Randol Mill Traffic Circle - - - - - - 2,019,600 2,019,600
Total Road/Street Improvements - - - - - - 2,019,600 2,019,600
TOTAL UNFUNDED CAPITAL PROJECTS -$ -$ -$ 3,527,100$ 5,322,243$ 8,544,030$ 11,698,280$ 29,091,653$
new project added this year
- - - - - - - - - - - - Five Year Projection - - - - - - - - - - -
DR
A
F
T
8
PARKS AND RECREATION OVERVIEW
The Parks & Recreation Department is responsible for maintaining the Town’s parks and
trails. The Town of Westlake provides residents with one Town Park which is located near
the Glenwyck subdivision.
The Town also maintains several trails
located near the Glenwyck and
Vaquero subdivisions. While many
more trails have been discussed, no
funding has been provided in recent
years. In recent resident surveys parks
and trails have consistently rated as
high priority/low satisfaction items
suggesting a need for improvement.
One of the goals of the current CIP is
to begin creating the trails that will
provide connectivity from the Town’s
West side to its Eastern limits as well as
interconnectivity with neighboring
jurisdiction’s trail systems.
Adopted Projects – CIP FY 12-17
Projects to be completed in FY 12-13
• Westlake Academy North Driveway Lighting
Projects to be completed in future years
• Trail Connection at Hwy 114/Solana
Proposed Projects – CIP FY 13-18
• Glenwyck Farms Park Improvements
• Trail - Fidelity Campus to Westlake Parkway
• Trail - Westlake Academy to Cemetery
• Trail - Dove / Pearson/ Aspen
Unfunded (Under Discussion) Projects
• Cemetery Improvements
• 10-20 Acre Community Park
DR
A
F
T
9
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - 10,000 - - - - 10,000
Construction - 15,000 - 15,450 - - - 30,450
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - 15,000 10,000 15,450 - - - 40,450
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bonds 2011 CO $2.095M - 15,000 - - - - - 15,000
Unfunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - 15,000 - - - - 15,000
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - - -
Insurance - - - - - - - -
Repair & Maintenance - - - - - - - -
Rent & Utilities - - - - - - - -
Debt Service - - - - - - -
OPERATING IMPACT - - - - - - -
FUNDED CAPITAL IMPROVEMENT
Trail Connection at 114/Solana
This project will be a cooperative effort between Westlake, Trophy Club,
and Southlake consisting of the design and engineering of an intra-city trail
system. The engineering/design costs will be shared with all cities.
Construction and landscaping are estimated costs until engineering and
design are completed. The Town continues to work with Cassidy Turley to
construct the trail between Sam School Road and Hwy 114.
5 Year Projection
5 Year Projection
PROJECT FUNDING
5 Year Projection
IMPACT ON OPERATING BUDGET
PROJECT EXPENSE
DR
A
F
T
10
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - 10,000 - - - 10,000
Construction - - - 240,000 - - - 240,000
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - - 250,000 - - - 250,000
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bonds 2014/15 CO $2.1M - - - 250,000 - - - 250,000
Unfunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - - - 250,000 - - - 250,000
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - 1,030 1,590 2,180 2,800 7,600
Services - - 1,030 1,060 1,090 1,120 4,300
Insurance - - - 258 265 273 280 1,075
Repair & Maintenance - - - 1,030 1,590 2,180 2,800 7,600
Rent & Utilities - - - 2,060 2,120 2,180 2,240 8,600
Debt Service - - - - - - - -
OPERATING IMPACT - - - 5,408 6,625 7,903 9,240 29,175
FUNDED CAPITAL IMPROVEMENT
Glenwyck Farms Park Improvements
5 Year Projection
5 Year Projection
5 Year Projection
PROJECT EXPENSE
PROJECT FUNDING
IMPACT ON OPERATING BUDGET
Purchase of playground equipment, benches and
ammmenities to be located along the current GlenWyck
Farms and Terra Bella trail systems. This project would
include additional features along trails, i.e. park benches,
trash cans, stretching stations, mile markers, lighting and
way finding signs etc.
DR
A
F
T
11
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - 20,800 - - - 20,800
Construction - - - 208,000 - - - 208,000
Design - - - 41,800 - - - 41,800
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - - 270,600 - - - 270,600
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bonds 2014/15 CO $2.1M - - - 270,600 - - - 270,600
Unfunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - - - 270,600 - - - 270,600
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - 2,060 2,120 2,180 2,240 8,600
Insurance - - - - - - - -
Repair & Maintenance - - - 1,545 1,590 1,635 1,680 6,450
Rent & Utilities - - - 7,210 7,420 7,630 7,840 30,100
Debt Service - - - - - - - -
OPERATING IMPACT - - - 10,815 11,130 11,445 11,760 45,150
FUNDED CAPITAL IMPROVEMENT
5 Year Projection
IMPACT ON OPERATING BUDGET
5 Year Projection
Trail - Fidelity Campus to Westlake Parkway on 114
PROJECT EXPENSE
5 Year Projection
PROJECT FUNDING
This project will provide connectivity from Hwy 114 to
Capital Parkway along the east side of Westlake Parkway.
DR
A
F
T
12
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - - 21,100 21,100
Construction - - - - - - 212,000 212,000
Design - - - - - - 43,000 43,000
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - - - - - 276,100 276,100
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bonds 2017/18 CO $2.6M - - - - - - 276,100 276,100
Unfunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - - - - - - 276,100 276,100
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - 3,360 3,360
Insurance - - - - - - - -
Repair & Maintenance - - - - - - 896 896
Rent & Utilities - - - - - - 8,960 8,960
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - - 13,216 13,216
FUNDED CAPITAL IMPROVEMENT
Trail - Westlake Academy to Cemetery
5 Year Projection
5 Year Projection
5 Year Projection
PROJECT EXPENSE
PROJECT FUNDING
IMPACT ON OPERATING BUDGET
This project will provide East to West interconnectivity
within the Westlake trail system. Includes a primitive trail
head on the Southeast corner of the cemetery property
(primitive parking, restroom and water fountain).
DR
A
F
T
13
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - 21,000 - 21,000
Construction - - - - - 210,000 - 210,000
Design - - - - - - - -
Contingency - - - - - 42,600 - 42,600
Other - - - - - - - -
EXPENDITURES TOTAL - - - - - 273,600 - 273,600
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bonds 2017/18 CO $2.6M - - - - - 273,600 - 273,600
Unfunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - - - - - 273,600 - 273,600
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - 924 1,035 1,959
Insurance - - - - - - - -
Repair & Maintenance - - - - - 4,044 4,529 8,573
Rent & Utilities - - - - - 8,720 8,960 17,680
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - 13,688 14,524 28,212
FUNDED CAPITAL IMPROVEMENT
5 Year Projection
PROJECT EXPENSE
5 Year Projection
Trail - Dove Road / Pearson Road / Aspen Lane
PROJECT FUNDING
5 Year Projection
IMPACT ON OPERATING BUDGET
This project will provide connectivity from Aspen Lane north
to Dove Road along the east side of Pearson Road. This
will include crosswalk devices at the corner of Dove and
Pearson. This project will be completed in conjunction with
the Pearson Lane Reconstruction & Drainage to keep costs
at a minimum.
DR
A
F
T
14
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - - - -
Construction - - - 60,000 60,000 60,000 60,000 329,050
Design - - - 15,750 - - - 15,750
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - - 63,000 31,800 125,000 125,000 344,800
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bond Issuance - - - - - - - -
Unfunded - - - 63,000 31,800 125,000 125,000 344,800
Other - - - - - - - -
FUNDING TOTAL - - - 63,000 31,800 125,000 125,000 344,800
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - 5,450 5,600 11,050
Insurance - - - - - - - -
Repair & Maintenance - - - - - 16,350 16,800 33,150
Rent & Utilities - - - - - - - -
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - 21,800 22,400 44,200
UNFUNDED (UNDER DISCUSSION) CAPITAL IMPROVEMENT
5 Year Projection
Cemetery Improvements
PROJECT EXPENSE
5 Year Projection
PROJECT FUNDING
5 Year Projection
IMPACT ON OPERATING BUDGET
These improvements will consist of section markers,
roadways and landscaping. The project also anticipates
a future trail head with rest facilities that will accomodate
the future cemetery/academy trail. Based on current
funding sources, this project will be dependent upon the
future sale of plots. The project would be completed in
four phases. Phase I & II road improvemants, Phase III &
IV landscape and trailer improvements.
DR
A
F
T
15
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - 60,000 60,000 - - 120,000
Construction - - - - 1,500,000 - - 1,500,000
Design - - - 60,000 60,000 - - 120,000
Contingency - - - - - - - -
Other - land purchase - - - 3,000,000 - - - 3,000,000
EXPENDITURES TOTAL - - - 3,120,000 1,620,000 - - 4,740,000
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bond Issuance - - - - - - - -
Unfunded - - - 3,120,000 1,620,000 - - 4,740,000
Other - - - - - - - -
FUNDING TOTAL - - - 3,120,000 1,620,000 - - 4,740,000
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - 2,725 2,800 5,525
Services - - - - - 16,350 16,800 33,150
Insurance - - - - - - - -
Repair & Maintenance - - - - - 2,725 2,800 5,525
Rent & Utilities - - - - - 8,720 8,960 17,680
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - 30,520 31,360 61,880
PROJECT FUNDING
5 Year Projection
IMPACT ON OPERATING BUDGET
5 Year Projection
UNFUNDED (UNDER DISCUSSION) CAPITAL IMPROVEMENT
10-20 Acre Community Park
This project would include the purchase of 10 to 20 acres
of open space with the ability to add amenities such as
small covered pavilions, trail head, playground stations,
sports fields, general use open spaces, dog park,
restroom and parking.
PROJECT EXPENSE
5 Year Projection
DR
A
F
T
16
FACILITIES OVERVIEW
Currently, The Town of Westlake owns
and operates three facilities: the
Westlake Academy, the temporary
buildings that house our emergency
services personnel and equipment,
and the Parchment house which is
currently being utilized for storage.
The Town also leases approximately
12,000 square feet of office space.
This Capital Improvement Plan
proposes increasing the number of
buildings on the Westlake Academy
campus as well as providing new
municipal buildings for staff and
community events.
Adopted Project
Projects to be completed in FY 13-14 and future years
• Westlake Academy – Phase I Expansion
Proposed Projects – CIP FY 13-18
• Outdoor Warning System
• WA - West Parking Improvements
Unfunded (Under Discussion) Projects
• Municipal Building
• Fire Station Complex
• Maintenance and Storage Facility
• WA - Sport field complex
• WA Phase II - 15 classroom Secondary Addition
• WA Phase II - 4 Classroom Kindergarten Addition
• WA Phase III - Art & Science Classrooms
• WA Phase III – Performing Arts Center
DR
A
F
T
17
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - 30,000 - - - - 30,000
Construction - - 170,000 - - - - 170,000
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - 200,000 - - - - 200,000
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - 200,000 - - - - 200,000
Contributions/Grants - - - - - - - -
Bond Issuance - - - - - - - -
Unfunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - - 200,000 - - - - 200,000
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - 250 258 265 273 280 1,325
Insurance - - - - - - - -
Repair & Maintenance - - 750 773 795 818 840 3,975
Rent & Utilities - - 1,000 1,030 1,060 1,090 1,120 5,300
Debt Service - - - - - - - -
OPERATING IMPACT - - 2,000 2,060 2,120 2,180 2,240 10,600
PROJECT FUNDING
5 Year Projection
IMPACT ON OPERATING BUDGET
5 Year Projection
FUNDED CAPITAL IMPROVEMENT
Westlake Academy - West Parking Improvements
The west parking area was constructed in the summer of
2006 as a temporary asphalt parking lot for pick-up and
drop-off of students. Improvements include curbs,
landscape islands, sidewalks and lighting. The parking lot
does not meet the required Town development standards
for new construction. The projected expense below includes
the following: curb only, lighting, landscaping, additional
two inches of asphalt, striping and marking.
PROJECT EXPENSE
5 Year Projection
DR
A
F
T
18
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - - - -
Construction - - - - - - - -
Design - - - - - - - -
Contingency - - - - - - - -
Other (Equipment) - - 99,000 - - - - 99,000
EXPENDITURES TOTAL - - 99,000 - - - - 99,000
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - 99,000 - - - - 99,000
Contributions/Grants - - - - - - - -
Bond Issuance - - - - - - - -
Unfunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - - 99,000 - - - - 99,000
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - - -
Insurance - - - - - - - -
Repair & Maintenance - - - 1,000 1,000 1,000 1,000 4,000
Rent & Utilities - - 300 600 900 900 900 3,600
Debt Service - - - - - - - -
OPERATING IMPACT - - 300 1,600 1,900 1,900 1,900 7,600
PROJECT FUNDING
5 Year Projection
IMPACT ON OPERATING BUDGET
5 Year Projection
FUNDED CAPITAL IMPROVEMENT
Outdoor Warning System
Promote Community Health, Safety, and Welfare is a focus point in the
Strategic Plan. Within that focus point is the Strategic Issue "Public
Safety and Emergency Preparedness" The strategy is to provide a safe
community for our residents and business partners. Building an effective
Emergency Warning Notification System will enhance the Town's ability to
ensure the safety of the community. An Outdoor Warning System will
provide notification of approaching severe storms to the active outdoor
population such as school children, joggers, golfers, workers, citizens
engaged in outdoor activities around their homes, etc.
PROJECT EXPENSE
5 Year Projection
DR
A
F
T
19
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering 43215 4,940 100,000 70,000 - - - - 174,940
Construction 46195 - 1,000,000 4,200,000 1,050,000 - - - 6,250,000
FF&E 47415 - - 800,000 - - - - 800,000
Design 43248 31,458 150,000 248,600 55,000 - - 485,059
Contingency 43520 - 49,500 390,000 - - - 439,500
Advertising 45405 - 500 - - - - - 500
Portables 73000 350,000 350,000
EXPENDITURES TOTAL 36,398 1,650,000 5,708,601 1,105,001 - - - 8,500,000
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers 36,398 (36,398) - - - - - -
Contributions/Grants - - - - - - - -
Bond Issuance $8.5M - 8,500,000 - - - - - 8,500,000
Unfunded - - - - - - - -
FUNDING TOTAL 36,398 8,463,602 - - - - 8,500,000
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - 10,000 10,600 11,236 11,910 12,625 56,371
Services - - 5,000 5,300 5,618 5,955 6,312 28,185
Insurance - - - 1,000 1,060 1,124 1,191 4,375
Repair & Maintenance - - 8,000 8,480 8,989 9,528 10,100 45,097
Rent & Utilities - - - 20,000 20,600 21,200 22,472 84,272
Misc - - 10,000 10,600 11,236 11,910 12,625 56,371
OPERATING IMPACT - - 33,000 55,980 58,739 61,627 65,325 274,671
PROJECT FUNDING
5 Year Projection
IMPACT ON OPERATING BUDGET (ACADEMY)
5 Year Projection
FUNDED CAPITAL IMPROVEMENT
Westlake Academy - Phase I Expansion
This project consists of the construction of three buildings: 1) Multi-
purpose hall, portable stage, storage and catering kitchen for dining and
general purposes at approx. 9,600 sf. 2) Three story Secondary School
at apprx. 18,900 sf. Includes 12 classrooms, flex and office space.
Designed to allow for future addition in needed. 3) Fieldhouse at approx.
9,600 sf. Will house locker rooms to be used for both athletics and PE,
storage for equipment, offices, classrooms and space to be used for the
PE program.
PROJECT EXPENSE
5 Year Projection
DR
A
F
T
20
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - 344,100 86,000 - - - 430,100
Construction - - - 2,890,100 - - - 2,890,100
Design - - - 166,000 - - - 166,000
Contingency - - - - - - - -
Other (FF&E) - - - 100,000 - - - 100,000
EXPENDITURES TOTAL - - 344,100 3,242,100 - - - 3,586,200
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bond Issuance - - - - - - - -
Unfunded - - 344,100 3,242,100 - - - 3,586,200
Other - - - - - - - -
FUNDING TOTAL - - 344,100 3,242,100 - - - 3,586,200
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - 6,180 2,000 2,000 2,240 12,420
Services - - - 8,240 8,480 8,720 8,960 34,400
Insurance - - - 515 530 545 560 2,150
Repair & Maintenance - - - - 24,380 25,070 25,760 75,210
Rent & Utilities - - - 5,150 21,200 21,800 22,400 70,550
Debt Service - - - - - - - -
OPERATING IMPACT - - - 20,085 56,590 58,135 59,920 194,730
UNFUNDED (UNDER DISCUSSION) CAPITAL IMPROVEMENT
5 Year Projection
Municipal Building
PROJECT EXPENSE
PROJECT FUNDING
IMPACT ON OPERATING BUDGET
5 Year Projection
5 Year Projection
This project consists of the construction of a new Town Hall that will serve
both staff and the community. The building will be 2 stories and
approximately 16,000 square feet in size contain all municipal functions,
including court. The total estimated construction cost is $3,500,000. This
would be a joint effort between the Entrada development and the Town.
DR
A
F
T
21
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - 52,500 21,100 - 73,600
Construction - - - - - 3,816,000 - 3,816,000
Design - - - - 319,500 215,000 - 534,500
Contingency - - - - - 50,160 - 50,160
Other - - - - - 696,300 - 696,300
EXPENDITURES TOTAL - - - - 372,000 4,798,560 - 5,170,560
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bond Issuance - - - - - - - -
Unfunded - - - - 372,000 4,798,560 - 5,170,560
Other - - - - - - - -
FUNDING TOTAL - - - - 372,000 4,798,560 - 5,170,560
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - 4,000 4,480 8,480
Services - - - - - 6,000 6,720 12,720
Insurance - - - - - 1,000 1,120 2,120
Repair & Maintenance - - - - - 52,320 53,760 106,080
Rent & Utilities - - - - - 15,000 16,800 31,800
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - 78,320 82,880 161,200
UNFUNDED (UNDER DISCUSSION) CAPITAL IMPROVEMENT
5 Year Projection
PROJECT FUNDING
IMPACT ON OPERATING BUDGET
Fire Station Complex
PROJECT EXPENSE
5 Year Projection
5 Year Projection
This project will provide a 14,000 square foot fire station including four
bays, sleeping area, meeting room, kitchen, storage and two offices.
Anticipate land to be contributed.
DR
A
F
T
22
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - - - -
Construction - - - - - - - -
Design - - - - - - - -
Contingency - - - - - - - -
Building retrofit - - - - - - 10,000 10,000
EXPENDITURES TOTAL - - - - - - 10,000 10,000
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bond Issuance - - - - - - - -
Unfunded - - - - - - 10,000 10,000
Other - - - - - - - -
FUNDING TOTAL - - - - - - 10,000 10,000
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - 5,000 5,000
Services - - - - - - 500 500
Insurance - - - - - - 500 500
Repair & Maintenance - - - - - - 2,000 2,000
Rent & Utilities - - - - - - 5,000 5,000
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - - 13,000 13,000
PROJECT FUNDING
5 Year Projection
IMPACT ON OPERATING BUDGET
5 Year Projection
UNFUNDED (UNDER DISCUSSION) CAPITAL IMPROVEMENT
Maintenance & Storage Facility
The proposed Maintenance and Public Works facility would utilize the
existing Fire Department engine bay once new permanent Fire Station has
been constructed.
PROJECT EXPENSE
5 Year Projection
DR
A
F
T
23
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - 54,500 56,000 110,500
Construction - - - - - - 2,800,000 2,800,000
Design - - - - - 29,250 - 29,250
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - - - - 83,750 2,856,000 2,939,750
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bond Issuance - - - - - - - -
Unfunded - - - - - 83,750 2,856,000 2,939,750
Other - - - - - - - -
FUNDING TOTAL - - - - - 83,750 2,856,000 2,939,750
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - 10,000 10,000
Services - - - - - - 20,000 20,000
Insurance - - - - - - 1,000 1,000
Repair & Maintenance - - - - - - 8,000 8,000
Rent & Utilities - - - - - - 15,000 15,000
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - - 54,001 54,001
UNFUNDED (UNDER DISCUSSION) CAPITAL IMPROVEMENT
5 Year Projection
Westlake Academy - Sports Field Complex
PROJECT EXPENSE
PROJECT FUNDING
IMPACT ON OPERATING BUDGET (ACADEMY)
5 Year Projection
5 Year Projection
This 12 -14 acre outdoor sports complex project would
include: one 11 man football field with a running track, cross
country trail, outdoor tennis and basketball courts,
baseball and softball fields. The project would include
restrooms, concession area with outdoor eating area and
parking. This facility would provide programs and activities
to the Westlake Community and Westlake Academy. Land
is anticipated to be donated.
DR
A
F
T
24
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - 56,343 111,331 - 167,674
Construction - - - - - 2,226,638 - 2,226,638
Design - - - - - 175,131 - 175,131
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - - - 56,343 2,513,100 - 2,569,443
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bond Issuance - - - - - - - -
Unfunded - - - - 56,343 2,513,100 - 2,569,443
Other - - - - - - - -
FUNDING TOTAL - - - - 56,343 2,513,100 - 2,569,443
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - 4,000 4,000
Services - - - - - - 20,000 20,000
Insurance - - - - - - 2,000 2,000
Repair & Maintenance - - - - - - 15,000 15,000
Rent & Utilities - - - - - 10,000 11,200 21,200
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - 10,000 52,200 62,200
UNFUNDED (UNDER DISCUSSION) CAPITAL IMPROVEMENT
5 Year Projection
Westlake Academy - Phase II - 15 Classroom Secondary Addition
PROJECT EXPENSE
PROJECT FUNDING
IMPACT ON OPERATING BUDGET (ACADEMY)
5 Year Projection
5 Year Projection
As part of Phase II of the Westlake Academy Master Plan,
this project includes a 15 classroom addition to the
Secondary School. The building will total approximately
11,000 sq. feet and will be attached onto the north side of
the existing building.
DR
A
F
T
25
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - 21,800 - 21,800
Construction - - - - - 991,900 - 991,900
Design - - - - - 9,920 - 9,920
Contingency - - - - - - - -
Other (FF&E) - - - - - 50,000 - 50,000
EXPENDITURES TOTAL - - - - - 1,023,620 - 1,073,620
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bond Issuance - - - - - - - -
Unfunded - - - - - 1,023,620 - 1,023,620
Other - - - - - - - -
FUNDING TOTAL - - - - - 1,023,620 - 1,023,620
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - 4,480 4,480
Services - - - - - - 11,200 11,200
Insurance - - - - - - 1,120 1,120
Repair & Maintenance - - - - - - 6,720 6,720
Rent & Utilities - - - - - - 4,480 4,480
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - - 28,000 28,000
UNFUNDED (UNDER DISCUSSION) CAPITAL IMPROVEMENT
Westlake Academy - Phase II - 4 Classroom Kindergarten Addition
PROJECT EXPENSE
5 Year Projection
PROJECT FUNDING
IMPACT ON OPERATING BUDGET (ACADEMY)
5 Year Projection
5 Year Projection
Per the Master Plan this project is part of Phase II. The
Kindergarten addition would be located east of the original
primary building. This would include: 4 classrooms with
individual restrooms in each room for a total of 4,600
square feet that will match existing exterior building
features.
DR
A
F
T
26
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - - 16,800 16,800
Construction - - - - - - 1,555,680 1,555,680
Design - - - - - - 155,600 155,600
Contingency - - - - - - - -
Other (FF&E) - - - - - - 150,000 150,000
EXPENDITURES TOTAL - - - - - - 1,878,080 1,878,080
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bond Issuance - - - - - - - -
Unfunded - - - - - - 1,878,080 1,878,080
Other - - - - - - - -
FUNDING TOTAL - - - - - - 1,878,080 1,878,080
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - 4,480 4,480
Services - - - - - - 11,200 11,200
Insurance - - - - - - 1,120 1,120
Repair & Maintenance - - - - - - 2,240 2,240
Rent & Utilities - - - - - - 4,480 4,480
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - - 23,520 23,520
UNFUNDED (UNDER DISCUSSION) CAPITAL IMPROVEMENT
5 Year Projection
Westlake Academy - Phase III - Arts & Science Classroom Addition
PROJECT EXPENSE
PROJECT FUNDING
IMPACT ON OPERATING BUDGET (ACADEMY)
5 Year Projection
5 Year Projection
As part of Phase III of the WA Master Plan. This would be
an additional 5,200 square foot single-story building
attached to the existing Sam & Margret Lee Arts and
Sciences Center. This addition would include 3 classrooms,
labs and offices.
DR
A
F
T
27
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - - 28,000 28,000
Construction - - - - - - 4,256,000 4,256,000
Design - - - - - - 425,600 425,600
Contingency - - - - - - 100,000 100,000
Other - - - - - - 425,000 425,000
EXPENDITURES TOTAL - - - - - - 4,809,600 4,809,600
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - 1,120,000 1,120,000
Bond Issuance - - - - - - - -
Unfunded - - - - - - 3,689,600 3,689,600
Other - - - - - - - -
FUNDING TOTAL - - - - - - 4,809,600 4,809,600
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - 5,600 5,600
Insurance - - - - - - 1,120 1,120
Repair & Maintenance - - - - - - - -
Rent & Utilities - - - - - - 4,480 4,480
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - - 11,200 11,200
UNFUNDED (UNDER DISCUSSION) CAPITAL IMPROVEMENT
5 Year Projection
Westlake Academy - Phase III - Performing Arts Center
PROJECT EXPENSE
PROJECT FUNDING
IMPACT ON OPERATING BUDGET (ACADEMY)
5 Year Projection
5 Year Projection
In the Phase III of the Westlake Academy Master Plan a
new 16,000 square feet auditorium is constructed with
raised stage, fixed seating, dressing rooms, lighting,
restroom, offices, and lobby. This building would be located
to the west of the Sam and Margaret Lee Art's & Sciences
Building. We anticipate the cost of the interior ammenities
to be provided through contributions/grants.
DR
A
F
T
28
TRANSPORTATION OVERVIEW
One of the major concerns for any
municipality is its infrastructure of
streets. With the approval of the
previous year’s CIP and
accompanying bond issuance, the
Council recently addressed many of
the most pressing street maintenance
concerns in Westlake; this type of
commitment is essential to maintain
these valuable Town assets
Adopted Projects – CIP FY 12-17
Projects to be completed in FY 12/13
• Streets Survey
• Stagecoach Hills Reconstruction/Drainage
• Roanoke Road Reconstruction/Drainage North
• Hwy 377 Westport Parkway Signal
• Westlake Portion of Hillwood Projects
On-Going Projects (FY 12/13 and beyond)
• FM1938 Streetscape Improvements
• SH114/Hwy170 Enhancements
• Roanoke Road Reconstruction/Drainage South
• Sam School Rd Reconstruction/Drainage
• Dove Rd Reconstruction/Drainage (Vaquero/Terra Bella)
Proposed Projects – CIP FY 13-19
• HWY 377 Landscape Improvements
• Ottinger Road Bridge Creek Crossing
• Ottinger Road Reconstruction & Drainage
• Wyck Hill Resurface
• Pearson Lane Reconstruction & Drainage
Unfunded (Under Discussion) Projects
• Dove & Randol Mill Traffic Circle
DR
A
F
T
29
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering 97,980 30,000 29,001 - - - - 156,981
Construction 840,096 45,000 1,211,878 739,100 253,100 - - 3,089,174
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL 938,076 75,000 1,240,878 739,100 253,100 - - 3,246,155
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers 938,076 75,000 - 567,100 253,100 - - 1,833,277
Contributions (Fidelity) - - 1,240,878 172,000 - - - 1,412,878
Bond Issuance - - - - - - - -
UnFunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL 938,076 75,000 1,240,878 739,100 253,100 - 3,246,155
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - - -
Insurance - - - - - - - -
Repair & Maintenance - - - - - - - -
Rent & Utilities (water only) - - 5,000 5,150 5,300 5,450 5,600 26,500
Debt Service - - - - - - -
OPERATING IMPACT - - 5,000 5,150 5,300 5,450 5,600 26,500
FUNDED CAPITAL IMPROVEMENT
FM 1938 Streetscape/Wayfinding
5 Year Projection
5 Year Projection
Project consist of the design and construction of landscape and hardscape improvements to
the FM 1938 corridor from SH 114 south to Randol Mill Road, including sidewalks, trailheads,
signage, rest areas, plantings, entry monuments. Per developer's agreements: Fidelity is to
provide funding for landscape enhancements to the median and ROW (est. $322K). The Town
is required to install sidewalk on the west side of FM 1938 from Dove to SH 114 per the Fidelity
developer's agreement at our cost. Utility relocations will be necessary to accomodate
construction, including adjusting manholes, fire hydrants, valves and meters as necessary.
Utility cost is for irrigation only. A reduction to the total project cost of $670,000 is due to a
direct payment to the contractor from TxDot in the form of a grant.
5 Year Projection
PROJECT FUNDING
PROJECT EXPENSE
IMPACT ON OPERATING BUDGETDR
A
F
T
30
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering 7,500 345,460 390,940 336,000 - - - 1,079,900
Construction - - - - - - - -
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL 7,500 345,460 390,940 336,000 - - - 1,079,900
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - 89,370 - - - - 89,370
Contributions/Grants - - - - - - - -
Bonds 2011 CO $2.095M 7,500 345,460 301,570 - - - - 654,530
Bonds 2014/15 CO $2.1M - - - 336,000 - - - 336,000
Other - - - - - - - -
FUNDING TOTAL 7,500 345,460 390,940 336,000 - - 1,079,900
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - 50,000 51,500 53,000 54,500 56,000 265,000
Insurance - - - - - - - -
Repair & Maintenance - - - - - - - -
Rent & Utilities - - 50,000 51,500 53,000 54,500 56,000 265,000
Debt Service - - - - - - -
OPERATING IMPACT - - 100,000 103,000 106,000 109,000 112,000 530,000
FUNDED CAPITAL IMPROVEMENT
SH 170 & Hwy 114 Streetscape
5 Year Projection
5 Year Projection
PROJECT FUNDING
5 Year Projection
IMPACT ON OPERATING BUDGET
This project would be a cooperative effort between Westlake, Trophy
Club, and Roanoke consisting of the design and construction of landscape
and hardscape improvements to the SH 170 & Hwy 114 interchange to
include plantings, painting, and entry monuments. Maintenance is for
irrigation only. Project costs are estimated to be $3,000,000 for
construction and $200,000 for engineering design. Funding participation
is anticipated to be 1/3 from each party.
PROJECT EXPENSE
DR
A
F
T
31
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering 2,900 - - 453,000 - - - 455,900
Construction - - - - - - - -
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL 2,900 - - 453,000 - - - 455,900
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bonds 2011 CO $2.095M 2,900 - - - - - - 2,900
Bonds 2014/15 CO $2.1M - - - 453,000 - - - 453,000
Other - - - - - - - -
FUNDING TOTAL 2,900 - - 453,000 - - 455,900
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - - -
Insurance - - - - - - - -
Repair & Maintenance - - - - - 4,796 4,928 9,724
Rent & Utilities - - - - - - - -
Debt Service - - - - - - -
OPERATING IMPACT - - - - - 4,796 4,928 9,724
FUNDED CAPITAL IMPROVEMENT
Roanoke Road Reconstruction and Drainage South
(Highway 170 south to Town limits)
PROJECT EXPENSE
5 Year Projection
PROJECT FUNDING
The project will provide stabilization of road subgrade and 6" of asphalt to
approximately 4,000 LF of Roanoke Road and replace/improve culverts
and ditches, consistent with 2011 Graham Pavement Evaluation Study.
Project improvements will be from Highway 170 south to the Town Limits.
Foresee crack sealing during the 2nd year after completion.
5 Year Projection
5 Year Projection
IMPACT ON OPERATING BUDGETDR
A
F
T
32
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - 41,800 - - - 41,800
Construction - - - 174,200 - - - 174,200
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - - 216,000 - - - 216,000
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bonds 2014/15 CO $2.1M - - - 216,000 - - - 216,000
Unfunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - - - 216,000 - - 216,000
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - - -
Insurance - - - - - - - -
Repair & Maintenance - - - - - 2,398 2,464 4,862
Rent & Utilities - - - - - - - -
Debt Service - - - - - - -
OPERATING IMPACT - - - - - 2,398 2,464 4,862
5 Year Projection
5 Year Projection
PROJECT FUNDING
IMPACT ON OPERATING BUDGET
FUNDED CAPITAL IMPROVEMENT
Sam School Road Reconstruction and Drainage
(Solana to Town limits)
PROJECT EXPENSE
5 Year Projection
The project will provide stabilization of road subgrade and 6" of asphalt to
approximately 2,000 LF of Sam School Road and replace/improve culverts
and ditches, consistent with 2011 Graham Pavement Evaluation Study.
Anticipate crack sealing 2nd year from completion.
DR
A
F
T
33
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - 105,000 - - - 105,000
Construction - - - 404,945 - - - 404,945
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - - 509,945 - - - 509,945
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bonds 2014/15 CO $2.1M - - - 509,945 - - - 509,945
Unfunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - - - 509,945 - - 509,945
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - 3,815 3,920 7,735
Insurance - - - - - - - -
Repair & Maintenance - - - - - - - -
Rent & Utilities - - - - - 10,900 11,200 22,100
Debt Service - - - - - - -
OPERATING IMPACT - - - - - 14,715 15,120 29,835
FUNDED CAPITAL IMPROVEMENT
Dove Road Reconstruction and Drainage
(Vaquero to Terra Bella)
PROJECT EXPENSE
5 Year Projection
PROJECT FUNDING
The project will provide stabilization of road subgrade and 6" of asphalt to
approximately 6,500 LF of Dove Road and replace/improve culverts and
ditches, consistent with 2011 Graham Pavement Evaluation Study.
Anticipate crack sealing 2nd year from completion.
5 Year Projection
5 Year Projection
IMPACT ON OPERATING BUDGETDR
A
F
T
34
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - - 100,000 100,000
Construction - - - - - - 600,000 600,000
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - - - - - 700,000 700,000
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bonds 2016/17 CO $2.6M - - - - - - 700,000 700,000
Unfunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - - - - - - 700,000 700,000
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - - -
Insurance - - - - - - - -
Repair & Maintenance - - - - - - 5,000 5,000
Rent & Utilities - - - - - - 10,000 10,000
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - - 15,000 15,000
PROJECT FUNDING
5 Year Projection
IMPACT ON OPERATING BUDGET
5 Year Projection
FUNDED CAPITAL IMPROVEMENT
Hwy 377 Landscape Improvements
The project will include streetscape enhancements
(hardscape, landscape) along US Hwy 377 starting at
Westport Parkway stretching north for 3/4 mile. The
enhancements will only be located in the median and
consist of native and naturalized plantings, trees, plant bed
preparations, drip irrigation, and concrete edging/mowstrip.
Since the project will be within state ROW, the Town will
submit this project to TxDOT for potential grant funding
opportunities similar to the FM 1938 median landscape
project.
PROJECT EXPENSE
5 Year Projection
DR
A
F
T
35
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - 80,000 - 80,000
Construction - - - - - 250,000 - 250,000
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - - - - 330,000 - 330,000
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bonds 2016/17 CO $2.6M - - - - - 330,000 - 330,000
UnFunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - - - - - 330,000 - 330,000
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - - -
Insurance - - - - - - - -
Repair & Maintenance - - - - - - - -
Rent & Utilities - - - - - - - -
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - - - -
5 Year Projection
FUNDED CAPITAL IMPROVEMENT
The bridge is located between the Westlake Cemetery and
SH 170. The 2012 TxDOT Bridge Inspection Report has
identified this bridge as failing, and has recommended it be
replaced. This project will replace the existing Ottinger
Road bridge with new box culvert, much like the Dove Road
improvements. Staff will need to determine through
engineering design analysis the final design criteria
including horizontal and vertical alignment.
PROJECT EXPENSE
5 Year Projection
IMPACT ON OPERATING BUDGET
Ottinger Road Bridge Creek Crossing
PROJECT FUNDING
5 Year Projection
DR
A
F
T
36
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - - 108,060 108,060
Construction - - - - - - 464,650 464,650
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - - - - - 572,710 572,710
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bonds 2016/17 CO $2.6M - - - - - - 572,710 572,710
UnFunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - - - - - - 572,710 572,710
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - - -
Insurance - - - - - - - -
Repair & Maintenance - - - - - - - -
Rent & Utilities - - - - - - - -
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - - - -
PROJECT FUNDING
5 Year Projection
IMPACT ON OPERATING BUDGET
5 Year Projection
FUNDED CAPITAL IMPROVEMENT
Ottinger Road Reconstruction and Drainage
(North of Westlake Academy)
The project will provide stabilization of road subgrade and
7" of asphalt to approximately 4,000 LF of Ottinger Road
(from Westlake Academy to SH 170) and replace/improve
culverts and ditches, consistent with 2011 Graham
Pavement Evaluation Study. Anticipate crack sealing
during the 2nd year after completion.
PROJECT EXPENSE
5 Year Projection
DR
A
F
T
37
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - 10,850 - 10,850
Construction - - - - - 43,600 - 43,600
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - - - - 54,450 - 54,450
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bonds 2016/17 CO $2.6M - - - - - 54,450 - 54,450
UnFunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - - - - - 54,450 - 54,450
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - - -
Insurance - - - - - - - -
Repair & Maintenance - - - - - - - -
Rent & Utilities - - - - - - - -
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - - - -
PROJECT FUNDING
5 Year Projection
IMPACT ON OPERATING BUDGET
5 Year Projection
FUNDED CAPITAL IMPROVEMENT
Wyck Hill Pavement Resurface
The project will provide asphalt pavement resurfacing to
approximately 1,000 LF of Wyck Hill, consistent with 2011
Graham Pavement Evaluation Study. Foresee crack
sealing during the 2nd year after completion.
PROJECT EXPENSE
5 Year Projection
DR
A
F
T
38
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - 54,250 - 54,250
Construction - - - - - 327,000 - 327,000
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - - - - 381,250 - 381,250
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bonds 2016/17 CO $2.6M - - - - - 381,250 - 381,250
UnFunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - - - - - 381,250 - 381,250
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - - -
Insurance - - - - - - - -
Repair & Maintenance - - - - - - - -
Rent & Utilities - - - - - - - -
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - - - -
PROJECT FUNDING
5 Year Projection
IMPACT ON OPERATING BUDGET
5 Year Projection
FUNDED CAPITAL IMPROVEMENT
Pearson Lane Reconstruction and Drainage
The project will provide stabilization of road subgrade and
5" of asphalt to approximately 1,300 LF of Pearson Lane
and replace/improve culverts and ditches, consistent with
2011 Graham Pavement Evaluation Study. Foresee crack
sealing during the 2nd year after completion.
PROJECT EXPENSE
5 Year Projection
DR
A
F
T
39
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - - - - - 465,000 465,000
Construction - - - - - - 900,000 900,000
Design - - - - - - 35,000 35,000
Contingency - - - - - - - -
Other - - - - - - 619,600 619,600
EXPENDITURES TOTAL - - - - - - 2,019,600 2,019,600
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - - - - - - -
Contributions/Grants - - - - - - - -
Bond Issuance - - - - - - - -
UnFunded - - - - - - 2,019,600 2,019,600
Other - - - - - - - -
FUNDING TOTAL - - - - - - 2,019,600 2,019,600
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - - -
Insurance - - - - - - - -
Repair & Maintenance - - - - - - 2,800 2,800
Rent & Utilities - - - - - - 5,600 5,600
Debt Service - - - - - - - -
OPERATING IMPACT - - - - - - 8,400 8,400
PROJECT FUNDING
5 Year Projection
IMPACT ON OPERATING BUDGET
5 Year Projection
UNFUNDED (UNDER DISCUSSION) CAPITAL IMPROVEMENT
Dove & Randol Mill Traffic Circle
Reconstruction and reconfiguration of Dove Road and
Randol Mill from a 3-way stop intersection to a traffic circle
to improve traffic safety. Pavement construction will be
consistent with 2011 Graham Pavement Evaluation Study.
PROJECT EXPENSE
5 Year Projection
DR
A
F
T
40
VEHICLE AND EQUIPMENT OVERVIEW
Vehicles and equipment represent
approximately 6% of the Town’s assets
or roughly $3.4M. While the current CIP
does not contain any proposals for
vehicles, it is important to note that of
the seven vehicles (including a utility
truck) the Town currently owns, three
are completely depreciated and three
more will become completely
depreciated within the next five years.
Similarly, of the fourteen FF&E asset
groups, eight are currently fully
depreciated and the remainder will be
within the next five years.
Whether or not an asset has been fully depreciated does not by itself warrant the need to
replace it, however, depreciation does serve as an indicator that the likelihood the asset
will need to be replaced in the near future is fairly high.
The Town maintains a General Maintenance & Replacement Fund and is working towards
funding annually for any replacement items needed in subsequent years. We anticipate
a replacement vehicle for the Parks and Recreation Department to be paid from the
funds that have been transferred to this fund for just this purpose.
Vehicle Description
Department
Cost
Date
Placed
in
Service
Useful
Life
Remaining
Life
Ambulance Fire 144,981 2003 10 -
Fire Truck Fire 236,423 2003 15 5
Fire Chief Vehicle Fire 41,108 2004 5 -
Command Vehicle Fire 49,084 2013 5 5
Ambulance Fire 200,000 2012 10 10
Fire Attack Truck Fire 169,746 2012 10 10
Spartran Senator II School Bus Academy 41,625 2010 5 3
Girardin18 Passenger Bus Academy 41,625 2010 5 3
Pool vehicle (Sold FY 12/13) General 8,500 2004 4 -
Chevy Silverado Truck Building 15,704 2005 5 -
Marshal's Vehicle Court 23,000 2007 5 -
Chevy Silverado Truck Public Works 11,105 2008 5 -
$ 982,901
DR
A
F
T
41
Capital Maintenance and Replacement
The Town recognizes that deferred maintenance and not anticipating capital
replacement needs increases future capital costs. Annually, available funds will be
evaluated during the budget process and a percentage of each operating fund’s
budget will be recommended to the Council for transfer. Upon approval by the Council,
the recommended amount will be transferred to the appropriate funds (General or Utility
Maintenance Replacement Fund) for major maintenance/ replacement of street, building
roof, flooring, air conditioning, equipment, etc.
The Town of Westlake owns, operates, and maintains a number of vehicles. To provide a
fiscally responsible vehicle and equipment replacement policy that enables the Town to
maximize vehicle and equipment utilization, while maintaining the Town’s desired public
image and high quality program of services for our residents. Therefore, the Town of
Westlake will maintain a Vehicle and Equipment Replacement and Depreciation
Schedule; said schedule will be maintained by the Finance Department.
Vehicle and equipment replacement criteria will be developed according to each items
anticipated useful service life. Typically, this is based upon the type or “category” of the
vehicle/equipment and its usage. Each item will be surveyed annually and assigned a
score based upon the Point Range and Guideline document. A vehicle will be replaced
according to the established criteria unless the Department Head(s) and the Town
Manager’s office determine that: 1) mechanical failure or vehicle damage warrants
earlier replacement, or 2) the vehicle is still serviceable and may serve additional years
beyond its original anticipated service life.
Funding for vehicle/equipment replacement should be incrementally allocated from
department operating funds to a restricted Capital Maintenance and Replacement Fund,
subject to funding availability on an annual basis. Future vehicle/equipment
replacements should be funded from this restricted fund, which receives accumulated
operating fund transfers based upon the Vehicle and Equipment Depreciation Schedule.
Funding will consist of an annual set-aside based upon a straight-line depreciation for
each vehicle over the course of its useful life and budgeted as part of the annual budget
development process.
Depreciation fees should commence the same fiscal year of each new and replacement
vehicle/equipment purchase. Likewise, depreciation expenses should be expensed from
the respective department operating budget and deposited into the Capital
Maintenance and Replacement Fund. Depreciation expenses shall continue through the
service life of the new vehicle/equipment and shall cease upon retirement of said
vehicle/equipment.
DR
A
F
T
42
Vehicle and Equipment Replacement and Depreciation Guidelines
Purpose: To provide a fiscally responsible vehicle and equipment replacement and
depreciation policy, which will enable the Town of Westlake to maximize asset utilization
while maintaining a positive public image and being fiscally responsible in our budgeting
and fleet replacement programs.
Policy: Replacement criteria for Town-owned vehicles and equipment will depend
primarily on a point system, which is based upon the following factors:
• Age
• Miles/Hour Usage
• Type of Service
• Reliability
• Maintenance and Repair Costs (not to include incident repairs)
• Condition
Point Range Chart Note: The Town may decide to retain a vehicle beyond the stated
criteria after an evaluation of anticipated usage, repairs and operating costs. Each Town
vehicle and small equipment have been placed in a specific category (as listed below)
in order to allow for uniformity in our replacement standards.
Category "A"
This category consists of the one (1) 18-passenger and one (1) 20-passenger school
bus. The life span for school bus is 10 years. The Fire Department which includes
engines, ladder truck, ambulances, and attack truck which are used primarily as a
front-line response vehicle. The front-line life-span of the Engine is 15 years and has a
reserve life-span for additional five years. The ambulance front-line life-span is seven
years and has a reserve vehicle life-span for additional seven. The Town currently has
one (1) Engine, one (1) Attack Truck and two (2) Ambulances.
Category "B"
This category consists of Maintenances and Public Works vehicles which are used to serve
the public on a day-to-day basis and pull trailers. Due to the heavy use, these vehicles
may be scheduled for replacement at 100,000 miles provided the maintenance cost is
considerably higher than vehicles of the same type. The Town currently has two (2) Public
Works trucks.
Category "C"
This category consists of all other cars and pickups, which include administration pool car,
building inspection truck, warrant officer public safety vehicle. These vehicles are
generally assigned to a designated staff member and should not be replaced earlier than
100,000 miles provided the maintenance cost is considerably higher than vehicles of the
same type.
DR
A
F
T
43
Category "D"
This category consists of other off-road equipment (mule and mowers) that are used to
serve the public on an "as needed" basis. Replacement of this category may be made
after 2,500 operating hours, or provided the maintenance cost is considerably higher than
equipment of the same type. The Town currently has one (1) Kawasaki utility vehicle and
(1) mower.
Category "E"
This category consists of light equipment (weed-eaters, chain saw and pumps,
generators, trailers, and other small hand-operated equipment) which are used to serve
the public on an "as needed" basis. Replacements in this category may be made after
the total maintenance cost exceeds the original purchase price of a particular piece of
equipment. The cost of upgrading a piece of equipment will be the responsibility of the
operating division. The Town currently has one weed-trimmer, chain saw, blower, small
generator and a trailer.
Guide for Early Replacement of Town-Owned Vehicles
Early Replacement
The consideration of early replacement of a vehicle often arises when major expenditures
are necessary to restore it to a safe operating condition (e.g., major component failure
or incident damage). The economic effect of such repairs cannot be avoided because
the cost to the Town is normally about the same whether the vehicle is sold in un-repaired
condition or restored to repaired condition.
However, replacement prior to the normal criteria for vehicles will result in an acceleration of
all future replacement cost cycles required to satisfy a continuing vehicle need. This
acceleration of cost cycles causes a sizable increase in the total present value cost of all
fixture cycles and should be avoided whenever possible. Major vehicle repairs should
always be made, with two exceptions:
1. Major expenditures for repair should not be made when the cost of the repair
plus the vehicle salvage in un-repaired condition exceeds its wholesale value in
repaired condition.
2. Major deferrable expenditures should not be made when a vehicle is in the final six
months of its retention cycle. During this period the penalty for early replacement
is small and, therefore, the vehicle should be replaced rather than repaired.
Depreciation Formula
Current acquisition price of each vehicle divided by the utilization cycle mileage or
total maintenance cost) will provide the yearly depreciation allowance.
EXAMPLE A – Vehicles
Mileage: $30,000.00 vehicle divided by the target replacement cycle of 100,000
miles will give you a depreciation cost of $.30 per mile.
$0.30 times the number of miles (20,000) the vehicle was driven the previous year
will give you the yearly depreciation amount $6,000.00.
DR
A
F
T
44
EXAMPLE B – Small Equipment
Maintenance Cost: depreciate the original purchase price by 15% per year, for
power hand tools, trailers, etc. Replace the item only when the maintenance cost
reaches the original purchase price.
Point Ranges for Replacement Consideration
Point Scale Condition Description
20 points & under Excellent Do not replace
21 to 25 points Very Good Re-evaluate for the following year's budget
26 to 31 points Fair Qualifies for replacement if M/R cost exceed 60% of cost
32 to 37 point Poor Replacement if budget allows
Above 38 points failed Needs priority replacement
Below are two examples on how the point range and guidelines for Category "B" and “C”
would work with current town vehicles.
Example: Pool Vehicle
Data Description Points
Year 1999 26 points
Type Crown Victoria Passenger Car 1 point
Mileage 64,000 6 points
Maintenance Repair driver side window motor 2 points
Condition Poor paint and body condition, hail
damage, rust spots, small dents, interior -
rips, tears, stains, cracking on seat covers
5 points
Total Points 40 points
Staff recommendation = Replacement this year
Data Description Points
Year 2005 14 points
Type Silverado F150 extended cab truck 1 point
Mileage 35,000 3 points
Maintenance low 1 points
Condition Very good exterior and interior condition 1 points
Total Points 20 points
Staff recommendation = Include the replacement cost in the five year forecast
DR
A
F
T
45
Point range and guidelines for Category "B" and “C”
Factor Points Description
Age Usage Type
of Service
1 Each 10,000 miles of usage
1 Standard sedans, SUV’s and pickups
2 Each year of chronological age
3 Any vehicle that pulls trailer, hauls heavy loads and continued off-
road usage
4 Any vehicle involved in ice or snow removal or road treatment
Reliability
Preventive
Maintenance
Work Not
Included
1 In shop one time within three month time period, no major
breakdowns/road side assistance call with 3 month period
2 In shop one time within three month time period, 1 breakdown/
road side assistance call within 3 month period
3 In shop more than once within 3 month time period, 1 or more
breakdown/road side assistance call within same period
4 In shop more than twice within one month time period, 1 or more
breakdowns/road side assistance call in same time period
5 Two or more breakdowns within one month time period
M&R Cost
Incident Repair
Not Include
1 Maintenance cost are less than or equal to 20% of replacement
2 Maintenance cost are 21-40% of replacement cost
3 Maintenance cost are 41-60% of replacement cost
4 Maintenance cost are 61-80% of replacement cost
5 Maintenance cost are greater than or equal to 81% of
replacement cost
Condition 1 No visual damage or rust
2 Minor imperfections in body and paint, interior fair (no rips, tears,
burn)
3 Noticeable imperfections in body and paint surface, minor rust,
minor damage for add-on equipment, won interior (one or more
rips, tears, burns).
4 Poor paint and body condition, rust (holes), interior (rips, tears,
burns, cracked dash) and major damage for add-on equipment
5 Previous accident damage, poor paint and body condition, rust
(holes), interior (rips, tears, burns, cracked dash) and major
damage for add-on equipment
Point Ranges Condition Description
0-20 Excellent Do not replace
21-25 Very
Good
Re-evaluate for next year’ budget (5 year forecast)
26-31 Good Qualifies for replacement this year if M/R cost exceed 60% of cost
32-37 Fair Qualities for replacement this if budget allows
38+ Poor Needs priority
DR
A
F
T
46
UTILITY IMPROVEMENTS OVERVIEW
The Town of Westlake currently owns
a minimum of approximately $24M
of utility fixed assets. These take the
form of water, sewer and
telecommunications duct bank lines.
These assets are initially installed
through development and later
transferred to the Town for upkeep
and maintenance.
With the recent completion of the
Stagecoach Hills water main, the
Town’s utility infrastructure is in
relatively good shape with no known
deficiencies. The five items that are
fully depreciated are water lines that
were transferred from the City of
Keller which may need replacement
in the near future but are fully
operational now. It should also be noted that the Town is currently engineering a GIS
system that will map all infrastructure; this project provides us the opportunity to review the
condition of these assets and their values which will be revised as necessary.
Adopted Projects – CIP FY 12-17
Projects to be completed in FY 12-13
• N1 Sewer Line Transfer I&I Repairs
• Stagecoach Hills Waterline Phase II
Projects to be completed in FY 13-14
• Ground Storage Tank
• N1 Sewer Line Transfer
Unfunded (Under Discussion) Projects
• There are no unfunded projects
DR
A
F
T
47
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering - - 12,467 - - - - 12,467
Construction - - 70,500 - - - - 70,500
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL - - 82,967 - - - - 82,967
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers - - 82,967 - - - - 82,967
Contributions/Grants - - - - - - - -
Bond Issuance - - - - - - - -
UnFunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL - - 82,967 - - - 82,967
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - - -
Insurance - - - - - - - -
Repair & Maintenance - - - - - - - -
Rent & Utilities - - - - - - - -
Debt Service - - - - - - -
OPERATING IMPACT - - - - - - -
FUNDED CAPITAL IMPROVEMENT
TRA Assumption of N-1 Sewer Line
PROJECT EXPENSE
5 Year Projection
PROJECT FUNDING
This project is intended to transfer ownership of a section of sewer line
from Westlake and Southlake to TRA. It includes the design and
construction of a metering station with SCADA equipment at the proposed
Town of Westlake "Point of Entry." Westlake will be required to conduct
an extensive inflow and infiltration study and perform repairs (separate
capital improvement).
5 Year Projection
5 Year Projection
IMPACT ON OPERATING BUDGETDR
A
F
T
48
Project Description:
Totals Thru Estimated Project
EXPENDITURE TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Engineering 3,088 47,800 1,449,113 - - - - 1,500,001
Construction - - - - - - - -
Design - - - - - - - -
Contingency - - - - - - - -
Other - - - - - - - -
EXPENDITURES TOTAL 3,088 47,800 1,449,113 - - - - 1,500,001
Totals Thru Estimated Project
FUNDING TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Cash/Transfers 3,088 (3,088) 500,000 - - - - 500,000
Contributions/Grants - - - - - - - -
Bond Issuance $1.0M - 50,888 949,113 - - - - 1,000,000
UnFunded - - - - - - - -
Other - - - - - - - -
FUNDING TOTAL 3,088 47,800 1,449,113 - - - 1,500,000
Totals Thru Estimated Project
IMPACT TYPE FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17 FY 17/18 Total
Supplies - - - - - - - -
Services - - - - - - - -
Insurance - - - - - - - -
Repair & Maintenance - - - 500 530 545 560 2,135
Rent & Utilities - - - - - - - -
Debt Service - - - - - - -
OPERATING IMPACT - - - 500 - - 2,135
FUNDED CAPITAL IMPROVEMENT
Ground Storage Tank
PROJECT EXPENSE
5 Year Projection
PROJECT FUNDING
This project will consist of designing and constructing a new ground
storage tank at the existing pump station. We anticipate this tank will be a
1,000,000 gallon tank and will be needed to augment services once
Deloitte has become fully staffed. Maintenance (consisting of inspection
and cleaning) would not be expected until year two. Total amount =
$1,558,500; Debt service payments = approximately $170k/yr for 10 years.
5 Year Projection
5 Year Projection
IMPACT ON OPERATING BUDGETDR
A
F
T
49
DR
A
F
T
50
DR
A
F
T
Debt Service Obligations by Fiscal Year and Type
Principal Amounts Only
Debt per
Capita
Estimated
Population
per CAFR Fiscal
2002 WA
Construction
2003 WA
Construction
2007
Refunding
02 only
2008 A & S
Center
2011 Street
Improvements
2011
Refunding
02 & 03
2013
Refunding
03 & 08
2013 WA
Expan & UF
Tank
2015 Parks,
Trails, Streets
2017 Trails
and Streets TOTAL
Fiscal Year
Principal
Payment
$65,087 289 FY 02/03 12,400,000 6,410,000 - 18,810,000 -
$62,079 303 FY 03/04 12,400,000 6,410,000 - 18,810,000 -
$57,348 328 FY 04/05 12,400,000 6,410,000 - 18,810,000 350,000
$52,000 355 FY 05/06 12,190,000 6,270,000 - 18,460,000 370,000
$27,393 698 FY 06/07 5,630,000 6,125,000 7,365,000 19,120,000 6,805,000
$30,192 703 FY 07/08 5,395,000 5,980,000 7,350,000 2,500,000 21,225,000 420,000
$26,382 785 FY 08/09 5,145,000 5,830,000 7,330,000 2,405,000 20,710,000 515,000
$25,137 803 FY 09/10 4,880,000 5,675,000 7,310,000 2,320,000 20,185,000 525,000
$25,649 847 FY 10/11 4,600,000 5,515,000 7,285,000 2,230,000 2,095,000 21,725,000 555,000
$21,822 992 FY 11/12 645,000 2,225,000 7,260,000 2,135,000 2,007,000 7,375,000 21,647,000 7,453,000
$29,795 1014 FY 12/13 330,000 2,055,000 7,235,000 - 1,917,000 7,275,000 2,080,000 9,320,000 30,212,000 2,955,000
$28,584 1024.14 FY 13/14 - 1,880,000 7,200,000 - 1,824,000 7,175,000 1,975,000 9,220,000 29,274,000 938,000
$29,232 1034.3814 FY 14/15 - 1,695,000 7,165,000 - 1,727,000 6,735,000 1,855,000 9,025,000 2,035,545 30,237,545 1,126,719
$27,843 1044.7252 FY 15/16 - 1,505,000 6,755,000 - 1,627,000 6,635,000 1,755,000 8,830,000 1,980,826 29,087,826 1,171,607
$27,474 1055.1725 FY 16/17 - - 6,330,000 - 1,552,000 6,360,000 1,625,000 8,630,000 1,904,220 2,588,110 28,989,330 1,251,179
$0
$4
$8
$12
$16
$20
$24
$28
$32
FY 02/03 FY 03/04 FY 04/05 FY 05/06 FY 06/07 FY 07/08 FY 08/09 FY 09/10 FY 10/11 FY 11/12 FY 12/13 FY 13/14 FY 14/15 FY 15/16 FY 16/17
$12.40 $12.40 $12.40 $12.19
$5.63 $5.40 $5.15 $4.88 $4.60
$6.41 $6.41 $6.41 $6.27
$6.13 $5.98 $5.83 $5.68 $5.52
$2.23 $2.06 $1.88 $1.70 $1.51
$7.37 $7.35 $7.33 $7.31 $7.29
$7.26 $7.24 $7.20 $7.17 $6.76
$6.33
$2.50 $2.41 $2.32 $2.23
$2.14
$2.10
$2.01
$1.92 $1.82 $1.73
$1.63
$1.55
$7.38
$7.28
$7.18 $6.74
$6.64
$6.36
$2.08
$1.98
$1.86
$1.76
$1.63
$9.32
$9.22
$9.03
$8.83
$8.63
$2.04
$1.98
$1.90
$2.59
Mi
l
l
i
o
n
s
Debt Service Obligations by Fiscal Year & Type
(Principal Amounts Only)
2017 Trails and
Streets
2015 Parks, Trails,
Streets
2013 WA Expan & UF
Tank
2013 Refunding 03 &
08
2011 Refunding 02 &
03
2011 Street
Improvements
2008 A & S Center
2007 Refunding 02
only
2003 WA
Construction
2002 WA
Construction
Debt Service Fund
Long-Term Debt Summary
Pym
t Fiscal 300.48840.00.
17
300.48850.00.
17
300.48840.00.
15
300.48850.00.
15
300.48840.00.
13
300.48850.00.
13
300.48840.00.
12
300.48850.00.
12
300.48840.00.
11
300.48850.00.
11
No.Year Principal Interest Principal Interest Principal Interest Principal Interest Principal Interest
1 2014 - - - - - - 105,000 46,700 151,700 100,000 407,159 507,159 93,000 60,791 153,791
2 2015 - - - 54,719 89,608 144,327 120,000 44,450 164,450 195,000 312,044 507,044 97,000 57,704 154,704
3 2016 - - - 76,607 67,578 144,184 100,000 42,250 142,250 195,000 308,144 503,144 100,000 54,503 154,503
4 2017 69,573 113,933 183,506 76,607 65,663 142,269 130,000 39,950 169,950 200,000 304,194 504,194 75,000 79,475 154,475
5 2018 97,402 85,922 183,324 87,550 63,611 151,161 125,000 37,400 162,400 200,000 300,194 500,194 79,000 75,625 154,625
6 2019 97,402 83,487 180,889 87,550 61,422 148,972 135,000 34,463 169,463 205,000 296,144 501,144 83,000 71,575 154,575
7 2020 111,317 80,878 192,195 87,550 59,233 146,784 140,000 31,025 171,025 215,000 291,944 506,944 87,000 67,325 154,325
8 2021 111,317 78,096 189,412 87,550 57,045 144,595 145,000 27,463 172,463 215,000 287,106 502,106 91,000 62,875 153,875
9 2022 111,317 75,313 186,629 87,550 54,637 142,187 145,000 23,838 168,838 225,000 281,606 506,606 96,000 58,200 154,200
10 2023 111,317 72,530 183,846 98,494 51,846 150,340 150,000 20,375 170,375 230,000 275,344 505,344 101,000 53,275 154,275
11 2024 111,317 69,468 180,785 98,494 48,645 147,139 145,000 17,130 162,130 240,000 268,294 508,294 106,000 48,100 154,100
12 2025 125,231 65,920 191,151 98,494 45,198 143,692 155,000 13,830 168,830 240,000 261,094 501,094 111,000 42,675 153,675
13 2026 125,231 61,850 187,081 109,438 41,559 150,997 165,000 10,063 175,063 255,000 253,669 508,669 117,000 36,975 153,975
14 2027 125,231 57,467 182,698 109,438 37,729 147,167 160,000 6,000 166,000 260,000 245,619 505,619 123,000 30,975 153,975
15 2028 139,146 52,841 191,986 109,438 33,762 143,199 160,000 2,000 162,000 270,000 237,006 507,006 129,000 24,675 153,675
16 2029 139,146 47,970 187,116 120,382 29,452 149,834 - - - 390,000 225,794 615,794 136,000 18,050 154,050
17 2030 139,146 42,926 182,072 120,382 24,788 145,169 - - - 405,000 211,881 616,881 143,000 11,075 154,075
18 2031 153,060 37,448 190,508 120,382 19,972 140,354 - - - 415,000 197,531 612,531 150,000 3,750 153,750
19 2032 153,060 31,517 184,577 131,325 14,938 146,264 - - - 595,000 178,369 773,369 - - -
20 2033 153,060 25,394 178,454 131,325 9,357 140,682 - - - 315,000 160,169 475,169 - - -
21 2034 166,975 18,993 185,968 142,269 3,201 145,470 - - - 330,000 147,269 477,269 - - -
22 2035 166,975 11,897 178,872 - - - - - - 345,000 133,769 478,769 - - -
23 2036 180,889 4,070 184,959 - - - - - - 360,000 119,669 479,669 - - -
24 2037 - - - - - - - - - 370,000 105,763 475,763 - - -
25 2038 - - - - - - - - - 385,000 92,078 477,078 - - -
26 2039 - - - - - - - - - 400,000 77,850 477,850 - - -
27 2040 - - - - - - - - - 415,000 62,300 477,300 - - -
28 2041 - - - - - - - - - 430,000 45,400 475,400 - - -
29 2042 - - - - - - - - - 450,000 27,800 477,800 - - -
30 2043 - - - - - - - - - 470,000 9,400 479,400 - - -
$2,588,110 $1,117,921 $3,706,031 $2,035,545 $879,243 $2,914,788 $2,080,000 $396,935 $2,476,935 $9,320,000 $6,124,599 $15,444,599 $1,917,000 $857,623 $2,774,623
SERIES 2013 COSeries
Type
Funded by
Use:Partial refunding of 2003 & 2008 Various street projectsWA Expansion / Ground Storage Tank
Issue Date:April 2013 March 29, 2011April 2013Fiscal Year 2017
Original Issue:$2,200,000 $2,095,000$9,500,000$2,588,110
Issued By: US Bank Independent Bank US Bank
TOTAL
4B Fund & General Fund DS 300 Property Tax4B Fund & General Fund
TOTAL TOTAL TOTAL
*partial refunding of 2003/2008 Certificates of ObligationCertificates of Obligation
SERIES 2013 GO-Refunding SERIES 2011 CO
Trails and Streets
UNKNOWN
PROPOSED
SERIES 2015 CO
Certificates of Obligation
4B Fund & General Fund
TOTAL
$2,035,545
Fiscal Year 2015
Parks, Trails and Streets
UNKNOWN
PROPOSED
SERIES 2017 CO
Certificates of Obligation
4B Fund & General Fund
TOTAL
Pym
t Fiscal
No.Year
1 2014
2 2015
3 2016
4 2017
5 2018
6 2019
7 2020
8 2021
9 2022
10 2023
11 2024
12 2025
13 2026
14 2027
15 2028
16 2029
17 2030
18 2031
19 2032
20 2033
21 2034
22 2035
23 2036
24 2037
25 2038
26 2039
27 2040
28 2041
29 2042
30 2043
Series
Type
Funded by
Use:
Issue Date:
Original Issue:
Issued By:
TOTAL
300.48840.00.
10
300.48850.00.
10
300.48840.00.
07
300.48850.00.
07
300.48840.00.
03
300.48850.00.
03
300.48840.00.
02
300.48850.00.
02
Principal Interest Principal Interest Principal Interest Principal Interest Principal Interest Total Debt
100,000 223,200 323,200 35,000 294,608 329,608 175,000 97,411 272,411 330,000 21,450 351,450 938,000 1,151,319 2,089,319
440,000 217,800 657,800 35,000 293,295 328,295 185,000 90,630 275,630 - - - 1,126,719 1,105,530 2,232,249
100,000 212,400 312,400 410,000 291,983 701,983 190,000 83,230 273,230 - - - 1,171,607 1,060,087 2,231,693
275,000 207,275 482,275 425,000 276,608 701,608 - 75,250 75,250 - - - 1,251,179 1,162,347 2,413,526
700,000 192,650 892,650 40,000 259,608 299,608 - 75,250 75,250 - - - 1,328,952 1,090,260 2,419,212
715,000 171,425 886,425 40,000 258,008 298,008 - 75,250 75,250 - - - 1,362,952 1,051,773 2,414,726
730,000 149,750 879,750 45,000 256,408 301,408 - 75,250 75,250 - - - 1,415,867 1,011,813 2,427,680
750,000 127,550 877,550 50,000 254,608 304,608 - 75,250 75,250 - - - 1,449,867 969,991 2,419,858
770,000 104,750 874,750 55,000 252,608 307,608 - 75,250 75,250 - - - 1,489,867 926,201 2,416,068
790,000 81,350 871,350 60,000 250,408 310,408 - 75,250 75,250 - - - 1,540,811 880,377 2,421,188
820,000 55,150 875,150 65,000 248,008 313,008 - 75,250 75,250 - - - 1,585,811 830,045 2,415,856
260,000 36,250 296,250 645,000 245,408 890,408 - 75,250 75,250 - - - 1,634,725 785,624 2,420,350
260,000 27,150 287,150 670,000 219,608 889,608 - 75,250 75,250 - - - 1,701,669 726,123 2,427,792
275,000 17,100 292,100 700,000 192,808 892,808 - 75,250 75,250 - - - 1,752,669 662,947 2,415,616
290,000 5,800 295,800 730,000 164,808 894,808 - 75,250 75,250 - - - 1,827,584 596,141 2,423,725
- - - 760,000 134,695 894,695 350,000 75,250 425,250 - - - 1,895,527 531,212 2,426,739
- - - 790,000 103,345 893,345 365,000 57,750 422,750 - - - 1,962,527 451,765 2,414,293
- - - 825,000 70,560 895,560 385,000 39,500 424,500 - - - 2,048,442 368,761 2,417,203
- - - 855,000 35,910 890,910 405,000 20,250 425,250 - - - 2,139,386 280,984 2,420,369
- - - - - - - - - - - - 599,386 194,920 794,306
- - - - - - - - - - - - 639,244 169,463 808,707
- - - - - - - - - - - - 511,975 145,666 657,641
- - - - - - - - - - - - 540,889 123,739 664,628
- - - - - - - - - - - - 370,000 105,763 475,763
- - - - - - - - - - - - 385,000 92,078 477,078
- - - - - - - - - - - - 400,000 77,850 477,850
- - - - - - - - - - - - 415,000 62,300 477,300
- - - - - - - - - - - - 430,000 45,400 475,400
- - - - - - - - - - - - 450,000 27,800 477,800
- - - - - - - - - - - - 470,000 9,400 479,400
$7,275,000 $1,829,600 $9,104,600 $7,235,000 $4,103,285 $11,338,285 $2,055,000 $1,367,021 $3,422,021 $330,000 $21,450 $351,450 $34,835,655 $16,697,678 $51,533,333
Bank of New York
Partial refunding of 2002 & 2003
Certificates of Obligation
4B Fund 200
SERIES 2011 GO-Refunding
TOTAL TOTAL
Bank of New York
$6,410,000 $12,400,000
January 15, 2002
2nd phase construction of WA 1st phase construction of WA
June 23, 2003
Partial refunding of Series 2002
March 15, 2007December 29, 2011
$7,465,000$7,375,000
US Bank US Bank
TOTAL GRAND TOTALTOTAL
Certificates of Obligation*partial refunding of 2002/2003 *partial refunding of 2002
4B Fund 2004B Fund & General Fund4B Fund & General Fund
SERIES 2002 COSERIES 2007 GO-Refunding SERIES 2003 CO