2. Precinct Line Road Construction — Mid-Range Goal.
Team Leader: Jarrod Greenwood
Strategic Plan Page Number: 8
Progress to Date: Conducted stakeholder meetings. Project bid in Summer 2010
Timeline/Schedule: On schedule
Future Progress: TxDOT to begin construction Spring 2010 and complete by Winter
2011
Outcome Strategies:
2.Review the drainage and storm water plans needed to minimize the impact of severe
weather on our neighborhoods — Short-Range Goal.
Team Leader: Jarrod Greenwood
Strategic Plan Page Number: 17
Timeline/Schedule: N/A
Progress to Date: Completed Stagecoach Drainage Improvement project Fall 2009
Future Progress: N/A
Vision Point
Two
We are Leaders
Key Result Area: Infrastructure Maintenance and Planning
Vision Point
One
Inviting Residential and Corporate Neighborhoods
Key Result Area: Outstanding Community Appearance
Outcome Strategies:
1. Streetscape projects to enhance community appearance — Short-Range
Goal.
Team Leader: Jarrod Greenwood
Strategic Plan Page Number: 9
Progress to Date: Met with stakeholders to gain consensus. Continue to meet
with PAC regarding public art opportunities along FM 1938.
Timeline/Schedule: On schedule
Future Progress: Streetscape Master plan needs to be adopted by Town Council.
Outcome Strategies:
1. Develop a comprehensive automated recycling and composting program to
identify new technology which may be utilized in our environmental
stewardship — Short-Range and On-going Goals.
Team Co -Leaders: Jarrod Greenwood/Troy Meyer
Strategic Plan Page Number: 13-14
Progress to Date: Implemented recycling at all town facilities and produced
several water conservation messages through various mediums
Timeline/Schedule: On schedule
Future Progress: Establish Westlake Green Team; survey of surrounding recycling
and composting programs; interact with Westlake Academy to assist with water
Vision Point
Two
We are Leaders
Key Result Area: Environmental Stewardship Initiatives
Outcome Strategies:
2. Review the drainage and storm water plans needed to minimize the impact
of severe weather on our neighborhoods — Short-Range Goal.
Team Leader: Jarrod Greenwood
Strategic Plan Page Number: 17
Progress to Date: Completed Stagecoach Drainage Improvement project Fall 2009
Timeline/Schedule: N/A
Future Progress: N/A
Vision Point
Two
We are Leaders
Key Result Area: Infrastructure Maintenance and Planning
Outcome Strategies:
3. Storm Water Utility review — Short Range Goal.
Team Leader: Jarrod Greenwood
Strategic Plan Page Number: 17
Progress to Date: Met with Town Engineer to identify drainage issues
Timeline/Schedule: On schedule
Future Progress: Will present drainage issues and potential costs to remedy at
future workshop.
Vision Point
Two
We are Leaders
Key Result Area: Infrastructure Maintenance and Planning