Loading...
HomeMy WebLinkAboutPresentation Arts Sciences budget updateSam & Margaret Lee Arts and Sciences Center Budget Update October 26, 2009 Mile Stones •May 2007 - Gideon Toal was selected as the Architect •June 2007 - Location selected for the A& S Center •November 2007- 2.5M bond passed •April 2008 - Steele & Freeman the CM at Risk was selected •June 2008 - Ground Breaking Ceremony •July 2008 - Utility relocation was completed •September 15, 2008 - Council approves phase I •October 2008 - Construction starts • February 2009 - Foundation is poured •April 2009 - Beaming signing and steel structure started •August 24, 2009 - Interior completed for the first day of school •August 28, 2009 - Ribbon cutting ceremony Project Cost •CM @ Risk $4,115,221 •Town Soft cost $1,074,168 •Total $5,189,389 CM cost include - Construction management fee, site work, concrete, steel, interior and exterior finishes Soft cost include- Design, engineering, legal, utility relocation, low voltage package and FF & E YTD Cost Contract CM @ Risk $4,155,221 Amount paid $3,590,712 Balances $564,509 Soft cost $1,034,168 Amount Paid $930,279 Balances $103,889 Total balances to be paid $668,398 Total Project Funding Sources G.O. Bond Funds $2,500,000 Texas Student Housing $500,000 Lee Gift $500,000 Interest $64,666 Westlake Academy $200,000 Miscellaneous $460 Utility Funding $6,250 Remain of utility Relocation(Town) $3,666 Sub Total $3,775,042 Westlake Academy Foundation Two payments $847,559 Cash-($201,084) $270,685 Outstanding Pledges $284,319 Unfunded amount $11,784 Sub Total $1,414,347 Total Project Cost $5,189,389 Contingency Balance •Owner betterment balance $35,045 Project enchantments - Three add alternates, (A) Stain & polish floors, (B)two wooden beams, (C)wall covering, data and power drops, Lighting controls, sidewalks, pier casing, TVSS system and Sod •Contractor estimated Contingency balance $355,000 Credits – Phase two slab, wood doors, signage, vapor barrier, landscape maintenance contract •Dose not include two additional retaining walls and the FRP at the eyewash stations Expenditures to Estimated Cost Savings Remaining balance $668,398 Soft cost balance (Invoices) ($103,889) CM balance (Invoices) ($174,464) Retain wall, White board in ( $40,000) conference room, FRP eyewash etc Billing reductions ($150,000) YTD credit balance $200,045 Key Decision Points Where does the credit get applied? •Project enhancement, –Covered walkway $350,000 –Parking area $250,000 –Weather station $12,000 –Stage $10,000 •Cover long term pledge commitments from the Foundation •$2.5M Debt service (Bond payment)