Loading...
HomeMy WebLinkAboutFinal Arts and Science Center update Project Description: CAPITAL PROJECT FUNDING Actual Thru Project Project 09/31/2009 Total Total Revenues G.O. Bond 2,500,000$ 2,500,000$ -$ -$ -$ 2,500,000$ Lee Gift 500,000 500,000 - - - 500,000 Texas Student Housing 500,000 500,000 - - - 500,000 Interest 64,666 64,666 64,666 Miscellaneous 460 460 460 Classroom Operating Supplies Westlake Academy 08-09 budget $31K - - Westlake Academy Funds FF & E 50,000 - - - 50,000 FF & E Funded by Westlake Academy 200,000 150,000 - - - 150,000 Utility Relocation - - - - - - Utility relocation by utility fund 6,250 9,916 - - - 9,916 Westlake Academy Foundation - - - - - Utility relocation by Foundation 201,084 - - Cash receipts at 8.22.09 - 1,118,244 - - - 1,118,244 Two Payments 847,559 - Pledges $285,669 at 8.22.09 - 285,669 - - - 285,669 Unfunded amount 10,434 10,434 PROJECT FUNDING TOTAL 4,820,019$ 5,189,389$ -$ -$ -$ 5,189,389$ CAPITAL PROJECT EXPENDITURES Actual Thru Project Budget 09/30/09 Budget Total Construction CM 3,590,712$ 4,115,000$ -$ -$ -$ 4,115,000$ Design 371,382 360,000 - - - 360,000 Engineering/Legal/ Bond fees/Low voltage 193,829 303,389 303,389 FF & E Furniture 119,117 160,000 160,000 FF & E Classroom Supplies 38,617 40,000 - - - 40,000 Utility relocation 207,334 211,000 - - - 211,000 PROJECT EXPENDITURE TOTAL 4,520,991$ 5,189,389$ -$ -$ -$ 5,189,389$ YTD Project Cost & Credits Projected Project Budget 09/30/09 Budget Option 1 Option 2 Option 3 Total Contract CM @ Risk 3,590,712$ 4,155,221$ -$ -$ -$ 4,155,221$ Soft Cost 930,279 1,034,168 - - - 1,034,168 Total 4,520,991$ 5,189,389$ -$ -$ -$ 5,189,389$ Current Balance of Soft Cost 103,889$ Payment of outstanding invoices (103,889) Balance of Soft Cost -$ Contract CM @ Risk Contract CM Outstanding Invoices 174,464$ Owner Betterment 35,045 209,000 209,000 Construction Contingency 355,000 82,000 82,000 Balance of CM @ Risk Contact 564,509 Payment of outstanding invoices (174,464) Retaining wall, FRP, Conference room wall (40,000) Estimated billing reductions (150,000) Total cost saving 200,045$ Savings Options 200,045 200,045 200,045 Pledge to be collected 10,434 - - Payment to debt service 189,611 200,045 - Enhancement to the project - - 200,045 TOTAL - - - Project Update Report Unexpended Funds Option Change Order Project include two science labs, lobby, art room which is approximately 8,400 square feet. Cost to construction is $4.1M and soft cost is $1M; total cost of the project is $5.1M. Sam & Margaret Lee Arts and Sciences Center Project Description: CAPITAL PROJECT FUNDING Actual Thru Project 09/31/2009 Total Balance Revenues G.O. Bond 2,500,000$ 2,500,000$ -$ Lee Gift 500,000 500,000 - Texas Student Housing 500,000 500,000 - Interest 64,666 64,666 - Miscellaneous 460 460 - Classroom Operating Supplies Westlake Academy 08-09 budget $31K - - - Westlake Academy Funds FF & E 50,000 (50,000) FF & E Funded by Westlake Academy 200,000 150,000 50,000 Utility Relocation Utility relocation by Utility Fund 6,250 9,916 (3,666) Westlake Academy Foundation Utility relocation - A&S Portion 201,084 - 201,084 Two Payments made by WAF 847,559 847,559 WAF Capital Campaign receipts - 1,118,244 (1,118,244) Remaining CC cash balance - $270,685 - WAF Outstanding Pledges 8.22.09 - 284,319 (284,319) Unfunded amount 11,784 (11,784) PROJECT FUNDING TOTAL 4,820,019$ 5,189,389$ (369,370)$ CAPITAL PROJECT EXPENDITURES Actual Thru Project 09/30/09 Budget Balance Construction CM 3,590,712$ 4,115,000$ 524,288$ Design 371,382 360,000 (11,382) Engineering/Legal/ Bond fees/Low voltage 193,829 303,389 109,560 FF & E Furniture 119,117 160,000 40,883 FF & E Classroom Supplies 38,617 40,000 1,383 Utility relocation 207,334 211,000 3,666 PROJECT EXPENDITURE TOTAL 4,520,991$ 5,189,389$ 668,398$ YTD Project Cost & Credits Projected Project Remaining 09/30/09 Budget Option 1 Option 2 Option 3 Balance Contract CM @ Risk 3,590,712$ 4,155,221$ 564,509$ Soft Cost 930,279 1,034,168 103,889 Total 4,520,991$ 5,189,389$ 668,398$ Current Balance of Soft Cost 103,889$ Payment of outstanding invoices (103,889) Ending Balance of Soft Cost -$ Contract CM @ Risk Contract CM Outstanding Invoices 174,464$ Owner Betterment 35,045 209,000 Construction Contingency 355,000 82,000 Balance of CM @ Risk Contact 564,509 Payment of outstanding invoices (174,464) Retaining wall, FRP, Conference room wall (40,000) Estimated billing reductions (150,000) Total cost saving 200,045$ Savings Options 200,045$ 200,045$ 200,045$ Unfunded Amount 11,784 - - Payment to debt service 188,261 200,045 - Enhancement to the project - - 200,045 TOTAL - - - Unexpended Funds Option Project include two science labs, lobby, art room which is approximately 8,400 square feet. Cost to construction is $4.1M and soft cost is $1M; total cost of the project is $5.1M. Sam and Margaret Lee Arts & Sciences Center