HomeMy WebLinkAboutWestlake Academy Phase I Expansion presentationTown Council Workshop June 16, 2014 Secondary West Secondary East Secondary Classroom Secondary Restrooms Secondary Multi Purpose Hall Multi Purpose Hall Multi Purpose Hall Field House West Parking Area Project Update Secondary Building -06-18 Complete Stonework -06-18 Complete Roofing -06-16 Plumbing Fixtures -06-16 Hall Tile -06-23 Ceiling Tile -07-01 Doors and Hardware -07-01 Floor Finishes -07-15 Forbo -07-24 Final Cleaning Field House -06-14 EIFS -06-21 Mechanical Units -07-01 Interior Painting -07-20 Flooring -07-30 Final Cleaning Multipurpose Hall 06-16 Quarry Tile -06-23 Millwork -06-30 Ceiling Tile -07-10 Kitchen Equipment -07-17 Flooring -07-24 Final Cleaning Note 06-23 16 PYP classroom move 06-30 West Parking Lot Completed 07-28 Furniture scheduled to be delivered 08-04 13 MYP classrooms and 10 staff members move into new space