HomeMy WebLinkAboutWestlake Academy Phase I Expansion presentationTown Council Workshop
June 16, 2014
Secondary West
Secondary East
Secondary Classroom
Secondary Restrooms
Secondary
Multi Purpose Hall
Multi Purpose Hall
Multi Purpose Hall
Field House
West Parking Area
Project Update
Secondary Building
-06-18 Complete Stonework
-06-18 Complete Roofing
-06-16 Plumbing Fixtures
-06-16 Hall Tile
-06-23 Ceiling Tile
-07-01 Doors and Hardware
-07-01 Floor Finishes
-07-15 Forbo
-07-24 Final Cleaning
Field House
-06-14 EIFS
-06-21 Mechanical Units
-07-01 Interior Painting
-07-20 Flooring
-07-30 Final Cleaning
Multipurpose Hall
06-16 Quarry Tile
-06-23 Millwork
-06-30 Ceiling Tile
-07-10 Kitchen Equipment
-07-17 Flooring
-07-24 Final Cleaning
Note
06-23 16 PYP classroom move
06-30 West Parking Lot Completed
07-28 Furniture scheduled to be delivered
08-04 13 MYP classrooms and 10 staff members move into new space