HomeMy WebLinkAboutWestlake Academy Phase I Expansion presentationTown Council Workshop
May 12, 2014
ADA Sidewalk
Budget Review
YTD Contingency
Owner Betterment ($45,849)
Construction $85,244
Town $40,000
Utilities & appliance $30,000
ADA sidewalks $85,000
•Dirt Work $10,000
•Town Contingency $40,000
•Construction $30,000
South Side - Secondary
Secondary
Multi Purpose Hall
Multi Purpose Hall
Field House
Field House
Staff Recommendation
Staff recommends that the Council
authorize the Town Manager to approve
the change order in the amount of
$85,000.00 for the additional routes
necessary to comply with the Americans
with Disabilities Act routes in Phase One of
the Westlake Academy campus expansion
project