HomeMy WebLinkAboutWestlake Academy Phase I Expansion presentationTown Council Workshop
January 27, 2014
Multi Purpose Hall
Multi Purpose Hall
Multi Purpose Hall Today
Secondary Building
Project Update
January
Place Multipurpose slab
Complete grade beams Field House
Continue structural steel Secondary Building
Complete decking levels 1, 2 and 3 Secondary Building
Complete steel Multipurpose Hall
February
Top out Secondary Building
Third floor slab Secondary Building
Exterior walls/roof deck
Duct work & fire system
Place slab on Field House
Structural steel Field House
FF & E package go out for bid
March
Secondary Building
Interior walls
TC approves FF & E package
Note:
Weather Delays – Three weeks
Budget Update Saving
Portable Buildings $6,582.00
Pier /Casing Savings $58,928.00
Kitchen equipment Savings $25,000.00
Total saving $90,510.00
FF & E Package due in February
Approved by the TC on March 3rd