Loading...
HomeMy WebLinkAboutWestlake Academy Phase I Expansion presentationTown Council Workshop January 27, 2014 Multi Purpose Hall Multi Purpose Hall Multi Purpose Hall Today Secondary Building Project Update January Place Multipurpose slab Complete grade beams Field House Continue structural steel Secondary Building Complete decking levels 1, 2 and 3 Secondary Building Complete steel Multipurpose Hall February Top out Secondary Building Third floor slab Secondary Building Exterior walls/roof deck Duct work & fire system Place slab on Field House Structural steel Field House FF & E package go out for bid March Secondary Building Interior walls TC approves FF & E package Note: Weather Delays – Three weeks Budget Update Saving Portable Buildings $6,582.00 Pier /Casing Savings $58,928.00 Kitchen equipment Savings $25,000.00 Total saving $90,510.00 FF & E Package due in February Approved by the TC on March 3rd