HomeMy WebLinkAboutWA Phase I Expansion presentationTown Council Workshop
February 24, 2014
Field House
Multi Purpose Hall
Secondary Building
Multi Purpose Hall Today
Secondary Building
Project Update
February
Completed Multipurpose Hall slab
Completed slab on Field House
Completed structural steel Secondary Building
Completed exterior framing on level 1 & 2 Secondary Building
Completed steel Multipurpose Hall
Start exterior framing on Multipurpose Hall
Start CMU load bearing walls
March
Top out Secondary Building
Exterior walls/roof decks all three buildings
Duct work & fire system
Roof framing on Multipurpose Hall
Structural steel & roof Field House
Full FF & E package at March 3rd BOT
April
Secondary Building HVAC systems
Structural steel & roof Field House
Note:
Weather Delays – Three weeks
Pricing on west parking area, amend GMP
Multi Purpose Hall