HomeMy WebLinkAboutWestlake Academy Phase I Expansion presentationTown Council Workshop April 28, 2014 Project Update April Secondary Building Windows Completed Drywall finishing Field House CMU load bearing walls and Steele trusses Multipurpose Hall  Windows Completed  Roofing Completed May Secondary Building  Ceiling Grid Power / Start HVAC  EIFS, and Stone Field House Steel Trusses Roofing Power /HVAC Units Multipurpose Hall Drywall EIFS and Stone Power June  Secondary Building Ceramic tile Multipurpose Hall Ceiling Grid Field House Stone Parking Lot starts South Side - Secondary 1st Floor - Secondary 2nd Floor - Secondary 3 Floor - Secondary Roof - Secondary Multi Purpose Hall Multi Purpose Hall Field House Amending GMP Amending GMP by a $200,000 increase $8,631,439.18 2013-2014 west parking improvement capital project funds would be moved to the Westlake Academy Phase I expansion fund in the capital project budget. West Parking Improvements ADA Sidewalk Budget Review YTD Contingency Owner Betterment ($45,849) Construction $85,244 Town $40,000 Utilities & appliance $30,000 ADA sidewalks $85,000 •Dirt Work $10,000 •Town Contingency $40,000 •Construction $30,000 Staff Recommendation Staff recommends that the Council authorize the Town Manager to amend the guaranteed maximum price (GMP) by $200,000.