April 28, 2014
Project Update
April
Secondary Building
Windows Completed
Drywall finishing
Field House
CMU load bearing walls and Steele trusses
Multipurpose Hall
Windows Completed
Roofing Completed
May
Secondary Building
Ceiling Grid
Power / Start HVAC
EIFS, and Stone
Field House
Steel Trusses
Roofing
Power /HVAC Units
Multipurpose Hall
Drywall
EIFS and Stone
Power
June
Secondary Building
Ceramic tile
Multipurpose Hall
Ceiling Grid
Field House
Stone
Parking Lot starts
South Side - Secondary
1st Floor - Secondary
2nd Floor - Secondary
3 Floor - Secondary
Roof - Secondary
Multi Purpose Hall
Multi Purpose Hall
Field House
Amending GMP
Amending GMP by a $200,000 increase
$8,631,439.18
2013-2014 west parking improvement
capital project funds would be moved to
the Westlake Academy Phase I
expansion fund in the capital project
budget.
West Parking Improvements
ADA Sidewalk
Budget Review
YTD Contingency
Owner Betterment ($45,849)
Construction $85,244
Town $40,000
Utilities & appliance $30,000
ADA sidewalks $85,000
•Dirt Work $10,000
•Town Contingency $40,000
•Construction $30,000
Staff Recommendation
Staff recommends that the Council
authorize the Town Manager to amend
the guaranteed maximum price (GMP)
by $200,000.