Project Goals
Increase dining space
Increase in student enrollment- classroom
PYP gym space
Open the Secondary & Multi Purpose by
August 21, 2014
Followed by the Field House in September
2014
Secondary
Secondary
Secondary
Secondary
Secondary
Multi Purpose Hall
Multi Purpose Hall
Multi Purpose Hall
Field House
West Parking Area
Site Work
Project Update
Secondary Building
o Teachers & staff move in
o Student desk furniture arrived
o Fire Marshall inspections final by Thursday
o Restrooms, sidewalks, wall finishes , student desks, phones, AV equipment
Multipurpose Hall
o Restrooms
o Fire Marshall & Health inspection completed by Friday on Kitchen Equipment
o Painting Floor August 30th
Field House Project
o HVAC system turned on
o Interior walls 98% complete
o Painting
o Flooring completed by August 18th
o Weight equipment arrives August 29th
o Building opens on September 15th
West Parking Lot
Landscaping and lighting
Site Work
o Sidewalks completed at the SS and MPH
o Over all site clean up
Note: Full budget update on August 25th TC Work shop Meeting