HomeMy WebLinkAboutWestlake Academy Phase I Expansion presentationTown Council Workshop
March 24, 2014
Multi Purpose Hall
Field House
Secondary Building
Project Update
March
Secondary School Building
Windows
Field House
CMU load bearing walls and doors
Multipurpose Hall
Windows
Roofing
April
Secondary Building
Roofing, and Mechanical Units
Sheetrock
EIFS, and Stone
Field House
Steel Trusses
Multipurpose Hall
Sheetrock
EIFS and Stone
Mechanical Units
May
Secondary Building
Drywall Finishing
Ceiling Grid
Multipurpose Hall
Drywall Finishing and Ceiling Grid
Field House
EIFS
Roofing and Mechanical Units
IT & Security Budget
Total Low Voltage package $454,204
Short fall ($123,728)
Owner Betterment YTD $111,490
Total ($12,238)
Amending GMP
GMP was approved in August 2013
$8,578,694.00
Amending GPM to $8,467,204.00 by
decreasing the owners betterment by
$111,490.00 to cover the IT/Security
Fund moved to the IT & Security line
item
Staff Recommendation
Use Owners Betterment $111,490.00 to
cover the IT/Security budget of
$454,204.00
IT & Security Budget
Total Low Voltage package $454,204
Short fall ($123,728)
Owner Betterment YTD $111,490
Total ($12,238)
Furniture, Fixture and
Equipment Package
Package includes;
Classroom and office furniture
Athletic equipment
•Security system and equipment
•Communication equipment
•Audiovisual equipment
•Moving in costs
•Miscellaneous items, trash can, AED, start up
work room supplies, clocks and shelving
Total FF & E budget $1,001,685.
Bid Results
Furniture
Business Interiors $310,400
Alpha Fitness $118,780 ($58,780)
Total $429,180
Note: Short Fall of the athletic equipment covered by WA affiliates and or
interested parties to cover this cost increase.
Convergint Tech - $121,754
AVI $144,150
Synetra $188,300
Total $454,204
Short fall ($123,728)
Owner Betterment YTD $111,490
Total ($12,238)